Ballyhandle Quarry Crossbarry Co. Cork
INCOMPLETED APPLICATIONPlanning application 15/6088
Cork - Cork County Council
Proposed Development
Retention of extension to existing quarry (granted under planning ref 01/3907) including an extraction area of c.2.35 hectares, washing and screening plant, associated aggregate storage areas, settlement lagoons, stone cutting shed (114sq.m), machinery storage shed (180sq.m), all overburden storage areas, internal access roads and ancillary development beyond that permitted under planning ref: ref: 01/3907 all within an overall planning area of c.8.7 hectares. Permission is also sought for the continuance of use of blasting at the quarry as previously permitted under planning ref: 03/3458
Application Timeline
Application received
18 Sept 2015
Decision due
12 Nov 2015
Application Details
- Location
- Ballyhandle Quarry Crossbarry Co. Cork
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 18 September 2015
- Status
- INCOMPLETED APPLICATION
- Decision
- Pending
- Decision Due
- 12 November 2015
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
The continuance of use and retention with a planning application area of c.8.7 hectares of: [a] the existing quarry extraction area of c.2.35 hectares beyond that permitted under planning permission ref. nos. S/01/3907 and S/03/3458; [b] the existing washing and screening plant and associated aggregate storage areas and settlement lagoons located beyond that permitted under planning permission ref. S/05/5026; [c] machinery storage shed of 180 sq.m.; [d] stone cutting shed of 114 sq.m., and [e] all overburden storage areas, internal access roads and all other ancillary development beyond that permitted under planning permission ref. S/01/3907, S/03/3458 and S/05/5026
Ballyhandle Quarry Ballyhandle Crossbarry
Retention of extension to existing quarry (granted under planning ref 01/3907) including an extraction area of c.2.35 hectares, washing and screening plant, associated aggregate storage areas, settlement lagoons, stone cutting shed (114sq.m), machinery storage shed (180sq.m), all overburden storage areas, use of blasting, internal access roads and ancillary development beyond that permitted under planning reg.ref.no 01/3907, all within an overall quarry area of c.8.7 hectares
Ballyhandle Quarry Crossbarry Co. Cork
Retention of extension to existing quarry (granted under planning ref 01/3907) including an extraction area of c.2.35 hectares, washing and screening plant, associated aggregate storage areas, settlement lagoons, stone cutting shed (114sq.m), machinery storage shed (180sq.m), all overburden storage areas, use of blasting, internal access roads and ancillary development beyond that permitted under planning ref: 01/3907 all within an overall quarry area of c.8.7 hectares.
Ballyhandle Quarry Crossbarry, Ballymurphy Td Co. Cork
Installation & operation of an asphalt plant with an overall stack height of 27 meters, aggregate storage area , washing and screening facility, settlement lagoons and fuel storage
Ballyhandle Quarry Ballyhandle Crossbarry
Permission to waive Condition No. 3 of planning ref: 05/5026 to allow for the continuance of use for the duration of quarry extraction operations at the site, of the existing asphalt plant previously permitted under planning ref: No. 05/5026 with associated aggregate storage areas and settlement lagoons within an overall application area of c.2.75 hectares. Planning ref: 05/5026 was previously permitted for the installation and operation of an asphalt plant (with an overall stack height of 27 meters).
Ballyhandle Quarry Crossbarry Co. Cork
Permission to waive Condition No. 3 of planning ref: 05/5026 to allow for the continuance of use for the duration of quarry extraction operations at the site, of the existing asphalt plant previously permitted under planning ref: No. 05/5026 with associated aggregate storage areas and settlement lagoons within an overall application area of c.2.75 hectares. Planning ref: 05/5026 was previously permitted for the installation and operation of an asphalt plant (with an overall stack height of 27 meters).
Ballyhandle Quarry Crossbarry Co. Cork
Concrete products batching plant including provision of truck wash-out facility, site office, including canteen & washrom facility, 4 no. car parking spaces, aggregate storage, septic tank and percolation area.
Ballyhandle, Crossbarry
The development will consist of continued use and extension (c.6 hectares) of the existing quarry over a total extraction area of c.10 hectares and to a final floor level of c.57mOD; screening berms; final restoration; and related ancillary works; all within an overall application area of c.12.6 hectares.
Ballyhandle Quarry Ballyhandle Crossbarry, Co. Cork
Blasting at existing quarry
BALLYHANDLE, BALLYHANDLE,
A 10 Year Planning Permission for a 100% Carbon Negative Renewable Energy c.600 panel, 420 Kilo Watts (c.1875m2) ground mounted solar PV array and all associated works. This development is covered by the provisions of the Renewable Energy Directive III (Directive(EU)2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development regulations 2001 to 2025 shall apply.
Ballyhandle, Crossbarry, Co. Cork, T12DK46
The submission window has closed
Observations on this application closed on Thursday 22 October 2015, five weeks after it was received. The authority cannot accept a late submission.