Application Timeline
Application received
27 Oct 2005
Decision: CONDITIONAL
29 May 2006
Decision due
30 May 2006
Grant issued
4 Jul 2006
Application Details
- Location
- Knockpoge Waterfall
- Applicant
- N/A
- Application Type
- APPROVAL
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 27 October 2005
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 29 May 2006
- Grant Date
- 4 July 2006
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Construct a detached single storey garage.
Knockpoge Waterfall Co. Cork
Dwellinghouse
Ballyhank Waterfall
2 no. pre-fabricated buildings for use as office and canteen and toilet
Knockpoge Waterfall
Retention of the following structures/facilities: (a) Waste and recovery station building (change of plan from that permitted under planning reg. no. 01/384), (b) Prefabricated structures - office, canteen, toilet, tool store and hut for CCTV camera, (c) Workshop for servicing vehicles, (d) Open area (adjoining the western gable of the waste transfer building) containing plant/equipment (soil/stone separator), (e) Truck wash and bunded fuel tank and (f) Temporary facility for trucks, skips, cars, etc.
Knockpoge Waterfall Co Cork
Retention of the following structures/facilities: [a] material change in the construction of waste transfer station to structure permitted under planning reg. no. 01/384, [b] pre-fabricated structures - offices, canteen, toilet, tool store and hut for CCTV camera, [c] workshop for servicing vehicles, [d] open area (adjoining the western gable of the waste transfer building) containing plant/equipment (soil/stone separator) and [e] temporary facility for trucks, skips, cars etc. (the application relates to development which si for the purposes of an activity requiring a waste licence)
Knockpoge Waterfall
Permission to construct a lean-to roof structure over storage bays used to store materials, all associated with the existing waste recovery facility
Knockpoge Waterfall Co.Cork
Construction of detached single storey pre-fabricated office/toilet unit to serve existing waste recovery facility
Knockpoge Waterfall Co.Cork
Increase in existing waste tonnages from 23,000 tonnes per annum to 60,000 tonnes
Knockpoge Waterfall
Increase of waste tonnages processed at existing facility from 23,000 tonnes to 60,000 tonnes per annum
Knockpoge Waterfall
Increase of waste tonnages processed at existing facility from 23,000 tonnes to 60,000 tonnes per annum
Knockpoge Waterfall