← Back to search

Ballintaggart Townlnad, Ringaskiddy, Cork

Significant F.I. Received

Planning application 25/5896

Cork - Cork County Council

Proposed Development

1) Permission for retention of the following, a) modifications to the elevations, b) additional production floor area of i) 32 square metres at ground floor level, ii) 22.1 square metres at ground floor mezzanine level, iii) 48.1 square metres at first floor level, iv) 48.1 square metres at second floor level, v) 48.1 square metres at second floor mezzanine level and vi) 48.1 square metres at third floor level. This retention permission relates to the previously permitted New Product Technology Laboratory Extension, Planning ref. 22/5541. 2) Permission for retention of a 3 storey production extension at ground floor level with a second floor mezzanine to the north East of the previously permitted New Product Technology Laboratory Extension, Planning ref. 22/5541. The Extension to be retained has a total floor area of 84 square metres. The development is covered by an existing Industrial Emissions Directive Licence no. P0013. As the development refers to a modification to an establishment to which the major accident directive applies, information as specified in the third schedule of the major accident regulations will be submitted with the application.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    12 Sept 2025

  2. Decision due (upcoming)

    9 Sept 2026

Application Details

Location
Ballintaggart Townlnad, Ringaskiddy, Cork
Applicant
N/A
Application Type
Permission for Retention
Planning Authority
Cork County Council

Timeline

Registration Date
12 September 2025
Status
Significant F.I. Received
Decision
Pending
Decision Due
9 September 2026

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

15m
22/5541CONDITIONAL30 Jun 2022

(1) permission for retention of the following, (a) modifications to the elevations, (b) the extension of the goods lift to roof level including an external canopy at roof level, (c) the relocation of the firefighting stairs to the west of the existing building including signage on the western elevation, (d) an external access stairs from low level roof to high level roof, (e) additional production floor area of 139.5sq.m at ground floor mezzanine level, (f) additional production floor area of 621sq.m and 2 no. access platforms at second floor mezzanine level, (g) additional production floor area of 46.8 square metres at third floor level and (h) modifications to the location and size of the production stairs on the west & east side of the south side extension. This retention permission relates to the previously permitted New Product Technology Laboratory extension, planning ref. 18/7382. (2) Permission for the following, (a) the construction of a 4-storey production extension at ground floor level to the north & west with a ground floor and second floor mezzanine including a fire escape stairwell at the north west corner of this proposed extension. The proposed extension has a total floor area of 1,736 square metres. (b) additional plant room floor area of 166 square metres at third floor level and (c) the provision of roof mounted plant on the low-level roof area of the New Product Technology Laboratory building. The proposed development is covered by an existing Industrial Emissions Directive Licence no. P0013. As the development refers to a modification to an establishment to which the Major Accident Directives applies, information as specified in the third schedule of the major accident regulations will be submitted with the application.

Ballintaggart Townland Ringaskiddy Co.Cork

15m
22/5294INCOMPLETED APPLICATION3 Jun 2022

1. Permission for retention of the following, a) modifications to the elevations, b) the extension of the goods lift to roof level including an external canopy at roof level, c) the relocation of the firefighting stairs to the west of the existing building including signage on the western elevation, d) an external access stairs from low level roof to high level roof, e) additional production floor area of 139.5 square metres at ground floor mezzanine level, f) additional production floor area of 621 square metres and 2 no. access platforms at second floor mezzanine level, g) additional production floor area of46.8 square metres at third floor level and h) modifications to the location and size of the production stairs on the west & east side of the south side extension. This retention permission relates to the previously permitted New Product Technology Laboratory Extension, Planning Ref. 18/7382. 2. Permission for the following, a) the construction of a 4 storey production extension at ground floor level to the North & West with a ground floor and second floor mezzanine including a fire escape stairwell at the North West corner of this proposed extension. The proposed extension has a total floor area of 1,736 square metres. b) additional plant room floor area of 166 square metres at third floor level and c) the provision of a roof mounted plant on the low level roof area, of the New Product Technology Laboratory Building. The proposed development is covered by an existing Industrial Emissions Directive Licence No. P0013. As the development refers to a modification to an establishment to which the Major Accident Directive applies, information as specified in the Third Schedule of the Major Accident regulations will be submitted with the application.

