A ten year Planning Permission to construct a wind farm. The development will consist of the erection of 6no. wind turbines with ancillary equipment for the generation of electricity, upgrading of relevant access tracks & construction of new access tracks where required, a fenced electrical compound comprising a single-storey control building and substation, transformers, towers & all associated site works. Each wind turbine will have an overall maximum height of 126 metres, comprising a tower of nominally 80-85 metres high, with a diameter of about 4 metres at the base, to which three number blades of 41-45 metres length will be attached together with all other ancillary works.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    28 May 2013

  2. Decision due

    22 Jul 2013

Application Details

Location
Streamhill East & Streamhill West Co.Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
28 May 2013Other applications received that week
Status
INCOMPLETED APPLICATION
Decision
Pending
Decision Due
22 July 2013

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

0m
13/5885CONDITIONAL30 Sept 2013

Permission for wind farm. The development will consist of the erection of 6no.wind turbines with ancillary equipment for the generation of electricity, upgrading of relevant access tracks and construction of new access tracks where required, a fenced electrical compound comprising a single storey control building and substation, transformwers, towers, and all associated site works. Each wind turbine will have an overall maximum height of 126m, comprising a tower of nominally 80-85m high, with a diameter of about 4 metres at the base, to which three blades of 41-45 metres length will be attached together with all other ancillary works.

Streamhill East Streamhill West Doneraile Co.Cork

0m
13/5191INCOMPLETED APPLICATION21 Jun 2013

The development will consist of the erection of 6 wind turbines with ancillary equipment for the generation of electricity, upgrading of relevant access tracks and construction of new access tracks where required, a fenced electrical compound comprising a single-story control building and substation, transformers, towers and all associated site works. Each wind turbine will have an overall maximum height of 126 metres, comprising a tower of nominally 80-85 metres high, with a diameter of about 4 metres at the base, to which 3 blades of 41-45 metres length will be attached together with all other ancillary works.

Streamhill East and Streamhill West Doneraile Co Cork

0m
13/5499INCOMPLETED APPLICATION1 Aug 2013

The development will consist of the erection of 6no. wind turbines with ancillary equipment for the generation of electricity, upgrading of relevant access tracks & construction of new access tracks where required, a fenced electrical compound comprising a single storey control building and substation, transformers, towers and all associated site works. Each wind turbine will have an overall maximum height of 126 metres, comprising a tower of nominally 80-85 metres high, with a diameter of about 4 metres at the base, to which three blades of 41-45 metres length will be attached together with all other ancillary works.

Streamhill East Streamhill West Doneraile Co.Cork

269m
17/7128INCOMPLETED APPLICATION30 Nov 2017

1x 80m permanent meteorological mast to be erected for the purpose of collecting meteorological data. The Meteorological mast is a lattice structure of 80m height that will be fixed to ground anchors by guy wires.

Streamhill East Ballyhoura Doneraile Co. Cork

269m
17/7356CONDITIONAL20 Dec 2017

Erection of a 1 x 80m permanent meteorological mast for the purpose of collecting meteorological data. The meteorological mast is a lattice structure of 80m height that will be fixed to ground anchors by guy wires.

Streamhill East Ballyhoura Doneraile Co.Cork

1.0km
15/4155CONDITIONAL29 Jan 2015

Permission for minor modifications to the previously approved Buttevant Wind Farm development comprising 6 no. wind turbines (Planning Ref. No. 13/5885). The development will consist of an increase in the maximum overall dimensions of the 6 no. permitted wind turbines (from 126m to 135m) alterations to the permitted site boundaries resulting in a reduction in site area and omission of permitted southern access to site and all associated site works above and below ground

Streamhill East & Streamhill West Doneraile

1.0km
15/4019INCOMPLETED APPLICATION8 Jan 2015

Minor modifications to the previously approved Buttevant Wind Farm development comprising 6no. wind turbines (Planning Ref. No. 13/5885). The development will consist of an increase in the maximum overall dimensions of the 6no. permitted wind turbines (from 126m to 135m) and all associated site works above & below ground.

Streamhill East & Streamhill West Doneraile Co.Cork

1.3km
03/2263CONDITIONAL14 May 2003

Windfarm to include 12 no. turbines, 50m anemometer mast, control building/ switchyard,fencing & access tracks

CASTLEPOOK NORTH, CASTLEPOOK NORTH,

1.8km
14/6270INCOMPLETED APPLICATION22 Oct 2014

Minor modifications to the previously approved Castlepook Wind Farm development comprising 14no. wind turbines (An Bórd Pleanála Ref. PL04.240434, and Cork County Council Ref. No. 11/4947). The development will consist of an increase in the maximum overall dimensions of the 14 permitted wind turbines (from 126m to 135m); substitution of 2no. permitted guyed anemometer masts with 2no. free standing anemometer masts with a height corresponding to the amended wind turbine towers; realignment of the access to a number of the wind turbines and all associated site works above & below ground

Castlepook North Carker North Ballyhoura Co.Cork

1.8km
14/5603INCOMPLETED APPLICATION23 Jul 2014

Minor modifications to the permitted Castlepook wind farm development consisting of an increase in the maximum overall dimensions of the 14no. permitted wind turbines (from 126m to 135m); substitution of 2no. permitted guyed anemometer masts with 2no. free standing anemometer masts with a height corresponding to the amended wind turbine towers; realignment of the access to a number of wind turbines; and all associated site works, above and below ground

Castlepook North Carker North Ballyhoura Co.Cork

The submission window has closed

Observations on this application closed on Monday 1 July 2013, five weeks after it was received. The authority cannot accept a late submission.

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?