← Back to search

Millwood Littlesilver Bandon Co.Cork

CONDITIONAL

Planning application 10/6077

Cork - Cork County Council

Proposed Development

Demolition of existing conservatory and construction of single storey extension with refurbishments to existing dwelling and all associated works

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    19 Aug 2010

  2. Decision: CONDITIONAL

    12 Oct 2010

  3. Decision due

    13 Oct 2010

  4. Grant issued

    12 Nov 2010

Application Details

Location
Millwood Littlesilver Bandon Co.Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
19 August 2010
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
12 October 2010
Grant Date
12 November 2010

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

37m
05/7946REFUSED28 Oct 2005

Dwellinghouse and garage

Littlesilver Bandon

50m
24/5023CONDITIONAL4 Jun 2024

Permission for the proposed demolitions , extensions and alterations to an existing dwelling, and all associated site works

Littlesilver Bandon Co.Cork

147m
21/4255CONDITIONAL5 Feb 2021

Permission for retention of installation of septic tank and percolation area and permission for retention of domestic storage shed and associated siteworks.

Littlesilver Bandon Co. Cork

189m
25/6877Awaiting F.I. Response19 Dec 2025

EDF Renewables Ireland Limited intend to apply for a 10 Year Permission for development at this site of c. 1.29 ha, located on lands at Littlesilver, Bandon, Co. Cork. The proposed development consists of a battery energy storage system (BESS) facility, which will comprise of rechargeable battery units contained within 28 no. c. 25 ft containers on site; 7 no. MVs units; 1 no. auxiliary transformer; a resistor, reactor and harmonic filter unit; a low voltage (LV) building and a welfare and spares container. The proposed development also involves the diversion of the existing overhead line on site and includes an underground cable, which will connect the BESS facility to the Bandon 110kV substation. The proposed development will include for the demolition and removal of the existing decommissioned wind turbine and associated outbuilding on site. The proposed development also includes the construction of a 38kV substation building with associated compounds and car parking; stock proof fencing and gateways; landscaping; foul water holding tank; rainwater harvesting tank; stone soakaways; piped infrastructure and ducting; retention basin and stone headwall; signage; security fencing; boundary treatments; lighting; CCTV; SUDs; permeable gravel area; upgrading of the existing site entrance with partial hedgerow removal; new access track and upgrading of the existing access track; and all associated site development and excavation works above and below ground. Planning permission is sought for a period of 10 years.

Littlesilver,, Bandon, Co. Cork

198m
25/4837CONDITIONAL2 May 2025

Permission for retention of a single storey steel framed shed, concrete & stone hard standing area and associated site works for purpose of vintage vehicle/machinery storage.

Littlesilver Bandon co.Cork

198m
25/5743Invalid - Case Closed1 Sept 2025

Permission for the construction of proposed single storey steel framed shed and associated site works for the purpose of vintage vehicle and vintage machinery storage at the rear of existing dwelling.

Littlesilver Bandon Co. Cork P72 YV97

198m
25/6008Grant with Conditions23 Sept 2025

Permission for the construction of a single storey steel framed shed and associated site works for the purpose of vintage vehicle and machinery storage, all at the rear of existing dwelling.

Littlesilver, Bandon, Co. Cork, P72YV97

281m
21/5958CONDITIONAL14 Jul 2021

A horticultural enterprise for the production and processing of cut flowers and flower bulbs and will involve the construction of an operations building (1632.41 sq. m), photovoltaic panels (320.00 sq. m), hardstanding and storage area, parking area, wastewater treatment system and soil polishing filter, site entrance and internal access road, water storage tank, site lighting, boundary fencing, landscaping, and all ancillary works.

Littlesilver Bandon Co. Cork

299m
09/4456CONDITIONAL16 Feb 2009

Dwellinghouse & wastewater treatment unit

Mishells Bandon

303m
08/7526REFUSED27 Jun 2008

Dwellinghouse and installation of wastewater treatment unit

Mishells Bandon

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?