Proposed Development
Construction of 1 no. warehouse building comprising of 3 no. individual warehouse units with associated office areas, provision for 85 no. car spaces, 2 no. site entrances and associated site works
Application Timeline
Application received
26 Sept 2006
Decision: CONDITIONAL
5 Mar 2007
Decision due
6 Mar 2007
Grant issued
10 Apr 2007
Application Details
- Location
- Courtstown Little Island
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 26 September 2006
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 5 March 2007
- Grant Date
- 10 April 2007
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Construction of two storey extension to ancillary office space at existing warehouse building, palisade fencing to the side (south east) and rear (north east) boundaries of site, new security gates to existing entrances, new exit to existing roadway from new extended hardstanding area, new signage to elevations of warehouse building, landscaping and associated site works
Courtstown Business Park Courtstown Little Island
Retention of 1 no. ESB substation and associated site works
Courtstown Little Island
We, Inver Energy Limited, wish to apply for full planning permission for the following proposed works: 1) construct new site entrance; 2) install new unmanned overground fuel dispensing unit; 3) erect new ID sign; and 4) all associated site works at site located at Harbour Point Business Park, Little Island, Co. Cork.
Harbour Point Business Park, Little Island, Co. Cork
The construction of a Portakabin site office and meeting room totaling 195 sqm gross floor area and use of land as open storage and refurbishment of Portakabin buildings for use off-site placed up to two units high on the northern and western sections of the site and extending up to 7.48m above ground level together with all ancillary development. Access is to be taken from the existing access point on the southern corner of the site. Utilities and services are to be brought to the site office on the south-eastern side of the site. The compound will be secured by way of a 2.4m high galvanised fence.
Site 4 Harbour Point Business Park Courtstown Little Island Cork
The construction of a Portakabin site office and meeting room totalling 195 sq m gross floor area and use of the land as open storage of Portakabin buildings placed up to two units high on the northern and western sections of the site and extending up to 7.48m above ground level together with all ancillary development. Access is to be taken from the existing access point on the southern corner of the site. Utilities and Services are to be brought to the site office on the south-eastern side of the site. The compound will be secured by way of a 2.4m high galvanised fence.
Site 4 Harbour Point Business Park Courtstown Little Island Cork
A detached two storey house and all associated site works
4 Lower Courtstown Little Island Co. Cork
The construction of two strategic logistical, storage and distribution warehouse units, incorporating office accommodation, 2No. bicycle shelters, Associated site signage (4No. 1.8m high totem signs), adjusted site entrance access off existing estates road, site levelling and contouring, 2No. waste compactors, truck loading, hardstanding and truck parking bay areas, 66No. car parking spaces of which includes, 4No. disabled spaces, and 4No. electric charging spaces, and all other ancillary and associated site development works including landscaping.
Harbour Point Business Park Courtstown Little Island Co. Cork
The construction of 2 no. Strategic Logistical, storage and distribution warehouse units, incorporating office accommodation, 2 no. bicycle shelters, associated site signage (4 no. 1.8m high totem signs), adjusted site entrance access off existing Estates Road, site levelling and contouring, 2no. waste compactors, truck loading, hardstanding and truck parking bay areas, 66 no. car parking spaces of which include, 4 no. disabled spaces, and 4 no. electric charging spaces, and all other ancillary and associated site development works including landscaping. A Natura Impact Statement will be submitted to the planning authority with the application.
Harbour Point Business Park Courtstown Little Island Co. Cork
Alterations and extension to permitted Phase 2 building and retention of alterations to Phase 1 building to include removal of level entry door, revisions to service yard levels, alterations to 2 no. permitted level entry doors to dock leveller, relocation of retaining wall and retention of glazed screen on Southern elevation
Courtstown Ind. Est. Courtstown Little Island
Construction of extension to warehouse building permitted under Reg. No.03/3104 to include mezzanine areas for ancillary office use and storage, retention of alterations to permitted building to include removal of level entry door, revisions to service yard levels, alterations to 2 no. permitted level entry doors to dock leveller, relocation of retaining wall on southern elevation of building and retention of glazed screens in western elevation and installation of mezzanine area for ancillary storage use, associated car parking (208 spaces). landscaping and ancillary works
Courtstown Ind. Est. Courtstown Little Island
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?