← Back to search

Fareplay Terminal 2, Road No.2 North Extension, Dublin Port, Dublin 1

GRANT PERMISSION

Planning application 3688/20

Dublin - Dublin City Council

Proposed Development

The proposed development consists of dismantling a portion of the Terminal 2 site including a redundant building and a repair shop which will allow new entrance gates and associated boundary works to be carried out to accommodate for two entrance lanes for retail commercial loading tankers. Existing equipment including pumps, samples room, lab, and dye tanks will be relocated as part of the works. A new 30m3 additive tank will be provided. The existing Vapour Recovery Unit in Terminal 2 will be refurbished. Improved information signage for drivers at entrance and loading gantry will be installed and new internal road markings will be painted to identify parking spaces. The Major Accidents Directive is applicable to the site and as such a significant modification assessment has been completed.

Application Timeline

  1. Application received

    5 Nov 2020

  2. Decision due

    8 Jan 2021

  3. Decision: GRANT PERMISSION

    8 Jan 2021

  4. Grant issued

    23 Feb 2021

Application Details

Location
Fareplay Terminal 2, Road No.2 North Extension, Dublin Port, Dublin 1
Applicant
N/A
Application Type
Permission
Planning Authority
Dublin City Council
Site Area
3581.71 ha

Timeline

Registration Date
5 November 2020
Status
Decision Notice Issued
Decision
GRANT PERMISSION
Decision Date
8 January 2021
Grant Date
23 February 2021

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

48m
WEB1471/26APPLICATION DECLARED INVALID2 Mar 2026

The development consists of constructing a pipe bridge with an approximate overall height of 8m with associated concrete supports, to allow new pipelines and cables to be routed between two yards. This pipe bridge will span between the Circle K Terminal, and the pipe track on the opposite side of 2 Branch Road North Ext., outside TOP Yard 1, located in Dublin Port. Signs informing of the clearance height beneath the pipe bridge will also be installed on the bridge. A height restriction barrier with an accompanying sign informing of the clearance space beneath the pipe bridge will be installed over 2 Branch Road North Extension, south of the pipe bridge.

No. 2 Branch Road North Extension, Dublin Port, Dublin 3. The site is adjacent to Promenade Road and Tolka Quay Road.

48m
WEB1703/26APPLICATION DECLARED INVALID26 Mar 2026

The development consists of constructing a pipe bridge with an approximate overall height of 8m with associated concrete supports, to allow new pipelines and cables to be routed between two yards. This pipe bridge will span between the Circle K Terminal, and the pipe track on the opposite side of 2 Branch Road North Ext., outside TOP Yard 1, located in Dublin Port. Signs informing of the clearance height beneath the pipe bridge will also be installed on the bridge. A height restriction barrier with an accompanying sign informing of the clearance space beneath the pipe bridge will be installed over 2 Branch Road North Extension, south of the pipe bridge.

No. 2 Branch Road North Extension, Dublin Port, Dublin 3

48m
WEB1431/26APPLICATION DECLARED INVALID26 Feb 2026

The development consists of constructing a pipe bridge with an approximate overall height of 8m with associated concrete supports, to allow new pipelines and cables to be routed between two yards. This pipe bridge will span between the Circle K Terminal, and the pipe track on the opposite side of 2 Branch Road North Ext., outside TOP Yard 1, located in Dublin Port. Signs informing of the clearance height beneath the pipe bridge will also be installed on the bridge. A height restriction barrier with an accompanying sign informing of the clearance space beneath the pipe bridge will be installed over 2 Branch Road North Extension, south of the pipe bridge.

Circle K Terminal , Promenade Road , No 2 Branch Road, North Extension, Dublin Port, Dublin 3

48m
WEB2056/26GRANT PERMISSION1 May 2026

The development consists of constructing a pipe bridge with an approximate overall height of 8m with associated concrete supports, to allow new pipelines and cables to be routed between two yards. This pipe bridge will span between the Circle K Terminal, and the pipe track on the opposite side of 2 Branch Road North Ext., outside TOP Yard 1, located in Dublin Port. Signs informing of the clearance height beneath the pipe bridge will also be installed on the bridge. A height restriction barrier with an accompanying sign informing of the clearance space beneath the pipe bridge will be installed over 2 Branch Road North Extension, south of the pipe bridge.