Ballintaggart and Ballybricken Ringaskiddy Co. Cork

17m
18/7382CONDITIONAL20 Dec 2018

Alterations and extensions to permitted pharmaceutical production building, New Product Technology Laboratory (formerly known as Organic Synthesis Plant 2). The works include the following; i) a two storey extension at first floor level on the north west side, ii) a two storey extension at second floor level on the east side iii) a one storey extension to the east and west of the existing plant room at third floor level, iv) a one storey vertical extension of the existing lift at third floor level, v) a one storey vertical extension of the existing north western stairs at second floor level, vi) a four storey extension at ground floor level to the south, vii) an external drum warmer pad with canopy over the south and viii) minor elevational changes at production facility. The proposed development is covered by an existing Industrial Emissions Directive Licence No. P0013-04. The development refers to a modification to an establishment to which the Major Accident directive applies.

Ballintaggart and Ballybricken Ringaskiddy Co. Cork

48m
23/5839CONDITIONAL11 Sept 2023

Permission for the construction of an extension to the existing roof level platform for 1 no. air handling unit and associated ductwork over the existing organic synthesis plant 1. The construction of a roof level platform for 5 no. air handling units and associated plant and ductwork over the existing organic synthesis plant 3 including 2 no. cladded screens at penthouse level, 2 no. cladded screens with louvres at roof level and all ancillary site development works at their production facility. The proposed development is covered by an existing Industrial Emissions Licence No. P0013. As the development refers to a modification to an establishment to which the Major Accident Directive applies, information as specified in the Third Schedule of the Major Accident Regulations will be submitted with the application.

Ballintaggart Ringaskiddy Co Cork

52m
24/4786CONDITIONAL2 May 2024

Permission for the construction of a single storey electrical building and all ancillary site development works at their production facility. The proposed development is covered by an existing Industrial Emissions Directive Licence No. P0013-06. As the development refers to a modification to an establishment to which the Major Accident Directive applies, information as specified in the Third Schedule of the Major Accident Regulations will be submitted with the application.

Ballintaggart Ringaskiddy Co.Cork

55m
17/7390CONDITIONAL21 Dec 2017

Construction of a roof level platform for 2 no. Air Handling Units and associated ductwork and an extension to an existing stairs to access the proposed platform over the existing Organic Synthesis Plant 1 and the construction of a Drum Storage Canopy to the south of the existing Organic Synthesis Plant 3 at their production facility. The proposed development is covered by an existing Industrial Emissions Licence No. P001304. The development refers to a modification to an establishment to which the Major Accident directive applies.

Ballintaggart and Ballybricken Ringaskiddy Co. Cork

74m
19/5543CONDITIONAL12 Jun 2019

The construction of a 2 storey external utilities piperack extension enclosed with a full height perforated mesh screen at the second and third floor levels to the west, a 3 storey external utilities piperack extension enclosed with a full height perforated mesh screen at first, second and third floor to the east and an enclosed 4 storey access stairwell extending from ground level to third floor level to the east of the existing Organic Synthesis Plant 1 at production facility. The proposed development is covered by an existing Industrial Emissions Licence No. P0013-14. The development refers to a modification to an establishment to which the Major Accident Directive applies.

Ballintaggart Ballybricken Ringaskiddy Co. Cork

75m
18/4889CONDITIONAL11 Apr 2018

Construction of a 2 storey electrical room extension on the roof of the existing Laboratories and Offices Building, a service riser from the underside of the first floor level to roof level to roof level on the southern elevation and a platform on the roof of the existing Organic Synthesis Plant 1 at production facility. The proposed development is covered by an existing Industrial Emissions Licence No. P0013-04. The development refers to a modification to an establishment to which the Major Accident directive applies.

Ballintaggart and Ballybricken Ringaskiddy Co. Cork

80m
08/4083CONDITIONAL10 Jan 2008

Installation of Community Alert Siren on roof of existing OSP3 Production Plant

Ballintaggart Ringaskiddy

80m
07/12843INCOMPLETED APPLICATION4 Dec 2007

Installation of Community Alert Siren on roof of existing OSP3 Production Plant

Ballintaggart Ringaskiddy

Affected by this application?

Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.

Make a Submission or Objection

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.