Proposed Development
Construction of four bay straw bedded sheep shed and associated ancillary works
Application Timeline
Application received
22 Jun 2007
Decision: CONDITIONAL
15 Aug 2007
Decision due
16 Aug 2007
Grant issued
17 Sept 2007
Application Details
- Location
- Ballynaclashy Midleton
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 22 June 2007
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 15 August 2007
- Grant Date
- 17 September 2007
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
To demolish an existing dwellinghouse, erect a dormer type dwellinghouse, install an on-site sewage treatment system, and all associated site development works
Ballynaclashy Midleton Co. Cork
Intend to apply for a 10 year planning permission for proposed development of an underground electricity interconnector cable. The proposed development of the underground electricity interconnector cable will comprise 1 no. 33kV triple circuit cable of c.3.9 Km in length which is to be installed in an excavated trench including underground ducting, joint bays, communication chambers and all associated site development and reinstatement works. The interconnector cable will extend from two newly proposed ring main units at the permitted Ballynaclashy solar farm to an inverter at the permitted Lysaghtstown Solar Farm. The proposed development provides for a revision to part of the approved layout of the Ballynaclashy solar farm previously permitted under Cork County Council planning ref no. 21/4050 & An Bord Pleanála ref ABP 311238-21. The revision to the layout comprises the installation of 2 no. ring mains units and the laying of the underground electricity interconnector cable. The proposed development also provides for a revision to part of the approved layout of Lysaghtstown solar farm as previously permitted under Cork County Council planning ref no. 18/6769 (as amended by references 20/6891 and 21/5089). The revision to this layout comprises the laying of the underground electricity interconnector cable to an already permitted inverter. The development will be carried out within the combination of the above referenced permitted solar farm boundaries, on private lands within the L-7634, L-36172, L-7694 and R626 public roads. A Natura Impact Statement (NIS) has been prepared and will be submitted to the planning authority with the application.
Ballynaclashy Ballyrichard Beg Curragh & Lysaghtstown Co.Cork
Permission for a 10 year planning permission for the proposed development of an underground electricity interconnector cable will comprise of a 33kV double circuit underground cable route, of c.4.3km in length which is to be installed in an excavated trench including underground ducting, joint bays, horizontal directional drills (HDD), communication chambers and all associated site development and reinstatement works. The interconnector cable will extend from two newly proposed ring main units at the permitted Ballynaclashy Solar Farm to a substation at the permitted Lysaghtstown Solar Farm. The proposed development provides for a revision to part of the approved layout of the Ballynaclashy Solar Farm previously permitted under Cork County Council Planning Reference 21/4050 / An Bord Pleanála Reference ABP 311238-21. The revision to the layout comprises the installation of 2 no. ring main units and the laying of the underground electricity interconnector cable. The proposed development also provides for a revision to part of the approved layout of Lysaghtstown Solar Farm as previously permitted under Cork County Council Planning Reference 18/6769 (as amended by references 20/6891 and 21/5089). The revision to this layout comprises the laying of the underground electricity interconnector cable to a substation permitted under An Bord Pleanála Reference ABP 308979-20. The development will be carried out within a combination of the above referenced permitted solar farm boundaries, on private lands and within the L-7634, L-36172, L-7694 and R626 public roads. The underground electricity interconnector cable will be routed around Tomasheen Bridge through private lands via HDD. A Natura Impact Statement (NIS) has been prepared and will be submitted to the Planning Authority with the application.
Ballynaclashy Ballyrichard Beg Curragh and Lysaghtstown Co. Cork
Construction of a two storey dwellinghouse, detached store, domestic wastewater treatment system and raised soil polishing filter, new site entrance with walls and piers and all associated site works
Ballynaclashy Midleton Co. Cork
The proposed development of an underground electricity interconnector cable. The proposed development of the underground electricity interconnector cable will comprise 1 no. 33kV double circuit cable of c.4.3km in length which is to be installed in an excavated trench including underground ducting, joint bays, communication chambers and all associated site development and reinstatement works. The interconnector cable will extend from two newly proposed Ring Main Units at the permitted Ballynaclashy Solar Farm to a substation at the permitted Lysaghtstown Solar Farm. The proposed development provides for a revision to part of the approved layout of the Ballynaclashy Solar Farm previously permitted under Cork County planning reference 21/4050 / An Bord Pleanála reference ABP 311238-21. The revision to the layout comprises the installation of 2 no. Ring Main Units and the laying of the underground electricity interconnector cable. The proposed development also provides for a revision to part of the approved layout of Lysaghtstown solar farm as previously permitted under cork county council planning reference 18/6769 (as amended by references 20/6891 and 21/5089). The revision to this layout comprises the laying of the underground electricity interconnector cable to a substation permitted under an Board Pleanála reference ABP 308979-20. The development will be carried out within a combination of the above referenced permitted solar farm boundaries, on private lands and within the L-7634, L-36172, L-7694 and R626 public roads. A Natura Impact Statement (NIS) has been prepared and will be submitted to the planning Authority with the application.
Ballynaclashy, Ballyrichard Beg, Curragh Lysaghtstown Co.Cork
Dwelling
Ballynaclashy Midleton
planning permission for the importation of inert soil & stone to enable the raising/levelling of an agricultural field to improve the agricultural output of the lands. It is proposed to import and recover inert soil and stone under a waste facility permit, and as a by-product under article 27 of the European Communities (Waste Directive) Regulations 2011 (S.I. No 126 of 2011) to the amount of 114,930 tonnes. Permission is also sought for the construction of a wheel wash, new temporary haul road and temporary widening of existing access off the L3601 Permission is also sought for associated reinstatement landscaping and all associated development works. A Natura Impact Statement has been submitted with the planning appliation.
Ballyedmond, Midleton, Co. Cork
Construction of new dwelling, detached domestic garage, new site entrance and sewage treatment system and all other associated site works
Ballynaclashy Midleton Co.Cork
Retention of agricultural shed for storage of tractors
BALLYNACLASHY, BALLYNACLASHY,
Change of use of existing agricultural shed to agricultural store to include the storage of agricultural machinery, organic fertilisers such as granular fertiliser, sludge fertilisers, biosolids and soil conditioners
Curragh Midleton Co.Cork
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?