PepsiCo Worldwide Flavors Production Plant Little Island Industrial Estate, Ballytrasna Little Island Co. Cork
INCOMPLETED APPLICATIONPlanning application 16/4332
Cork - Cork County Council
Proposed Development
The development will consist of the construction of a new plant room adjacent to the existing production building, comprising of a two storey steel frame with the steel cladding on the upper section. New floor area to be 143sq.m with an overall height not exceeding 10.513m
View the full application file on the council's planning portal →Application Timeline
Application received
17 Feb 2016
Decision due
12 Apr 2016
Application Details
- Location
- PepsiCo Worldwide Flavors Production Plant Little Island Industrial Estate, Ballytrasna Little Island Co. Cork
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 17 February 2016
- Status
- INCOMPLETED APPLICATION
- Decision
- Pending
- Decision Due
- 12 April 2016
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Construction of a new plant room adjacent to the existing production building, comprising of a two storey steel frame with the steel cladding on the upper section. New floor area to be 143sq.m with an overall height not exceeding 10.513m
PepsiCo Worldwide Flavors Production Little Island Industrial Estate Ballytrasna Little Island
(1) Change of use of the existing maintenance store of the existing O'Neill's building to ground floor preparation area/tasting area & first floor office with external changes, (2) Change of use of existing R & D warehouse to part ground floor laboratory with associated offices overhead and external changes, and (3) Retention of existing E.S.B.substation at the existing PepsiCo Ireland Plant and associated works
Ballytrasna Little Island
Dust extraction building as lean-to extension to rear of factory
UNIT 25W, LITTLE ISLAND IND. EST., BALLYTRASNA,
Construction of steel framed sheeted building to enclose storage tank and plant
UNIT 25W, LITTLE ISLAND IND. EST., BALLYTRASNA,
Relocation of process water treatment room to new purpose built building
Ballytrasna Little Island
Demolition of the existing Reagecon building including crushing concrete on site and all ancillary site works
Little Island Business Park Ballytrasna Little Island Co. Cork
Construction of a single storey extension to the administration block along the north elevation to accommodate additional canteen & locker space, and for alteration to the façade along its western elevation, and for construction of a single storey reception/security building along with all associated site works
Little Island Industrial Estate Ballytrasna Little Island Co. Cork
Construction of a single storey extension to the administration block along the north elevation to accommodate additional canteen and locker space, including a glazed walkway, internal alterations, alterations to the ground and first floor façade on the western and northern elevations and construction of a single storey reception/security building along with all associated site works
Little Island Industrial Estate Ballytrasna Little Island
Extension to the administration block at the east end to accommodate new laboratories at ground floor and associated offices at first floor along with associated works, along with retention of the emergency stairway to south elevation of main warehouse, the annex building and foam house buildings to the west elevation of main warehouse
Little Island Business Park Ballytrasna Little Island Co. Cork
Extension to administration block at north-east end of site to accommodate new laboratories at ground floor and associated offices at first floor along with associated works, along with retention of emergency stairway to south elevation of main warehouse and retention of annex building and foam house buildings to the west elevation of main warehouse
Little Island Business Park Ballytrasna Little Island
Affected by this application?
Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.
Make a Submission or ObjectionPlanning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?