← Back to search

Ballintaggart Ballybricken Ringaskiddy Co. Cork

CONDITIONAL

Planning application 19/5543

Cork - Cork County Council

Proposed Development

The construction of a 2 storey external utilities piperack extension enclosed with a full height perforated mesh screen at the second and third floor levels to the west, a 3 storey external utilities piperack extension enclosed with a full height perforated mesh screen at first, second and third floor to the east and an enclosed 4 storey access stairwell extending from ground level to third floor level to the east of the existing Organic Synthesis Plant 1 at production facility. The proposed development is covered by an existing Industrial Emissions Licence No. P0013-14. The development refers to a modification to an establishment to which the Major Accident Directive applies.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    12 Jun 2019

  2. Decision due

    6 Aug 2019

  3. Decision: CONDITIONAL

    6 Aug 2019

  4. Grant issued

    16 Sept 2019

Application Details

Location
Ballintaggart Ballybricken Ringaskiddy Co. Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
12 June 2019
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
6 August 2019
Grant Date
16 September 2019

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

2m
18/4889CONDITIONAL11 Apr 2018

Construction of a 2 storey electrical room extension on the roof of the existing Laboratories and Offices Building, a service riser from the underside of the first floor level to roof level to roof level on the southern elevation and a platform on the roof of the existing Organic Synthesis Plant 1 at production facility. The proposed development is covered by an existing Industrial Emissions Licence No. P0013-04. The development refers to a modification to an establishment to which the Major Accident directive applies.

Ballintaggart and Ballybricken Ringaskiddy Co. Cork

24m
17/7390CONDITIONAL21 Dec 2017

Construction of a roof level platform for 2 no. Air Handling Units and associated ductwork and an extension to an existing stairs to access the proposed platform over the existing Organic Synthesis Plant 1 and the construction of a Drum Storage Canopy to the south of the existing Organic Synthesis Plant 3 at their production facility. The proposed development is covered by an existing Industrial Emissions Licence No. P001304. The development refers to a modification to an establishment to which the Major Accident directive applies.

Ballintaggart and Ballybricken Ringaskiddy Co. Cork

46m
23/5839CONDITIONAL11 Sept 2023

Permission for the construction of an extension to the existing roof level platform for 1 no. air handling unit and associated ductwork over the existing organic synthesis plant 1. The construction of a roof level platform for 5 no. air handling units and associated plant and ductwork over the existing organic synthesis plant 3 including 2 no. cladded screens at penthouse level, 2 no. cladded screens with louvres at roof level and all ancillary site development works at their production facility. The proposed development is covered by an existing Industrial Emissions Licence No. P0013. As the development refers to a modification to an establishment to which the Major Accident Directive applies, information as specified in the Third Schedule of the Major Accident Regulations will be submitted with the application.

Ballintaggart Ringaskiddy Co Cork

46m
06/12988CONDITIONAL5 Dec 2006

Replacement of 3 no. solvent towers, construction of tanker unloading facility and control room extension to plant

Ballintaggart Ringaskiddy

48m
15/4182CONDITIONAL2 Feb 2015

Construction of extension at ground, first, second and penthouse floor levels of the existing organic synthesis production building No.1 and an ancillary single storey shed to accommodate cylinder storage

Ballintaggart Ballybricken Ringaskiddy Co.Cork

48m
16/6937CONDITIONAL25 Nov 2016

Construction of a two-storey extension at ground floor level to an existing Laboratory building at their production facility at Ballintaggart and Ballybricken townlands. The proposed extension will consist of a hydrogenation room, an electrical room, a fumehood laboratory, laboratory technology space and an associated external covered canopy with a combined floor area of 207m².

Ballintaggart and Ballybricken Townlands Ringaskiddy Co. Cork

48m
17/5864CONDITIONAL19 Jul 2017

Construction of 2 no. storage sheds adjacent to the existing Organic Synthesis Plant 4 Finished Goods Building at their production facility. The proposed development is covered by an existing Industrial Emissions Directive Licence No. P0013-04. The development refers to a modification to an establishment to which the Major Accident directive applies.

Ballintaggart and Ballybricken Townlands Ringaskiddy Co Cork

48m
16/6500CONDITIONAL7 Oct 2016

The construction of a one storey extension above the existing stairs, access corridor, lift and escape stairs to serve the plant room floor level of the extension granted under Planning Reg. No. 16/4784 to raise the height of this extension to the existing Organic Synthesis Production Building No. 1. The proposed development is covered by an existing Industrial Emissions Licence No. P0013-04. The development refers to a modification to an establishment to which the Major Accident directive applies.

Ballintaggart and Ballybricken Ringaskiddy Co. Cork

48m
16/4629CONDITIONAL18 Mar 2016

Construct a ground floor extension to the existing Organic Synthesis Production Building No.1 and an extension at ground, mezzanine, first, second and penthouse floor levels to the existing Organic Synthesis Production Building No.3. The proposed development is covered by an existing Integrated Pollution Prevention and Control License No. P0013-14. The development refers to modification to an establishment to which the Major Accident directive applies.

Ballintaggart & Ballybricken Ringaskiddy Co. Cork

48m
16/4784CONDITIONAL8 Apr 2016

The construction of an extension at ground, first, second, third and plant room floor levels to the existing Organic Synthesis Production Building No. 1. The proposed development is covered by an existing Industrial Emissions Licence No. P0013-04. The development refers to a modification to an establishment to which the Major Accident directive applies.

Ballintaggart & Ballybricken Ringaskiddy Co. Cork

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?