Castlepook Wind Farm Castlepook North Ballyhoura Co.Cork

WITHDRAWN

Planning application 15/4037

Cork - Cork County Council

Proposed Development

Permission to substitute the electrical transformer station Permitted under Planning Ref. No. 11/4947 (An Bórd Pleanála Ref. No. pl 04.240434) for Castlepook wind farm with a relocated and larger Electrical Transformer Station comprising 2no. single storey control buildings with associated outdoor electrical equipment, including transformers, lightning protection masts and SCADA pole; effluent holding tanks, internal roads, boundary fencing around the perimeter of the compound, associated access track and all other associated site development works above & below ground

View the full application file on the council's planning portal →

Application Details

Location
Castlepook Wind Farm Castlepook North Ballyhoura Co.Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
12 January 2015Other applications received that week
Status
WITHDRAWN
Decision
Pending

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

0m
14/6643INCOMPLETED APPLICATION9 Dec 2014

Amended electrical transformer station at Castlepook Windfarm (pl04.240434 and Ref. No. 11/4947). The development will consist of a 38kV electrical transformer station comprising 2no. single storey control buildings and a substation with associated outdoor electrical equipment, including transformers, lightning protection masts and SCADA pole; effluent holding tanks, internal roads, boundary fencing around the perimeter of the compound, associated access track and all other associated site development works above & below ground

Castlepook North Ballyhoura Co.Cork

528m
03/2263CONDITIONAL14 May 2003

Windfarm to include 12 no. turbines, 50m anemometer mast, control building/ switchyard,fencing & access tracks

CASTLEPOOK NORTH, CASTLEPOOK NORTH,

1.0km
15/4155CONDITIONAL29 Jan 2015

Permission for minor modifications to the previously approved Buttevant Wind Farm development comprising 6 no. wind turbines (Planning Ref. No. 13/5885). The development will consist of an increase in the maximum overall dimensions of the 6 no. permitted wind turbines (from 126m to 135m) alterations to the permitted site boundaries resulting in a reduction in site area and omission of permitted southern access to site and all associated site works above and below ground

Streamhill East & Streamhill West Doneraile

1.0km
15/4019INCOMPLETED APPLICATION8 Jan 2015

Minor modifications to the previously approved Buttevant Wind Farm development comprising 6no. wind turbines (Planning Ref. No. 13/5885). The development will consist of an increase in the maximum overall dimensions of the 6no. permitted wind turbines (from 126m to 135m) and all associated site works above & below ground.

Streamhill East & Streamhill West Doneraile Co.Cork

1.1km
05/8946CONDITIONAL2 Dec 2005

Erection of 36m telecommunications structure carrying antennae, 2 no. equipment containers within a fenced compound and access track

Ballyhoura Carker North

1.1km
11/4249UNCONDITIONAL11 Feb 2011

Completion of a 36m telecommunications support structure carrying antennae and 2no. equipment containers within a fenced compound and access track

Ballyhoura Carter North Co Cork

1.2km
17/5773CONDITIONAL11 Jul 2017

Replacement of an existing telecommunications mast 10m high with one of 18m in height, so as to continue to supply a Broadband and Phone service from existing compound. The existing 7 dishes and 2 antennae will be transported across to the new mast and 8 new dishes will be added to enhance the service. Four of the five cabins on site, will be retained including one for the Limerick Fire Service

Ballyhoura Mountains Carker North Ballycoskery Co. Cork

1.4km
14/6270INCOMPLETED APPLICATION22 Oct 2014

Minor modifications to the previously approved Castlepook Wind Farm development comprising 14no. wind turbines (An Bórd Pleanála Ref. PL04.240434, and Cork County Council Ref. No. 11/4947). The development will consist of an increase in the maximum overall dimensions of the 14 permitted wind turbines (from 126m to 135m); substitution of 2no. permitted guyed anemometer masts with 2no. free standing anemometer masts with a height corresponding to the amended wind turbine towers; realignment of the access to a number of the wind turbines and all associated site works above & below ground

Castlepook North Carker North Ballyhoura Co.Cork

1.4km
14/5603INCOMPLETED APPLICATION23 Jul 2014

Minor modifications to the permitted Castlepook wind farm development consisting of an increase in the maximum overall dimensions of the 14no. permitted wind turbines (from 126m to 135m); substitution of 2no. permitted guyed anemometer masts with 2no. free standing anemometer masts with a height corresponding to the amended wind turbine towers; realignment of the access to a number of wind turbines; and all associated site works, above and below ground

Castlepook North Carker North Ballyhoura Co.Cork

1.4km
11/4947CONDITIONAL3 May 2011

The development will consist of a Wind Energy Project comprising 14 wind turbines, access tracks, a fenced Electrical Transformer Station comprising a single-storey Control Building and Substation, an effluent treatment system, two anemometer masts, borrow pits and all associated site works, above and below ground. Each wind turbine will have an overall maximum dimension of 126 metres, comprising a tower 80-85 metres high, with a diameter of about 4 metres at the base, to which three blades of 41-45 metres length will be attached.

Castlepook North Carker North Ballyhoura

The submission window has closed

Observations on this application closed on Sunday 15 February 2015, five weeks after it was received. The authority cannot accept a late submission.