Proposed Development
To demolish existing georgian columns and roof overhang and to construct
- (A)new storey and a half extension including porch to front elevation
- (B)new single storey flat roof extension to side elevation
- (C)new single storey flat roof extension to rear elevation
- (D)replace existing window on south western elevation with French doors-all to existing dwellinghouse
Application Timeline
Application received
2 Oct 2020
Decision due
26 Nov 2020
Decision: CONDITIONAL
26 Nov 2020
Grant issued
8 Jan 2021
Application Details
- Location
- Carrigoon Beg Mallow Co. Cork
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 2 October 2020
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 26 November 2020
- Grant Date
- 8 January 2021
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Dwellinghouse and garage
Carrigoon Beg Mallow
Dwellinghouse and garage
Carrigoon Beg Mallow
Demolition of existing changing room building, installation of 3no. individual prefabricated dressing room units. Each unit is to include 2 dressing rooms & ancillary shower & toilet facilities, and all associated site works including connection to existing services on site
Parkadallane Mallow
Demolition of changing room building and construction of new building consisting of four changing rooms and carrying out associated works
Parkadallane Mallow
Retention Permission for a temporary portacabin and permission for the demolition of a temporary portacabin and construction of a new pre-fabricated portacabin of 49s.q.m., and all associated site development works.
ESB 110kv Station St. Josephs Road Carrigoon Beg Mallow, Co. Cork
Permission for Retention of a temporary portacabin including holding tank, which was retained on site used for staff welfare after the construction period, and Permission for the demolition of this existing portacabin and construction of a new pre-fabricated portacabin, including holding tank for use as staff welfare and all associated site development works.
ESB 110 kV Substation St. Josephs Road Carrigoon Beg Mallow, Co.Cork
Retention permission for a temporary portacabin including holding tank, which was retained on site used for staff welfare after the construction period, and permission for the demolition of this existing portacabin and construction of a new pre-fabricated portacabin, including holding tank, for use as staff welfare, and all associated site development works
ESB 110kV Substation, St.Joseph's Road Carrigoon Beg Mallow Co.Cork
Retention permission for a temporary portacabin including holding tank, which was retained on site used for staff welfare after the construction period, and permission for the demolition of this existing portacabin and construction of a new pre-fabricated portacabin, including holding tank, for use as staff welfare and all associated site works
ESB 110kV Substation St.Josephs Road Carrigoon beg Mallow, Co.Cork
Retention of existing domestic garage and all associated works
Carrigoon More Mallow Co. Cork
Alterations to existing 110kV electrical transformer station to include installation of 2 no. 38kV/MV transformers and associated bunding, 1 no. oil/water interceptor and percolation area, 1 no. 38kV Transformer bay to include disconnects, circuit breakers, current transformers and cable sealing ends, new containerised medium voltage building and associated works
Carrigoon Beg Mallow
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?