← Back to search

Marshalsea Court, 22/23, Merchant's Quay, Dublin 8

GRANT PERMISSION

Planning application 3905/19

Dublin - Dublin City Council

Proposed Development

The development provides for the following alteration to the front facade of the building only; replacement of the existing steel access gate with a new steel gate featuring separate pedestrian-only access, addition of glazed tiling to the existing gate surrounds, addition of a painted render finish to brick facade sections, addition of glazed patterned tiling to window spandrels above first and second floor, new steel balconies to second and third floor and associated works.

Application Timeline

  1. Application received

    2 Sept 2019

  2. Decision: GRANT PERMISSION

    23 Oct 2019

  3. Decision due

    25 Oct 2019

  4. Grant issued

    3 Dec 2019

Application Details

Location
Marshalsea Court, 22/23, Merchant's Quay, Dublin 8
Applicant
N/A
Application Type
Permission
Planning Authority
Dublin City Council
Site Area
1250.01 ha

Timeline

Registration Date
2 September 2019
Status
Decision Notice Issued
Decision
GRANT PERMISSION
Decision Date
23 October 2019
Grant Date
3 December 2019

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

19m
5337/22REFUSE PERMISSION1 Dec 2022

PROTECTED STRUCTURE: permission for proposed change of use of 151 sq.m. from permitted office use to hostel (tourist) use (and associated works) at ground floor level of 18/19 Merchants Quay, Dublin D08CC90 (a protected structure), including modification to existing rear flat roof and associated internal modifications.

18/19 Merchants Quay, Dublin 8, D08 CC90

19m
3705/23REFUSE PERMISSION5 May 2023

PROTECTED STRUCTURE: The development will consist of proposed change of use of 18 and 19 Merchant's Quay from Office use of the Ground Floor and 3 Residential Accommodation units on the 1st, 2nd and 3rd floors overhead to Hostel (tourist) use with modifications to existing rear flat roof, amenity space at roof level, associated internal modification works and all associated site works and services.

18/19, Merchant's Quay, Dublin 8, D08 CC90

19m
2702/20GRANT PERMISSION14 May 2020

PROTECTED STRUCTURE: Planning permission for proposed change of use of 151 sq.m. from office to medical centre use (and associated works) at ground floor level of 18 -19 Merchants Quay, Dublin D08 CC90 (a protected structure), also new rooflight to rear flat roof, and associated internal modifications.

18 -19 Merchants Quay, Dublin 8, D08CC90

21m
4792/19GRANT PERMISSION20 Dec 2019

PROTECTED STRUCTURE: planning permission for the development at the facade facing onto Merchant's Quay is a Protected Structure Ref 5083. The development provides for the following alterations to the rear of the building: 1) the addition of 2 no. entrances to both side elevations at the rear. These will include 2 new glazed doors and 2 new windows. 2) the addition of a new external entrance ramp and stairs to the western elevation at the rear of the building. 3) associated internal works to provide access from the building to adjoining courtyards.

Merchants Court, 24, Merchant's Quay, Dublin 8

22m
WEB2509/26APPLICATION DECLARED INVALID17 Jun 2026

PROTECTED STRUCTURE: Planning Permission for the development at Merchants Court (the facade facing onto Merchant's Quay is a Protected Structure Ref 5083). The development provides for the following alterations to the rear of the building: 1) the addition of 2 no. external entrances to both side elevations at the rear. These will include 2 new glazed doors and 2 new windows. 2) the addition of a new external entrance ramp, steps and associated handrails/balustrading to the western elevation at the rear of the building. 3) The demolition of internal walls and screens to rear of property to facilitate the two proposed access points and circulation areas 4) associated internal works comprising steps and ramps to provide access from the building to adjoining courtyards

Merchants Court, 24 Merchant's Quay, Dublin 8

22m
WEB2544/26Registered Application22 Jun 2026

PROTECTED STRUCTURE: Planning Permission for the development at Merchants Court (the facade facing onto Merchant's Quay is a Protected Structure Ref 5083). The development provides for the following alterations to the rear of the building: 1) the addition of 2 no. external entrances to both side elevations at the rear. These will include 2 new glazed doors and 2 new windows. 2) the addition of a new external entrance ramp, steps and associated handrails/balustrading to the western elevation at the rear of the building. 3) The demolition of internal walls and screens to rear of property to facilitate the two proposed access points and circulation areas 4) associated internal works comprising steps and ramps to provide access from the building to adjoining courtyards

Merchants Court, 24 Merchant's Quay, Dublin 8

29m
3175/23GRANT PERMISSION7 Feb 2023

PROTECTED STRUCTURE: the development will consist of the creation of a new ope in the party wall separating Merchant's Court & Merchant's Hall at ground floor level.

Merchant's Court - 24 Merchant's Quay (a protected structure), Dublin 8, D08 X7YK and Merchant's Hall - 25-26 Merchant's Quay, Dublin 8, D08 NT3K

48m
3934/22APPLICATION DECLARED INVA10 May 2022

The development will consist of: The creation of a new ope in the party wall separating Merchant's Hall & Merchant's House at ground floor level.

Merchant's Hall, 25/26 Merchant's Quay, Dublin 8, (D08 NT3K) and Merchant's House, 27-30 Merchant's Quay, Dublin 8. (D08 K3KD)

48m
4003/22GRANT PERMISSION18 May 2022

Development will consist of : The creation of a new ope in the party wall separating Merchant's Hall & Merchant's House at ground floor level.

Merchant's Hall , 25/26, Merchants Hall, Merchant's Quay, Dublin 8 (D08 NT3K) and Merchant's House, 27/30 Merchant's Quay, Dublin 8 (D08 K3KD)

60m
3083/24GRANT PERMISSION24 Jan 2024

The development will consist of (i) partial change of use of the northern portion of ground floor level from office space to a bicycle showroom facility; (ii) internal reconfiguration including the provision of a new ope to the east to allow access to the buildings central portion, extinguishment of existing internal ope to the south and provision of internal bicycle storage space; and, (iii) all associated works necessary to facilitate the development.

Bond House, 9-10 Bridge Street Lower, Dublin 8, D08TH76

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?