← Back to search

CASTLEPOOK NORTH, CASTLEPOOK NORTH,

CONDITIONAL

Planning application 03/2263

Cork - Cork County Council

Proposed Development

Windfarm to include 12 no. turbines, 50m anemometer mast, control building/ switchyard,fencing & access tracks

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    14 May 2003

  2. Decision: CONDITIONAL

    3 Nov 2003

  3. Decision due

    5 Nov 2003

Application Details

Location
CASTLEPOOK NORTH, CASTLEPOOK NORTH,
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
14 May 2003Other applications received that week
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
3 November 2003

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

528m
14/6643INCOMPLETED APPLICATION9 Dec 2014

Amended electrical transformer station at Castlepook Windfarm (pl04.240434 and Ref. No. 11/4947). The development will consist of a 38kV electrical transformer station comprising 2no. single storey control buildings and a substation with associated outdoor electrical equipment, including transformers, lightning protection masts and SCADA pole; effluent holding tanks, internal roads, boundary fencing around the perimeter of the compound, associated access track and all other associated site development works above & below ground

Castlepook North Ballyhoura Co.Cork

528m
15/4037WITHDRAWN12 Jan 2015

Permission to substitute the electrical transformer station Permitted under Planning Ref. No. 11/4947 (An Bórd Pleanála Ref. No. pl 04.240434) for Castlepook wind farm with a relocated and larger Electrical Transformer Station comprising 2no. single storey control buildings with associated outdoor electrical equipment, including transformers, lightning protection masts and SCADA pole; effluent holding tanks, internal roads, boundary fencing around the perimeter of the compound, associated access track and all other associated site development works above & below ground

Castlepook Wind Farm Castlepook North Ballyhoura Co.Cork

556m
15/4155CONDITIONAL29 Jan 2015

Permission for minor modifications to the previously approved Buttevant Wind Farm development comprising 6 no. wind turbines (Planning Ref. No. 13/5885). The development will consist of an increase in the maximum overall dimensions of the 6 no. permitted wind turbines (from 126m to 135m) alterations to the permitted site boundaries resulting in a reduction in site area and omission of permitted southern access to site and all associated site works above and below ground

Streamhill East & Streamhill West Doneraile

556m
15/4019INCOMPLETED APPLICATION8 Jan 2015

Minor modifications to the previously approved Buttevant Wind Farm development comprising 6no. wind turbines (Planning Ref. No. 13/5885). The development will consist of an increase in the maximum overall dimensions of the 6no. permitted wind turbines (from 126m to 135m) and all associated site works above & below ground.

Streamhill East & Streamhill West Doneraile Co.Cork

1.2km
14/6270INCOMPLETED APPLICATION22 Oct 2014

Minor modifications to the previously approved Castlepook Wind Farm development comprising 14no. wind turbines (An Bórd Pleanála Ref. PL04.240434, and Cork County Council Ref. No. 11/4947). The development will consist of an increase in the maximum overall dimensions of the 14 permitted wind turbines (from 126m to 135m); substitution of 2no. permitted guyed anemometer masts with 2no. free standing anemometer masts with a height corresponding to the amended wind turbine towers; realignment of the access to a number of the wind turbines and all associated site works above & below ground

Castlepook North Carker North Ballyhoura Co.Cork

1.2km
14/5603INCOMPLETED APPLICATION23 Jul 2014

Minor modifications to the permitted Castlepook wind farm development consisting of an increase in the maximum overall dimensions of the 14no. permitted wind turbines (from 126m to 135m); substitution of 2no. permitted guyed anemometer masts with 2no. free standing anemometer masts with a height corresponding to the amended wind turbine towers; realignment of the access to a number of wind turbines; and all associated site works, above and below ground

Castlepook North Carker North Ballyhoura Co.Cork

1.2km
11/4947CONDITIONAL3 May 2011

The development will consist of a Wind Energy Project comprising 14 wind turbines, access tracks, a fenced Electrical Transformer Station comprising a single-storey Control Building and Substation, an effluent treatment system, two anemometer masts, borrow pits and all associated site works, above and below ground. Each wind turbine will have an overall maximum dimension of 126 metres, comprising a tower 80-85 metres high, with a diameter of about 4 metres at the base, to which three blades of 41-45 metres length will be attached.

Castlepook North Carker North Ballyhoura

1.2km
14/6379CONDITIONAL10 Nov 2014

Minor modifications to the previously approved Castlepook Wind Farm development comprising 14 wind turbines (An Bord Pleanala Ref. PL 04.240434, Cork County Council Ref. 11/4947). The development will consist of an increase in the maximum overall dimensions of the 14 permitted wind turbines (from 126m to 135m); substitution of two permitted guyed anemometer masts with two free-standing anemometer masts with a height corresponding to the amended wind turbine towers, which will be a maximum of 90m; realignment of the access to turbines No. T2, T4 and T10; and all associated site works, above and below ground.

Castlepook North Carker North Ballyhoura

1.3km
13/5885CONDITIONAL30 Sept 2013

Permission for wind farm. The development will consist of the erection of 6no.wind turbines with ancillary equipment for the generation of electricity, upgrading of relevant access tracks and construction of new access tracks where required, a fenced electrical compound comprising a single storey control building and substation, transformwers, towers, and all associated site works. Each wind turbine will have an overall maximum height of 126m, comprising a tower of nominally 80-85m high, with a diameter of about 4 metres at the base, to which three blades of 41-45 metres length will be attached together with all other ancillary works.

Streamhill East Streamhill West Doneraile Co.Cork

1.3km
13/5004INCOMPLETED APPLICATION28 May 2013

A ten year Planning Permission to construct a wind farm. The development will consist of the erection of 6no. wind turbines with ancillary equipment for the generation of electricity, upgrading of relevant access tracks & construction of new access tracks where required, a fenced electrical compound comprising a single-storey control building and substation, transformers, towers & all associated site works. Each wind turbine will have an overall maximum height of 126 metres, comprising a tower of nominally 80-85 metres high, with a diameter of about 4 metres at the base, to which three number blades of 41-45 metres length will be attached together with all other ancillary works.

Streamhill East & Streamhill West Co.Cork

Planning a project of your own?