Proposed Development
To demolish an existing dwellinghouse, erect a dormer type dwellinghouse, install an on-site sewage treatment system, and all associated site development works
Application Timeline
Application received
20 Oct 2016
Decision: CONDITIONAL
6 Dec 2016
Decision due
14 Dec 2016
Grant issued
20 Jan 2017
Application Details
- Location
- Ballynaclashy Midleton Co. Cork
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 20 October 2016
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 6 December 2016
- Grant Date
- 20 January 2017
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Construction of a two storey dwellinghouse, detached store, domestic wastewater treatment system and raised soil polishing filter, new site entrance with walls and piers and all associated site works
Ballynaclashy Midleton Co. Cork
Dwelling
Ballynaclashy Midleton
Construction of four bay straw bedded sheep shed and associated ancillary works
Ballynaclashy Midleton
Construction of new dwelling, detached domestic garage, new site entrance and sewage treatment system and all other associated site works
Ballynaclashy Midleton Co.Cork
Retention of agricultural shed for storage of tractors
BALLYNACLASHY, BALLYNACLASHY,
Alterations, extension and renovations to existing derelict chalet type dwelling and construct a new vehicular entrance, domestic garage, treatment unit and associated site works
Ballycurrany East Midleton Co. Cork
Permission to 1), carry out modifications and renovations to existing chalet type dwelling, 2) construct a new extension to the rear of the existing chalet type dwelling, 3) construct new entrance, domestic garage, treatment unit and associated site work
Ballycurrany East Midleton Co. Cork
Demolition of existing derelict dwelling and construction of dwelling, entrance, domestic garage, treatment unit and associated site works
Ballycurrany East Midleton Co.Cork
A 10 year planning permission for a solar farm consisting of up to 220,100 m2 of solar panels on ground mounted frames, 13 no. single storey electrical inverter/transformer stations and associated spare equipment container, battery storage container, customer switchgear container, security fencing, satellite communications pole, CCTV, access tracks, upgrades to two existing agricultural field entrances, temporary construction compounds, landscaping and all associated ancillary development works. Construction and operational access will be via the L-7694. The project will connect with and represents an extension to the adjacent solar farm permitted under Planning References 18/6769, 19/5729 and 19/6882. The solar farm will connect to the national grid and will have an operational lifespan of 35 years.
Ballynaclashy and Ballycurrany East Midleton Co. Cork
A 10 year planning permission for a solar farm consisting of up to 220,100 m2 of solar panels on ground mounted frames, 13 no. single storey electrical inverter/transformer stations and associated spare equipment container, battery storage container, customer switchgear container, security fencing, satellite communications pole, CCTV, access tracks, upgrades to two existing agricultural field entrances, temporary construction compounds, landscaping and all associated ancillary development works. Construction and operational access will be via the L-7694. The project will connect with and represents an extension to the adjacent solar farm permitted under Planning References 18/6769, 19/5729 and 19/6882. The solar farm will connect to the national grid and will have an operational lifespan of 35 years.
Ballynaclashy and Ballycurrany East Midleton Co. Cork
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?