ALTCOR & MEENAGRANOGE , INVER , CO DONEGAL
CONDITIONALPlanning application 2350033
Donegal - Donegal County Council
Proposed Development
AMENDMENTS TO THE DEVELOPMENT PERMITTED UNDER AN BORD PLEANÁLA REF. 308419-20 (PLAN REF. NO. 20/51028 REFERS) FOR THE CONSTRUCTION OF A NEW ON-SITE 38 KV AND 20KV SUBSTATION AND ALL ASSOCIATED WORKS WITHIN THE CONSENTED RED LINE BOUNDARY
View the full application file on the council's planning portal →Application Timeline
Application received
17 Jan 2023
Decision: CONDITIONAL
9 Mar 2023
Decision due
13 Mar 2023
Grant issued
14 Apr 2023
Application Details
- Location
- ALTCOR & MEENAGRANOGE , INVER , CO DONEGAL
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Donegal County Council
- Site Area
- 0.35 ha
Timeline
- Registration Date
- 17 January 2023
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 9 March 2023
- Grant Date
- 14 April 2023
- Permission Expires
- 1 January 2260
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
AMENDMENTS TO THE DEVELOPMENT PERMITTED UNDER AN BORD PLEANÁLA REF. 308419-20 (PLAN REF. NO. 20/51028 REFERS) FOR THE CONSTRUCTION OF A NEW ON-SITE 38 KV SUBSTATION AND ALL ASSOCIATED WORKS WITHIN THE CONSENTED RED LINE BOUNDARY
ALTCOR & MEENAGRANOGE , INVER , CO DONEGAL
ERECTION OF 3 NO. WIND TURBINES WITH A HUB HEIGHT UP TO 69M AND A MAXIMUM BLADE TIP HEIGHT UP TO 110M, UNDERGROUND CABLING, BORROW PIT, TOGETHER WITH ASSOCIATED ACCESS ROADS, HARDSTANDS, CLEARFELLING OF TREES AND SITE WORKS. THE DEVELOPMENT PROPOSES A GRID CONNECTION VIA AN ELECTRICAL CONNECTION INTO THE NEARBY KILLEN HILL 38KV SUB STATION CONSISTING OF C.1,245M OF UNDERGROUND DUCTED CABLE IN THE TOWNLANDS ALTCOR AND MEENAGRANOGE AND AN EXTENSION TO KILLIN HILL 38KV SUB STATION IN MEENAGRANOGE. A NATURA IMPACT STATEMENT ACCOMPANIES THIS APPLICATION
ALTCOR AND MEENAGRANOGE , INVER , DONEGAL PO
ERECTION OF 3 NO. WIND TURBINES WITH A HUB HEIGHT UP TO 69M AND A MAXIMUM BLADE TIP HEIGHT UP TO 110M, UNDERGROUND CABLING, BORROW PIT, TOGETHER WITH ASSOCIATED ACCESS ROADS, HARDSTANDS, CLEARFELLING APPROXIMATELY 2.488HA OF TREES AND SITE WORKS. THE DEVELOPMENT ALSO PROPOSES A GRID CONNECTION VIA AN ELECTRICAL CONNECTION INTO THE NEARBY KILLIN HILL 38kV SUB-STATION CONSISTING OF C.1,245M OF UNDERGROUND DUCTED CABLE IN THE TOWNLANDS OF ALTCOR AND MEENAGRANOGE, AND A 332.2M2 EXTENSION TO KILLIN HILL 38kV SUB-STATION IN MEENAGRANOGE. AN APPROPRIATE PERIOD OF 5 YEARS (I.E. DURATION OF THE PLANNING PERMISSION TO CONSTRUCT THE DEVELOPMENT) IS SOUGHT, WITH AN OPERATIONAL LIFE OF 30 YEARS AFTER THE DATE OF COMMISSIONING. AN ENVIRONMENTAL IMPACT ASSESSMENT REPORT AND NATURA IMPACT STATEMENT WILL ACCOMPANY THIS APPLICATION
ALTCOR AND MEENAGRANOGE , INVER , DONEGAL PO
2 NUMBER SHEEP AND CATTLE GRIDS WITH PEDESTRIAN ACCESS TO BE CONSTRUCTED OVER THE EXISTING ROADWAY THROUGH FARM AND ASSOCIATED SITE DEVELOPMENT WORKS
ALTCOR AND MEENAGRANOGE , INVER , DONEGAL PO
CONSTRUCTION OF AN EXTENSION CONSISTING OF LIVING ACCOMMODATION, EXTERNAL ACCESS WORKS AND ALL ASSOCIATED SITE WORKS
ALTCOR , INVER , DONEGAL PO
CONSTRUCTION OF AN EXTENSION CONSISTING OF LIVING ACCOMMODATION, EXTERNAL ACCESS WORKS AND ALL ASSOCIATED SITE WORKS
ALTCOR , INVER , DONEGAL PO
ERECTION OF ONE LATTICE TYPE METEOROLOGICAL MAST NOT EXCEEDING 74 METRES IN HEIGHT, UNDERGROUND ELECTRICAL CABLES AND ASSOCIATED WORKS
CLOGHERAVADDY , DONEGAL PO , CO. DONEGAL
ONE LATTICE TYPE METEOROLOGICAL MAST NOT EXCEEDING 74 METRES IN HEIGHT, UNDERGROUND ELECTRICAL CABLES AND ASSOCIATED WORKS TO BE IN PLACE FOR THE LIFE OF CLOGHERAVADDY WIND FARM
CLOGHERAVADDY , CO. DONEGAL
ERECTION OF AN EXTENSION TO THE REAR OF THE EXISTING DWELLING HOUSE AND ASSOCIATED SITE WORKS
ALTCOR , INVER , DONEGAL PO
ALTERATIONS TO DWELLING
CROAGH , DUNKINEELY , DONEGAL PO
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?