Alterations to the existing 110kV Mallow station comprising of the erection of 4 no. steel gantries and the removal of 1 no. steel gantry and associated site works

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    19 Feb 2009

  2. Decision: CONDITIONAL

    9 Apr 2009

  3. Decision due

    15 Apr 2009

  4. Grant issued

    12 May 2009

Application Details

Location
ESB 110kV Electrical Transformer Station Mallow Carrigoon Beg Mallow
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
19 February 2009
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
9 April 2009
Grant Date
12 May 2009

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

25m
10/5517CONDITIONAL21 Jun 2010

Alterations to include a new 38kV GIS module, an extension to the existing control building and associated site works

Carrigoon Beg Mallow

53m
07/7451CONDITIONAL2 May 2007

Alterations to existing 110kV electrical transformer station to include installation of 2 no. 38kV/MV transformers and associated bunding, 1 no. oil/water interceptor and percolation area, 1 no. 38kV Transformer bay to include disconnects, circuit breakers, current transformers and cable sealing ends, new containerised medium voltage building and associated works

Carrigoon Beg Mallow

53m
07/6285INCOMPLETED APPLICATION21 Mar 2007

Alterations to existing ESB electrical transformer station to include installation of 2 no. 38kV/MV transformers and associated bunding, 1 no. oil/water interceptor and percolation area, 2 no. 38kV transformer bays to include disconnects, circuit breaker, voltage transformers, current transformers and surge arrestors, new containerised medium voltage buildings and associated civil works

Carrigoon Beg Mallow

59m
07/11214INCOMPLETED APPLICATION25 Sept 2007

Erection of 36m high free standing lattice communications structure, carrying antennae and communication dishes with a 2.4m high palisade compound to existing Mallow 110kV substation

St. Josephs Rd Carrigoon Beg Mallow

59m
07/10586INCOMPLETED APPLICATION28 Aug 2007

Erection of 36m high free standing lattic communications structure, carrying antennae and communication dishes within a 2.4m high palisade compound to share with other licensed operators at existing ESB Mallow 110kV substation

St. Joseph's Rd Carrigoon Beg Mallow

59m
07/11773WITHDRAWN18 Oct 2007

Erection of 36m high free standing lattice communications structure carrying antennae and communication dishes within a 2.4m high palisade compound at existing Mallow 110kV substation

St. Joseph's Rd Carrigoon Beg Mallow

148m
24/5762Conditional17 Sept 2024

Retention permission for a temporary portacabin including holding tank, which was retained on site used for staff welfare after the construction period, and permission for the demolition of this existing portacabin and construction of a new pre-fabricated portacabin, including holding tank, for use as staff welfare and all associated site works

ESB 110kV Substation St.Josephs Road Carrigoon beg Mallow, Co.Cork

151m
24/5628Application Invalid28 Aug 2024

Retention permission for a temporary portacabin including holding tank, which was retained on site used for staff welfare after the construction period, and permission for the demolition of this existing portacabin and construction of a new pre-fabricated portacabin, including holding tank, for use as staff welfare, and all associated site development works

ESB 110kV Substation, St.Joseph's Road Carrigoon Beg Mallow Co.Cork

151m
24/4894INCOMPLETED APPLICATION17 May 2024

Retention Permission for a temporary portacabin and permission for the demolition of a temporary portacabin and construction of a new pre-fabricated portacabin of 49s.q.m., and all associated site development works.

ESB 110kv Station St. Josephs Road Carrigoon Beg Mallow, Co. Cork

151m
24/5131INCOMPLETED APPLICATION17 Jun 2024

Permission for Retention of a temporary portacabin including holding tank, which was retained on site used for staff welfare after the construction period, and Permission for the demolition of this existing portacabin and construction of a new pre-fabricated portacabin, including holding tank for use as staff welfare and all associated site development works.

ESB 110 kV Substation St. Josephs Road Carrigoon Beg Mallow, Co.Cork