CASTLEPOOK NORTH, CASTLEPOOK NORTH,
CONDITIONALPlanning application 03/2263
Cork - Cork County Council
Proposed Development
Windfarm to include 12 no. turbines, 50m anemometer mast, control building/ switchyard,fencing & access tracks
Application Timeline
Application received
14 May 2003
Decision: CONDITIONAL
3 Nov 2003
Decision due
5 Nov 2003
Application Details
- Location
- CASTLEPOOK NORTH, CASTLEPOOK NORTH,
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 14 May 2003Other applications received that week
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 3 November 2003
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Amended electrical transformer station at Castlepook Windfarm (pl04.240434 and Ref. No. 11/4947). The development will consist of a 38kV electrical transformer station comprising 2no. single storey control buildings and a substation with associated outdoor electrical equipment, including transformers, lightning protection masts and SCADA pole; effluent holding tanks, internal roads, boundary fencing around the perimeter of the compound, associated access track and all other associated site development works above & below ground
Castlepook North Ballyhoura Co.Cork
Permission to substitute the electrical transformer station Permitted under Planning Ref. No. 11/4947 (An Bórd Pleanála Ref. No. pl 04.240434) for Castlepook wind farm with a relocated and larger Electrical Transformer Station comprising 2no. single storey control buildings with associated outdoor electrical equipment, including transformers, lightning protection masts and SCADA pole; effluent holding tanks, internal roads, boundary fencing around the perimeter of the compound, associated access track and all other associated site development works above & below ground
Castlepook Wind Farm Castlepook North Ballyhoura Co.Cork
Permission for minor modifications to the previously approved Buttevant Wind Farm development comprising 6 no. wind turbines (Planning Ref. No. 13/5885). The development will consist of an increase in the maximum overall dimensions of the 6 no. permitted wind turbines (from 126m to 135m) alterations to the permitted site boundaries resulting in a reduction in site area and omission of permitted southern access to site and all associated site works above and below ground
Streamhill East & Streamhill West Doneraile
Minor modifications to the previously approved Buttevant Wind Farm development comprising 6no. wind turbines (Planning Ref. No. 13/5885). The development will consist of an increase in the maximum overall dimensions of the 6no. permitted wind turbines (from 126m to 135m) and all associated site works above & below ground.
Streamhill East & Streamhill West Doneraile Co.Cork
Minor modifications to the previously approved Castlepook Wind Farm development comprising 14no. wind turbines (An Bórd Pleanála Ref. PL04.240434, and Cork County Council Ref. No. 11/4947). The development will consist of an increase in the maximum overall dimensions of the 14 permitted wind turbines (from 126m to 135m); substitution of 2no. permitted guyed anemometer masts with 2no. free standing anemometer masts with a height corresponding to the amended wind turbine towers; realignment of the access to a number of the wind turbines and all associated site works above & below ground
Castlepook North Carker North Ballyhoura Co.Cork
Minor modifications to the permitted Castlepook wind farm development consisting of an increase in the maximum overall dimensions of the 14no. permitted wind turbines (from 126m to 135m); substitution of 2no. permitted guyed anemometer masts with 2no. free standing anemometer masts with a height corresponding to the amended wind turbine towers; realignment of the access to a number of wind turbines; and all associated site works, above and below ground
Castlepook North Carker North Ballyhoura Co.Cork
The development will consist of a Wind Energy Project comprising 14 wind turbines, access tracks, a fenced Electrical Transformer Station comprising a single-storey Control Building and Substation, an effluent treatment system, two anemometer masts, borrow pits and all associated site works, above and below ground. Each wind turbine will have an overall maximum dimension of 126 metres, comprising a tower 80-85 metres high, with a diameter of about 4 metres at the base, to which three blades of 41-45 metres length will be attached.
Castlepook North Carker North Ballyhoura
Minor modifications to the previously approved Castlepook Wind Farm development comprising 14 wind turbines (An Bord Pleanala Ref. PL 04.240434, Cork County Council Ref. 11/4947). The development will consist of an increase in the maximum overall dimensions of the 14 permitted wind turbines (from 126m to 135m); substitution of two permitted guyed anemometer masts with two free-standing anemometer masts with a height corresponding to the amended wind turbine towers, which will be a maximum of 90m; realignment of the access to turbines No. T2, T4 and T10; and all associated site works, above and below ground.
Castlepook North Carker North Ballyhoura
Permission for wind farm. The development will consist of the erection of 6no.wind turbines with ancillary equipment for the generation of electricity, upgrading of relevant access tracks and construction of new access tracks where required, a fenced electrical compound comprising a single storey control building and substation, transformwers, towers, and all associated site works. Each wind turbine will have an overall maximum height of 126m, comprising a tower of nominally 80-85m high, with a diameter of about 4 metres at the base, to which three blades of 41-45 metres length will be attached together with all other ancillary works.
Streamhill East Streamhill West Doneraile Co.Cork
A ten year Planning Permission to construct a wind farm. The development will consist of the erection of 6no. wind turbines with ancillary equipment for the generation of electricity, upgrading of relevant access tracks & construction of new access tracks where required, a fenced electrical compound comprising a single-storey control building and substation, transformers, towers & all associated site works. Each wind turbine will have an overall maximum height of 126 metres, comprising a tower of nominally 80-85 metres high, with a diameter of about 4 metres at the base, to which three number blades of 41-45 metres length will be attached together with all other ancillary works.
Streamhill East & Streamhill West Co.Cork
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?