Proposed Development
Permission for works to existing dwelling to comprise construction of part single storey extension, part two-storey extension, modification to said dwelling, a detached garage, a waste water treatment system, vehicular entrance, field entrance, demolition of existing outhouse structures and all associated site works.
View the full application file on the council's planning portal →Application Timeline
Application received
8 Dec 2023
Decision: CONDITIONAL
3 Sept 2024
Decision due
5 Sept 2024
Grant issued
11 Oct 2024
Application Details
- Location
- Mishells Bandon Co Cork
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 8 December 2023
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 3 September 2024
- Grant Date
- 11 October 2024
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Permission for change of design of works to existing dwelling to comprise construction of part single storey extension, part two-storey extension and modifications to said dwelling, as granted under permission reg. number 23/06445, and all associated site works.
Mishells, Bandon, Co. Cork, P72C448
Demolition of dwelling and outbuilding and construction of dwellinghouse and garage
Mishells Bandon
2km of grid connection infrastructure on the public road and agricultural land to connect the approved Finnis Solar Farm (Planning Reference 17/6111) to the existing Bandon Substation and to connect two parcels of land within the consented development comprising the laying of underground electricity cables, associated infrastructure and horizontal directional drilling.
Finnis Mishells Bandon Co. Cork
2km of grid connection infrastructure on the public road and agricultural land to connect the approved Finnis Solar Farm (Planning reference 17/6111) to the existing Bandon Substation and to connect two parcels of land within the consented development comprising the laying of underground electricity cables, associated infrastructure and horizontal directional drilling.
Finnis Mishells Bandon Co Cork
Construction of dwelling and associated site works which includes installation of foul water effluent treatment plant.
Mishells Bandon Co Cork
Construction of a dwelling and to carry out associated site works, including the installation of foul water effluent treatment plant
Mishells Bandon Co. Cork
Construction of dwelling, and to carry out associated site works which includes installation of foul water effluent treatment plant
Mishells Bandon Co. Cork
Construction of livestock housing with 2 no. slatted tanks and associated works
Mishells Bandon
Dwellinghouse
Mishells Bandon
Dwellinghouse with access roadway
MISHELLS, MISHELLS,