Permission for construction of a single storey extension to the existing industrial premises.
Application Timeline
Application received
19 Apr 2024
Decision: CONDITIONAL
11 Jun 2024
Decision due
13 Jun 2024
Grant issued
19 Jul 2024
Application Details
- Location
- Lettertec Ireland Ltd. Springhill House Springhill Business Park Carrigtwohill Co Cork
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 19 April 2024Other applications received that week
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 11 June 2024
- Grant Date
- 19 July 2024
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Installation of windows and provision of two storey office area within existing industrial building
6,7 & 8, KILLACLOYNE,
Change of use from a warehousing unit to a materials recovery facility & vehicle parking
Carhoo Carrigtwohill
Change of use from warehousing unit to materials recovery facility and vehicle parking
Carhoo Carrigtwohill
The development will consist of (1) a single storey laboratory building to include plant and equipment area, office area, meeting rooms, canteen and kitchen, staff toilets, laboratories, IT room, electrical switch rooms and store rooms. The main laboratory building is 6.1 metres high, 44.5 metres long and 21.5 metres wide with vertical brise soleil screen offset from the southern facade. (2) An ESB substation of 3.18 metres high, 4.83 metres long and 4.32 metres wide is proposed to the rear of the building adjacent to the proposed service yard to the north of the main laboratory building. (3) The proposed development also includes 19 No. new car parking spaces comprising 2 No. visitor parking bays, 5 No. car pool parking bays. 1 No. wheelchair accessible parking bay, 2 No. dedicated electric vehicle charging bays, 2 No. motorcycle parking spaces and a covered bicycle shelter. (4) The proposed site works will include a 2.2 metre high, full perimeter security fence with new vehicular entrance gate and pedestrian turnstile entrance to the south east corner of the site, new entrance/exit to the proposed site, internal access roads pedestrian pathways, underground and overhead utilities, landscaping and all other associated site works.
The IDA Business and Technology Park Killacloyne Carrigtohill Co. Cork
Construction of ESB substation. The ESB substation including an adjacent switchroom will be 3.375m high, 7,650m long and 4.360m wide (change of location from that previously permitted under Pl.Reg.20/4090)
The IDA Business and Technology Park Killacloyne Carrigtohill Co. Cork
The construction of a new and upgraded entrance to replace existing agricultural entrance. The new entrance is required to access lands zoned industrial.
Killacloyne Carrigtwohill Co Cork
Installation of photovoltaic panels on the existing rooftop of the packaging and warehouse buildings. The proposed development will comprise of 1,458 no. new photovoltaic panels, total area of 3,340 m sq. on a mix of roof mounted and ballasted frames together with all ancillary cabling and electrical infrastructure modules over 3 phases.
Gilead Sciences Ireland UC IDA Business and Technology Park Anngrove Carrigtwohill, Co. Cork
Construction of office complex comprising of 3 no. three to five storey blocks, provision of 276 no. basement car parking spaces, rooftop plant area, 2 no. ESB substations and all associated site development works
Fota Retail & Bus. Park Killacloyne Carrigtohill
Construction of office complex comprising of 3 no. three to five storey blocks, provision of 276 no. basement car parking spaces, rooftop plant area, 2 no. ESB substations and all associated site development works, extension of duration to permission granted under planning reg 07/13099
Fota Business Park Killacloyne Carrigtohill Co. Cork
Construction of office complex comprising of 3 no. three to five storey blocks, provision of 276 no. basement car parking spaces, rooftop plant area, 2 no. ESB substations and all associated site development works, extension of duration of permission granted under Planning Reg. No. 07/13099
Fota Business Park Killacloyne Carrigtwohill