Beaufort Building - Environmental Research University College Cork, Haulbowline Road Loughbeg, Ringaskiddy Co.Cork
CONDITIONALPlanning application 23/6365
Cork - Cork County Council
Proposed Development
Permission for the relocation and erection of a small micro generation research wind turbine at the north -eastern corner of the site. The wind turbine will be used to provide power to the Beaufort Building and for the educational purposes. The project involves:
- 1)construction of a concrete foundation for the turbine (measuring 12.25m2)
- 2)erection of the tower and turbine (metal lattice tower and turbine with tip height of 19.1m)
- 3)associated site works, fencing and utility connections
Application Timeline
Application received
24 Nov 2023
Decision due
29 Jan 2024
Decision: CONDITIONAL
29 Jan 2024
Grant issued
7 Mar 2024
Application Details
- Location
- Beaufort Building - Environmental Research University College Cork, Haulbowline Road Loughbeg, Ringaskiddy Co.Cork
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 24 November 2023Other applications received that week
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 29 January 2024
- Grant Date
- 7 March 2024
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Removal of three car parking spaces and the erection of a research container unit.
Beaufort Building - Environmental Research Institute University College Cork Haulbowline Road Loughbeg Ringaskiddy Co Cork
Widening of existing entrance, relocation of existing front road boundary fence, relocation of weighbridge, change of use of building 1 & 2 from bulk storage of granulated fertilizer to accommodate port related activities including storage and screening of wood pellets, timber, feedstuffs and non hazardous fertilizers routed through Port of Cork and open storage of finished product on pallets
Ringaskiddy
Widening of existing entrance, relocation of existing front road boundary fence, relocation of weighbridge, change of use of Building No's 1 & 2 to accommodate port related activities to include storage and screening of wood pellets, timber, feedstuffs and non hazardous fertilizers routed through Port of Cork and open sotrage of finished product on pallets
Ringaskiddy
Change of use of existing dis-used loading yard area to use for the open storage of aggregate material for road re-surfacing and use of existing hardcore yard for occasional re-cycling of aggregate material using mobile cold bitumen recycling mixing equipment
Ringaskiddy Co. Cork .
For the change of use of existing dis-used loading yard area to use for the open storage of aggregate material for road re-surfacing and use of existing hardcore yard for occasional re-cycling of aggregate material using mobile mixing equipment
Ringaskiddy Co.Cork .
Conversion of industrial storage facility in a former magazine building to crematorium with associated site works
Rocky Island Ringaskiddy
a) The demolition of a 107 square metre single storey timber framed structure and cladded canopy within the loading bay area to the north of the existing production facility, b) the construction of 1 no. single storey extension within the loading bay area to the north and 1 no. single storey extension to the north west of the existing production facility and c) all associated modifications and site development works.
Loughbeg Ringaskiddy Co. Cork
Retention of a 240 square meter two storey structure for office use on the east side of the existing manufacturing facility. The above facility is ancillary to the existing production and plant areas
Loughbeg Ringaskiddy Co. Cork
Retention of a 60metre high meteorological data collection mast at Loughbeg. The period of retention in relation to this application is 2 years
Loughbeg Industrial Estate Loughbeg Ringaskiddy
Installation of a solar photovoltaic (PV) array on the roof of production facility within a site of 0.32ha. The array will consist of c.1825sq.m of PV modules. The proposed PV array will have a maximum generating capacity of c.300kW.
Loughbeg Ringaskiddy Co. Cork
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?