Proposed Development
Erect a dwelling house, an on-site sewage treatment system, and all associated site development works.
Application Timeline
Application received
26 Aug 2016
Decision due
20 Oct 2016
Decision: REFUSED
20 Oct 2016
Application Details
- Location
- Barryscourt Carrigtwohill Co. Cork
- Applicant
- N/A
- Application Type
- OUTLINE PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 26 August 2016Other applications received that week
- Status
- APPLICATION FINALISED
- Decision
- REFUSED
- Decision Date
- 20 October 2016
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Retention of a firewater retention pond and associated works
Tullagreen Carrigtohill
Retention of a firewater retention pond and associated works
Tullagreen Carrigtohill
The creation of a temporary surface treatment for the purpose of commercial storage of articulated truck trailers, a new vehicular entrance, palisade boundary fencing and associated site works.
Barryscourt Carrigtwohill Co. Cork
Create a temporary surface treatment for the purpose of commercial storage of articulated truck trailers, a new vehicular entrance, palisade boundary fencing and associated site works.
Barryscourt Carrigtwohill Co. Cork
To create a temporary surface treatment for the purpose of commercial storage of articulated truck trailers, a new vehicular entrance, palisade boundary fencing and associated site works. A Natura Impact Statement will be submitted to the Planning Authority with the application.
Barryscourt Carrigtohill TD. Carrigtwohill Co. Cork
Create a temporary surface treatment for the purpose of commercial storage of articulated truck trailers, a new vehicular entrance, palisade boundary fencing and associated site works.
Barryscourt Carrigtwohill Co. Cork
To create a temporary surface treatment for the purpose of commercial storage and associated site works.
Barryscourt Carrigtwohill Co. Cork
[1] Change of use from warehousing to manufacturing with total floor area of 330sqm. [2] Construction of a new chemical store with IBC bunded racking, new floor slab and associated works. [3] Construction of new small volume chemical store and associated site works.
Tullagreen Carrigtwohill
The Development will consist of a new waste water treatment area. Works will include the construction of a standalone single storey roofed tankage structure, a two-storey dewatering/sludge building, a concrete slab area, access road, 3 no. vehicle parking bays and associated ground level mounted equipment and storage area. This application is for an amendment to the WWT area previously approved under reference no. 22/4839. The proposed development is on an existing manufacturing site to which the Major Accidents Directive applies, and to which an Industrial Emissions Licence and an Integrated Pollution Control Licence that are regulated by the Environmental Protection Agency (EPA) applies.
Tullagreen & Carrigtohill Carrigtwohill Co.Cork
Construction of warehouse with office space
Carrigtwohill
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?