← Back to search

18/19, Merchant's Quay, Dublin 8, D08 CC90

REFUSE PERMISSION

Planning application 3705/23

Dublin - Dublin City Council

Proposed Development

PROTECTED STRUCTURE: The development will consist of proposed change of use of 18 and 19 Merchant's Quay from Office use of the Ground Floor and 3 Residential Accommodation units on the 1st, 2nd and 3rd floors overhead to Hostel (tourist) use with modifications to existing rear flat roof, amenity space at roof level, associated internal modification works and all associated site works and services.

Application Timeline

  1. Application received

    5 May 2023

  2. Decision: REFUSE PERMISSION

    27 Jun 2023

  3. Decision due

    29 Jun 2023

  4. Appeal submitted

    25 Jul 2023

  5. Grant issued

    19 Mar 2024

  6. Appeal decided: GRANT PERMISSION

    19 Mar 2024

Application Details

Location
18/19, Merchant's Quay, Dublin 8, D08 CC90
Applicant
N/A
Application Type
Permission
Planning Authority
Dublin City Council
Site Area
243 ha

Timeline

Registration Date
5 May 2023
Status
Appeal Decided
Decision
REFUSE PERMISSION
Decision Date
27 June 2023
Grant Date
19 March 2024

An Coimisiún Pleanála Appeal

Appeal Reference
ABP-317636-23
Decision
GRANT PERMISSION
Submitted
25 July 2023
Decided
19 March 2024

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

0m
5337/22REFUSE PERMISSION1 Dec 2022

PROTECTED STRUCTURE: permission for proposed change of use of 151 sq.m. from permitted office use to hostel (tourist) use (and associated works) at ground floor level of 18/19 Merchants Quay, Dublin D08CC90 (a protected structure), including modification to existing rear flat roof and associated internal modifications.

18/19 Merchants Quay, Dublin 8, D08 CC90

0m
2702/20GRANT PERMISSION14 May 2020

PROTECTED STRUCTURE: Planning permission for proposed change of use of 151 sq.m. from office to medical centre use (and associated works) at ground floor level of 18 -19 Merchants Quay, Dublin D08 CC90 (a protected structure), also new rooflight to rear flat roof, and associated internal modifications.

18 -19 Merchants Quay, Dublin 8, D08CC90

19m
3905/19GRANT PERMISSION2 Sept 2019

The development provides for the following alteration to the front facade of the building only; replacement of the existing steel access gate with a new steel gate featuring separate pedestrian-only access, addition of glazed tiling to the existing gate surrounds, addition of a painted render finish to brick facade sections, addition of glazed patterned tiling to window spandrels above first and second floor, new steel balconies to second and third floor and associated works.

Marshalsea Court, 22/23, Merchant's Quay, Dublin 8

40m
4792/19GRANT PERMISSION20 Dec 2019

PROTECTED STRUCTURE: planning permission for the development at the facade facing onto Merchant's Quay is a Protected Structure Ref 5083. The development provides for the following alterations to the rear of the building: 1) the addition of 2 no. entrances to both side elevations at the rear. These will include 2 new glazed doors and 2 new windows. 2) the addition of a new external entrance ramp and stairs to the western elevation at the rear of the building. 3) associated internal works to provide access from the building to adjoining courtyards.

Merchants Court, 24, Merchant's Quay, Dublin 8

41m
WEB2509/26APPLICATION DECLARED INVALID17 Jun 2026

PROTECTED STRUCTURE: Planning Permission for the development at Merchants Court (the facade facing onto Merchant's Quay is a Protected Structure Ref 5083). The development provides for the following alterations to the rear of the building: 1) the addition of 2 no. external entrances to both side elevations at the rear. These will include 2 new glazed doors and 2 new windows. 2) the addition of a new external entrance ramp, steps and associated handrails/balustrading to the western elevation at the rear of the building. 3) The demolition of internal walls and screens to rear of property to facilitate the two proposed access points and circulation areas 4) associated internal works comprising steps and ramps to provide access from the building to adjoining courtyards

Merchants Court, 24 Merchant's Quay, Dublin 8

41m
WEB2544/26Registered Application22 Jun 2026

PROTECTED STRUCTURE: Planning Permission for the development at Merchants Court (the facade facing onto Merchant's Quay is a Protected Structure Ref 5083). The development provides for the following alterations to the rear of the building: 1) the addition of 2 no. external entrances to both side elevations at the rear. These will include 2 new glazed doors and 2 new windows. 2) the addition of a new external entrance ramp, steps and associated handrails/balustrading to the western elevation at the rear of the building. 3) The demolition of internal walls and screens to rear of property to facilitate the two proposed access points and circulation areas 4) associated internal works comprising steps and ramps to provide access from the building to adjoining courtyards

Merchants Court, 24 Merchant's Quay, Dublin 8

46m
WEB5484/25APPLICATION DECLARED INVALID23 Oct 2025

Merchants Quay Ireland (Homeless & Drugs Services) intend to apply for permission for development at 13/14 Merchants Quay (Riverbank Building), Dublin 8, D08 KT61. Permission is sought for the permanent change of use of previously vacant basement to a Medically Supervised Injecting Facility together with its associated access, operational management, and ancillary support services as previously granted on a temporary basis under Reg. Ref. 4121/18 / ABP-312618-22 at the basement level at 13/14 Merchants Quay (Riverbank Building), Dublin 8. No alterations or further works are proposed as part of this application.

13/14, Merchant's Quay (Riverbank Building), Dublin 8

46m
WEB5521/25GRANT PERMISSION28 Oct 2025

Merchants Quay Ireland (Homeless & Drugs Services) intend to apply for permission for development at 13/14 Merchants Quay (Riverbank Building), Dublin 8, D08 KT61. Permission is sought for the permanent change of use of previously vacant basement to a Medically Supervised Injecting Facility together with its associated access, operational management, and ancillary support services as previously granted on a temporary basis under Reg. Ref. 4121/18 / ABP-312618-22 at the basement level at 13/14 Merchants Quay (Riverbank Building), Dublin 8. No alterations or further works are proposed as part of this application.

13/14 Merchants Quay (Riverbank Building) , Dublin 8

46m
3175/23GRANT PERMISSION7 Feb 2023

PROTECTED STRUCTURE: the development will consist of the creation of a new ope in the party wall separating Merchant's Court & Merchant's Hall at ground floor level.

Merchant's Court - 24 Merchant's Quay (a protected structure), Dublin 8, D08 X7YK and Merchant's Hall - 25-26 Merchant's Quay, Dublin 8, D08 NT3K

64m
3934/22APPLICATION DECLARED INVA10 May 2022

The development will consist of: The creation of a new ope in the party wall separating Merchant's Hall & Merchant's House at ground floor level.

Merchant's Hall, 25/26 Merchant's Quay, Dublin 8, (D08 NT3K) and Merchant's House, 27-30 Merchant's Quay, Dublin 8. (D08 K3KD)