Proposed Development

Construction of new biomass boiler house incorporating a storage bunker

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    15 Sept 2009

  2. Decision due

    9 Nov 2009

  3. Decision: CONDITIONAL

    9 Nov 2009

  4. Grant issued

    10 Dec 2010

Application Details

Location
Depuy (Ireland) Ltd. Loughbeg Ringaskiddy
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
15 September 2009Other applications received that week
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
9 November 2009
Grant Date
10 December 2010

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

50m
20/4200CONDITIONAL6 Feb 2020

a) The demolition of a 107 square metre single storey timber framed structure and cladded canopy within the loading bay area to the north of the existing production facility, b) the construction of 1 no. single storey extension within the loading bay area to the north and 1 no. single storey extension to the north west of the existing production facility and c) all associated modifications and site development works.

Loughbeg Ringaskiddy Co. Cork

97m
11/6527CONDITIONAL2 Dec 2011

Construction of a 222 sq metre single storey extension to the existing open roofed waste storage compound to the north west of the existing manufacturing facility permitted under Pl. Reg. No. 01/4145 increasing the total area for the compound to 422sq metres. The above facility is ancillary to the existing production and plant areas

Loughbeg Ringaskiddy .

97m
11/6483INCOMPLETED APPLICATION25 Nov 2011

Construction of a 222sq metre single storey extension to the existing open roofed waste storage compound to the north west (Planning Reg. No. 01/4145) of the existing manufacturing facility increasing the total area for the compound to 422 sq metres. The above facility is ancillary to the existing production and plant areas

Loughhbeg Ringaskiddy Co. Cork

103m
18/7056CONDITIONAL22 Nov 2018

Installation of a solar photovoltaic (PV) array on the roof of production facility within a site of 0.32ha. The array will consist of c.1825sq.m of PV modules. The proposed PV array will have a maximum generating capacity of c.300kW.

Loughbeg Ringaskiddy Co. Cork

123m
17/7092CONDITIONAL28 Nov 2017

Retention of a 240 square meter two storey structure for office use on the east side of the existing manufacturing facility. The above facility is ancillary to the existing production and plant areas

Loughbeg Ringaskiddy Co. Cork

220m
10/4078INCOMPLETED APPLICATION20 Jan 2010

Retention of a 60metre high meteorological data collection mast at Loughbeg. The period of retention in relation to this application is 2 years

Loughbeg Industrial Estate Loughbeg Ringaskiddy

245m
13/6262CONDITIONAL29 Nov 2013

The construction of a security building at the existing entrance road security barrier and a car park with 202 spaces and associated site works for use ancillary to the existing manufacturing facility

Loughbeg Ringaskiddy

463m
12/5374INCOMPLETED APPLICATION22 Jun 2012

Demolition of the existing administrative building (147m²); the reconstruction and extension of the existing concrete yard to facilitate the provision of a metal shearing machine, control panel tower, conveyor and output stockpile; new non-ferrous processing building with weighbridge (530m²); store (20m²); new administration building (220m²); change of use of part of existing workshop to depollutant bay for End of Life Vehicles (ELVs) (60m²); car storage area (150m²); underground petrol tank; bunded area (41m²); ramp; retaining/devider walls; car parking; lorry parking; new weighbridge; amendments to existing access off the Ringaskiddy Road, including new 8m wide gates; all site development works, including rock removal and earthworks; and new landscaping works and boundary treatment; new drainage works, including 3no. attenuation tanks and 3no. full flow oil interceptors; pump house (3m²); and temporary construction compound including temporary access off the Ringaskiddy Road, temporary administration, security hut, site office, palisade fencing, gate and car parking. The proposed development also requires the removal of condition no. 25 of S/770/90; all on a site of c. 2.4ha

Hammond Lane Metal Company Loughbeg Ringaskiddy Co. Cork

463m
12/5863CONDITIONAL29 Aug 2012

Demolition of the existing administrative building (147m2); the reconstruction and extension of the existing concrete yard to facilitate the provision of a metal shearing machine, control cabin tower, conveyor and output stockpile; new non-ferrous processing building with weighbridge (530m2); store (20m2); new administration building (220m2); change of use of part of existing workshop to depollutant bay for End of Life Vehicles (ELVs) (60m2); covered car storage area for cars awaiting depollution (150m2); underground petrol tank; bunded area (41m2); gas storage compound (uncovered) (92m2); diesel tank bund (3m2); ramp; retaining/divider walls; car parking; lorry parking; new weighbridge; amendments to existing access off the Ringaskiddy Road, including new 8m wide gates; all site development works, including rock removal and earthworks; and new landscaping works and boundary treatment; new drainage works, including 3no. attenuation tanks and 3no. full flow oil interceptors; pump house (3m2); and temporary construction compound including temporary access off the Ringaskiddy Road, temporary administration building, security hut, site office, palisade fencing, gate and car parking. The proposed development also requires the removal of condition no. 26 of S/770/90 to allow raw material scrap in lots of smaller quantities than 10 tonnes to be accepted on site

Hammond Lane Metal Company Loughbeg Ringaskiddy Co. Cork

463m
12/5514INCOMPLETED APPLICATION11 Jul 2012

Demolition of the existing administrative building (147m2); the reconstruction and extension of the existing concrete yard to facilitate the provision of a metal shearing machine, control cabin tower, conveyor and output stockpile; new non-ferrous processing building with weighbridge (530m2); store (20m2); new administration building (220m2); change of use of part of existing workshop to depollutant bay for End of Life Vehicles (ELVs)(60m2); covered car storage area for cars awaiting depollution (150m2); underground petrol tank; bunded area (41m2); gas storage compound (uncovered) (92m2); diesel tank bund (3m2); ramp; retaining/divider walls; car parking; lorry parking; new weighbridge; amendments to existing access off the Ringaskiddy Road, including new 8m wide gates; all site development works, including rock removal and earthworks; and new landscaping works and boundary treatment; new drainage works, including 3no.attenuation tanks and 3no. full flow oil interceptors; pump house (3m2); and temporary construction compound including temporary access off the Ringaskiddy Road, temporary administration building, security hut, site office, palisade fencing, gate and car parking. The proposed development also requires the removal of condition no.26 of S/770/90 to allow raw material scrap in lots of smaller quantities than 10 tonnes to be accepted on site, all on a site of c.24ha

Hammond Lane Metal Company Loughbeg Ringaskiddy Co. Cork