Coomatallin Drinagh

REFUSED

Planning application 07/1136

Cork - Cork County Council

Proposed Development

Dwelling, domestic garage and associated site works

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    30 Apr 2007

  2. Decision due

    24 Jun 2007

  3. Decision: REFUSED

    25 Jun 2007

Application Details

Location
Coomatallin Drinagh
Applicant
N/A
Application Type
OUTLINE PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
30 April 2007
Status
APPLICATION FINALISED
Decision
REFUSED
Decision Date
25 June 2007

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

452m
12/436CONDITIONAL4 Jul 2012

Construction of a two turbine extension to an existing four turbine wind farm at the townlands of Coomatallin, Kippagh and The Pike near Drinagh, Co. Cork. The maximum hub height will be 65m and the maximum rotor diameter will be 82.5m resulting in a maximum tip height of 106.25m. The associated works will include turbine foundations and hardstanding, transformers, access track, drainage and an extension to the existing substation

Townlands of Coomatallin, Kippagh and The Pike, Drinagh, Co. Cork

594m
06/960UNCONDITIONAL25 May 2006

Windfarm consisting of 7no. wind turbines, meteorological mast (50m high), electrical sub-station, control building, upgrading entrance and ancillary works

Coomatalin Kippagh Drinagh

594m
00/6380CONDITIONAL24 Oct 2000

Windfarm consisting of 7 no. wind turbines,meteorological mast(50m high),electrical sub- station,control building,up- grading entrance & anc. works

COOMATALLIN, COOMATALLIN,

623m
25/6057Grant with Conditions29 Sept 2025

The development will consist of: The extension of the operational duration of the existing Coomatallin Wind Farm and associated infrastructure (as permitted pursuant to Cork County Council Planning Register Reference 00/6380) for a further period of 20 years from the date of the expiry of its current operational duration. No changes are proposed to the number or dimensions of the existing permitted wind turbines. The existing wind farm comprises: (i) 4 no. wind turbines; (ii) associated turbine foundations and crane hardstandings; (iii) 2 no. site entrances, from the L8586 and L8299 public roads respectively; (iv) approximately 2.4 kilometres (km) of on-site access tracks; (v) a 20 kilovolt (kV) electrical substation and control building with a gross floor area of 74 square metres and associated electrical apparatus; (vi) underground electrical and communications cabling; and (vii) a meteorological mast with a total height of 60 metres (m). The development provides for the installation of an aviation warning light on turbine T4. This planning application is accompanied by an Environmental Impact Assessment Report and Natura Impact Statement which includes an assessment of the likely significant effects of the development; both individually and in combination with the relevant off-site or secondary developments which will occur as a direct result of the development, including the development' s existing grid connection infrastructure which comprises approximately 160m of 20kV underground electricity line and approximately 8km of 20kV overhead electricity line located within the townlands of Kippagh, Coomatallin, The Pike, Drinagh East, Lisbealad East, Lisbealad West, Kilronane West, Kilronane East, Milleenanannig, Nedinagh West and Ballyhalwick, County Cork. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning And Development Regulations 2001 to 2025 shall apply. The planning application, Environmental Impact Assessment Report and Natura Impact Statement may be inspected, or purchased at a fee not exceeding the reasonable cost of making a copy, at the offices of the planning authority during its public opening hours. A submission or observation in relation to the application may be made in writing to the planning authority on payment of the prescribed fee, €20, within the period of - (a) 5 weeks or (b) 2 weeks, in the case of a planning application for small-scale solar energy equipment development or development that is the installation of a small-scale non-ground source heat pump, beginning on the date of receipt by the authority of the application, and such submissions or observations will be considered by the planning authority in making a decision on the application. The planning authority may grant permission subject to or without conditions, or may refuse to grant permission.

Coomatallin Windfarm (ROI) Limited, Coomatallin and Kippagh, Drinagh, Co. Cork

650m
00/6382CONDITIONAL24 Oct 2000

Construction of a 50m high monitoring mast for wind measurement purposes

COOMATALLIN, COOMATALLIN,

734m
06/2030CONDITIONAL5 Oct 2006

Detached dwelling ancillary to main dwelinghouse

Carrigfadda Reenacreena

770m
17/215CONDITIONAL13 Apr 2017

Demolition of an existing agricultural outhouse, the construction of a dwelling house, the installation of a septic tank with percolation area and all associated site works

Coomatallin Drinagh Co Cork

770m
17/158INCOMPLETED APPLICATION16 Mar 2017

The demolition of an existing agricultural outhouse, the construction of a dwellinghouse, the installation of a septic tank with percolation area and all associated work

Coomatallin Drinagh Co. Cork

918m
05/4692REFUSED1 Jul 2005

Dwellinghouse and garage

Carrigfadda Rosscarbery

952m
03/2390WITHDRAWN20 May 2003

Dwellinghouse with conservatory

COOMATALLIN, COOMATALLIN,

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?