No. 2 Branch Road North Extension, Dublin Port, Dublin 3

140m
3733/20GRANT PERMISSION13 Nov 2020

The development will consist of the installation of a new bitumen storage tank of 30m in diameter and 19.2m in height with a volume of approximately 11,300m3 and the installation of an aromatic oil tank of 8m in diameter and 12.8m in height with a volume of approximately 600m3. A concrete containment area will also be installed around the perimeter of the proposed tanks.

Lagan Materials Ltd. site, Alexandra Road, Dublin Port, Dublin 1, D01 DK64

165m
4115/19GRANT PERMISSION1 Oct 2019

The development will consist of the removal of a redundant fire water storage tank of 7.6m in diameter and 7.5m in height with a volume of approximately 340m3 and the installation of a new bitumen storage tank of 3.37m in diameter and 17.3m in height with a volume of approximately 100m3.

Lagan Materials Ltd., Alexandra Road, Dublin Port, Dublin 1

167m
3671/21GRANT PERMISSION11 Oct 2021

Planning permission for development at the following adjacent sites: Top Oil Yard 1, Promenade Road, Parish of Saint Thomas, Dublin Port, Dublin 3, D03 HK83. Top Oil Yard 2, Tolka Quay Road, Dublin Port. Circle K Yard 2, Tolka Quay Road, Dublin Port. The sites are adjacent to Tolka Quay Road, Promenade Road and 2 Branch Road North Extension. The development consists of constructing two pipebridges with a maximum height of 8.5m to allow new pipework and cables to be routed between the yards. Pipebridge No. 1 will be between Top Oil Yard 1 and the neighbouring Fareplay Yard 2. Pipebridge No. 2 will be between the Top Oil Yard 2 and the neighbouring Fareplay Yard 2. A small concrete shelter in Fareplay Yard 2 is to be dismantled to allow room for pipebridge supports.

Top Oil Yard 1, Promenade Road, Parish of Saint Thomas, Dublin Port, Dublin 3, D03 HK83

206m
WEB2500/24GRANT PERMISSION14 Nov 2024

For development at this site at the former Trim Transport Ltd yard, Tolka Quay Road, Dublin Port, Dublin 1, D01 H977. The subject site comprises of c. 0.147ha within the overall former Trim Transport Ltd site. The development will consist of: •The construction of a single storey modular office building (180sqm) with 2 no. solar photovoltaic panel arrays at roof level and external heat pumps to the rear; •The provision of a storage container (28sqm) to accommodate ancillary storage and a secure sheltered bicycle store; •The provision of site lighting and utility connections;•The replacement of existing access gates with a new 2.25m high vehicular double swing gate and a new 2.25m high pedestrian double swing gate with a 2.5m high concrete wall panel and pier;•The provision of a 2.5m high chain link fence along the northern boundary;•Repairs to / renewal of existing boundary treatments where required; and; •The provision of ancillary car parking, landscaping, servicing and all associated site works.

Former Trim Transport Ltd Yard, Tolka Quay Road, Dublin Port, Dublin 1

338m
WEB2680/24APPLICATION DECLARED INVA10 Dec 2024

The replacement of approximately 52 m of existing 2.4 m high chainlink perimeter fencing and associated access / emergency gates with new 2.4 m high security fencing, gates, 2 no. 8 m CCTV poles and all associated site works.

North Wall Above Ground Installation (AGI), Alexandra Rd, North Wall, Dublin 1

338m
WEB2709/24APPLICATION DECLARED INVA13 Dec 2024

The replacement of approximately 52 m of existing 2.4 m high chainlink perimeter fencing and associated access / emergency gates with new 2.4 m high security fencing, gates, 2 no. 8 m CCTV poles and all associated site works.

Alexandra Road, North Wall, Dublin 1