← Back to search

Townlands of Coomatallin, Kippagh and The Pike, Drinagh, Co. Cork

CONDITIONAL

Planning application 12/436

Cork - Cork County Council

Proposed Development

Construction of a two turbine extension to an existing four turbine wind farm at the townlands of Coomatallin, Kippagh and The Pike near Drinagh, Co. Cork. The maximum hub height will be 65m and the maximum rotor diameter will be 82.5m resulting in a maximum tip height of 106.25m. The associated works will include turbine foundations and hardstanding, transformers, access track, drainage and an extension to the existing substation

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    4 Jul 2012

  2. Decision: CONDITIONAL

    22 Aug 2012

  3. Decision due

    28 Aug 2012

  4. Grant issued

    27 Sept 2012

Application Details

Location
Townlands of Coomatallin, Kippagh and The Pike, Drinagh, Co. Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
4 July 2012
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
22 August 2012
Grant Date
27 September 2012

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

221m
06/960UNCONDITIONAL25 May 2006

Windfarm consisting of 7no. wind turbines, meteorological mast (50m high), electrical sub-station, control building, upgrading entrance and ancillary works

Coomatalin Kippagh Drinagh

221m
00/6380CONDITIONAL24 Oct 2000

Windfarm consisting of 7 no. wind turbines,meteorological mast(50m high),electrical sub- station,control building,up- grading entrance & anc. works

COOMATALLIN, COOMATALLIN,

274m
00/6382CONDITIONAL24 Oct 2000

Construction of a 50m high monitoring mast for wind measurement purposes

COOMATALLIN, COOMATALLIN,

295m
25/6057Grant with Conditions29 Sept 2025

The development will consist of: The extension of the operational duration of the existing Coomatallin Wind Farm and associated infrastructure (as permitted pursuant to Cork County Council Planning Register Reference 00/6380) for a further period of 20 years from the date of the expiry of its current operational duration. No changes are proposed to the number or dimensions of the existing permitted wind turbines. The existing wind farm comprises: (i) 4 no. wind turbines; (ii) associated turbine foundations and crane hardstandings; (iii) 2 no. site entrances, from the L8586 and L8299 public roads respectively; (iv) approximately 2.4 kilometres (km) of on-site access tracks; (v) a 20 kilovolt (kV) electrical substation and control building with a gross floor area of 74 square metres and associated electrical apparatus; (vi) underground electrical and communications cabling; and (vii) a meteorological mast with a total height of 60 metres (m). The development provides for the installation of an aviation warning light on turbine T4. This planning application is accompanied by an Environmental Impact Assessment Report and Natura Impact Statement which includes an assessment of the likely significant effects of the development; both individually and in combination with the relevant off-site or secondary developments which will occur as a direct result of the development, including the development' s existing grid connection infrastructure which comprises approximately 160m of 20kV underground electricity line and approximately 8km of 20kV overhead electricity line located within the townlands of Kippagh, Coomatallin, The Pike, Drinagh East, Lisbealad East, Lisbealad West, Kilronane West, Kilronane East, Milleenanannig, Nedinagh West and Ballyhalwick, County Cork. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning And Development Regulations 2001 to 2025 shall apply. The planning application, Environmental Impact Assessment Report and Natura Impact Statement may be inspected, or purchased at a fee not exceeding the reasonable cost of making a copy, at the offices of the planning authority during its public opening hours. A submission or observation in relation to the application may be made in writing to the planning authority on payment of the prescribed fee, €20, within the period of - (a) 5 weeks or (b) 2 weeks, in the case of a planning application for small-scale solar energy equipment development or development that is the installation of a small-scale non-ground source heat pump, beginning on the date of receipt by the authority of the application, and such submissions or observations will be considered by the planning authority in making a decision on the application. The planning authority may grant permission subject to or without conditions, or may refuse to grant permission.

Coomatallin Windfarm (ROI) Limited, Coomatallin and Kippagh, Drinagh, Co. Cork

452m
07/1136REFUSED30 Apr 2007

Dwelling, domestic garage and associated site works

Coomatallin Drinagh

662m
16/134CONDITIONAL10 Mar 2016

Change of use of part of an existing farm-holding from agricultural use to religious community use, the completion of the demolition of an existing agricultural outbuilding, the erection of a chapel building encompassing the footprint of said agricultural building, the installation of a wastewater treatment system and car parking facilities and the carrying out all associated works

St. Finbar's Priory Maulatanvally Drinagh Co. Cork

665m
19/27WITHDRAWN21 Jan 2019

A cemetery incorporating an altar with life size crucifix and related statuary, an ancillary car park, a memorial garden, a site entrance area incorporating life size statuary and a notice board and all associated works to serve a religious community

St. Finbar's Priory Maulatanvally Drinagh Co. Cork

692m
15/675CONDITIONAL26 Nov 2015

A single electricity generating wind turbine with a hub height of up to 65m and a rotor diameter of up to 55m, giving an overall tip height not exceeding 92.5m, with associated hardstand area, control building, access track and associated site works at Kippagh, Drinagh, Co. Cork. The planning application is accompanied by an Environmental Report (ER).

Kippagh Drinagh Co Cork

755m
00/4811REFUSED4 Aug 2000

Dwellinghouse

SITE NO. 1, SITE NO. 1, MAULATANVALLY,

761m
00/4810CONDITIONAL4 Aug 2000

Dwellinghouse

SITE NO. 2, SITE NO. 2, MAULATANVALLY,