Townlands of Finnis and Mishells Co. Cork

CONDITIONAL

Planning application 17/6111

Cork - Cork County Council

Proposed Development

A ground mounted solar photovoltaic (PV) farm within a site area of approximately 40 hectares consisting of solar photovoltaic panels covering an area of up to 75,100sq.m on ground mounted steel frames, 1 no. on-site substation with 2 possible locations, option 1 identifies the substation location within the townland of Finnis and option 2 identifies the substation location within the townland of Mishells, up to 8 no. inverter/transformer stations, underground cables and ducts, boundary security fence, new internal tracks, CCTV cameras and all associated site services and works located within the townlands of Finnis and Mishells.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    16 Aug 2017

  2. Decision: CONDITIONAL

    8 Jun 2018

  3. Decision due

    13 Jun 2018

Application Details

Location
Townlands of Finnis and Mishells Co. Cork .
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
16 August 2017
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
8 June 2018

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

502m
05/6721CONDITIONAL16 Sept 2005

Dwellinghouse

Finnis Bandon

675m
07/9087CONDITIONAL28 Jun 2007

Construction of cattle shed over existing feeding passage with new underground slurry storage tank, new dirty water tank and associated site works

Finnis Bandon

701m
25/6845Awaiting F.I. Response17 Dec 2025

The provision of a Battery Energy Storage System (BESS), compound and cable route on a site of c. 4.61ha. The BESS compound will accommodate self-contained Lithium Iron Phosphate batteries within 32 no. BESS units, 8 no. MV Switchgear units, and a 38kV substation including a control room of 126m2. A cable route of c. 2km is proposed to run south from the compound to the L2033 and east along the L2033 to the nearby Bandon 110kV Substation. The proposed development includes for all associated development, site levelling, boundary treatments, security fencing, site access works, ducting and cabling and all ancillary works.

Mishells, Bandon, Co. Cork

896m
05/953CONDITIONAL21 Feb 2005

Extension to dwellinghouse

Mishells Bandon

905m
22/5103WITHDRAWN13 May 2022

Permission to construct dwelling house, domestic garage and associated site works.

Mishells Bandon Co.Cork

923m
25/4752INCOMPLETED APPLICATION23 Apr 2025

Permission for the proposed construction of a new detached dwelling house, (Proposed relocation of the permitted dwelling, garage, waste water treatment plant and percolation area positions on site, under Planning Reference 23/05501), and all associated site works.

Mishells Bandon Co. Cork

923m
25/5290Conditional Permission1 Jul 2025

Permission for the proposed construction of a dwelling house, garage, waste water treatment plant and percolation area (change of plan to that permitted by pl reg. no. 23/5501) and all associated site works

Mishells Bandon Co.Cork

923m
23/5501CONDITIONAL24 Jul 2023

The proposed construction of a new detached dwelling house, detached garage and all associated site works.

Mishells Bandon Co. Cork

945m
06/9630CONDITIONAL10 Aug 2006

Construction of loose cattle shed, milking parlour, soiled water tank, concrete apron, overground slurry storage tank and associated site works

Mishells Bandon

982m
16/5713CONDITIONAL11 Jul 2016

Construction of a new detached dwelling house, detached garage and the installation of a waste water treatment plant and all associated site works.