← Back to search

Chestnut House , Millennium Park Obsertown , Naas

CONDITIONAL

Planning application 2460439

Kildare - Kildare County Council

Proposed Development

for the permanent retention of 189 car parking spaces (as previously granted under Planning Permission: 07500092) including the existing site lighting, landscape works and all ancillary site development works on the site

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    17 May 2024

  2. Decision: CONDITIONAL

    3 Jul 2024

  3. Decision due

    11 Jul 2024

  4. Grant issued

    12 Aug 2024

Application Details

Location
Chestnut House , Millennium Park Obsertown , Naas
Applicant
N/A
Application Type
RETENTION
Planning Authority
Kildare County Council
Site Area
0.465 ha

Timeline

Registration Date
17 May 2024
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
3 July 2024
Grant Date
12 August 2024
Permission Expires
11 August 2029

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

47m
2460405N/A7 May 2024

for the permanent retention of 189 car parking spaces (as previously granted under Planning Permission: 07500092) including the existing site lighting, landscape works and all ancillary site development works on the site

Chestnut House , Millennium Park Obsertown , Naas

93m
20806N/A23 Jul 2020

The construction of a 5627 square metre Specialist Packaging single storey high level manufacturing facility with three storey head office incorporating, administration, sales, design, research and development departments, staff changing room, staff canteen, car parking, bicycle parking, ESB sub station, two storey services plant room, loading bay, entrance gates, pedestrian gate, building signage, landscaping, extension to existing estate service road and all associated siteworks on a site of 2.5672 hectatres

Millennium Business Park , Osberstown , Naas

105m
21246CONDITIONAL2 Mar 2021

Extension of Duration of Planning Ref. 15/850 - The development will consist of a new four storey office building of approx 5,574 sq.m gross floor area(excluding plant) with a set back at fourth storey level ( and an external terraced area on all elevations) as well as open and enclosed plant (approx. 153 sq.m) at roof level. The overall height of the proposed office building (including plant) is approx. 17.8 m. The proposal will provide ancillary facilities including a reception area, toilets, showers, stores, lift cores, internal stairs and external stair cores to the northeast and southwest facades; and an ESB substation, switch room and refuse building (with an overall area of approximately 42 sq.m). Permission is also sought for 280 surface car parking spaces, 30 covered cycle parking spaces, internal road and footpaths, a new vehicular access and a separate pedestrian access from existing Millennium Park Site Distributor Road on the southeast side of the site and a second pedestrian access point on the southwest side of the site from the Western Distributor Road, hard/soft landscaping, lighting and associated site development works; all on a site of approx. 1.57 hectares

Site D5 , Millennium Business Park , Naas

109m
211728CONDITIONAL8 Dec 2021

(a) Erection of a two storey office/laboratories building with reception entrance area, staff toilets, shower room with goods-in delivery area and storage on ground floor with managers office and staff canteen facilities and staff toilets on first floor. (b) The installation of new foul sewer and surface water sewer and connection into the existing Millennium Park drainage system and connection into the existing water mains. (c) Permission is also sought for 27 surface car parking spaces including 4 E-Car charging points, 20 covered cycle parking spaces, delivery area and turning area on south east elevation and all site drainage/site development works

Millennium Park , Osberstown , Naas

118m
20561CONDITIONAL4 Jun 2020

(a) Erection of a two storey office/laboratories building with reception entrance area, staff toilets, shower room with goods-in delivery area and storage on ground floor with managers office and staff canteen facilities and staff toilets on first floor. (b) the installation of new foul sewer and surface water sewer and connection into the existing Millennium Park drainage system and connection into the existing watermains. (c) Permission is also sought for 27 surface car parking spaces with 3 E car charging points, 20 covered cycle parking spaces, delivery area and turning area on south east elevation and (d) Permissions to extend the existing distributor road consisting of new vehicular access road with footpath on both sides and Cycle lane and all site drainage/site development works

Millennium Park , Osberstown , Naas

120m
20521N/A26 May 2020

(a )Erection of a two storey office/laboratories building with reception entrance area, staff toilets, shower room with goods-in delivery area and storage on ground floor with manager’s office and staff canteen facilities and staff toilets on first floor; (b) The installation of new foul sewer and surface water sewer and connection into the existing Millennium Park drainage system and connection into the existing watermains; (c) Permission is also sought for 27 surface car parking spaces with 3 E car charging points, 20 covered cycle parking spaces, delivery area and turning area on south east elevation and (d) Permission to extend the existing distributor road consisting of new vehicular access road with footpath on both sides and cycle land and all site drainage/site development works

Millennium Park , Osberstown , Naas

127m
201564CONDITIONAL18 Dec 2020

(a) Extension of the existing 7.3m wide two-lane carriageway by 137m to the north (b) Provision of a 2m grass verge, 2m cycle path and 2m footpath along the east and west of the proposed access road extension (c) provision of a vehicular entrance to the west of the proposed extension to facilitate a proposed access to a planned commercial development (Kildare Co. Co. Planning Ref. 20840) (d) provision of a vehicular entrance to the east of the proposed extension to facilitate a proposed access to a planned commercial development (Kildare Co. Co. Planning Ref. 20561) (e) provision of surface water, foul drainage and watermain services along the 137m length of proposed extension which shall serve a further future road extension to the north and shall connect to the existing 900mm dia. Millennium Park surface water sewers to the north west (f) provision of a raised shared tabletop on the existing internal road to the south at the entrance to the permitted Kildare Co. Co. Planning Ref. 07500092 Osberstown Developments Limited 189 car parking space temporary car parking serving existing Block D9 (g) Upgrading 475m of the existing 2m wide footpath to the south of the proposed extension to incorporate new 2m wide cycle tracks and 2m wide footpaths either side of the road with associated uncontrolled crossings and the provision of all associated road markings and signage

Millennium Park , Osberstown , Naas

180m
18751CONDITIONAL22 Jun 2018

the demolition of an existing bungalow to provide for a new one and a half storey five bedroom dwelling house, new effluent treatment system, new garage and all associated site development works

Grove House , Osberstown , Naas

188m
20840CONDITIONAL30 Jul 2020

the construction of a 5627 square metre Specialist Packaging Single Storey High Level Manufacturing Facility with Three Storey Head office incorporating, administration, sales, design, research and development departments, staff changing room, staff canteen, car parking, bicycle parking, ESB sub station, two storey services plant room, loading bay, entrance gates, pedestrian gate, building signage, landscaping, extension to existing estate service road and all associated siteworks on a site of 2.5672 hectares

Millennium Business Park , Osberstown , Naas

189m
171205REFUSED27 Oct 2017

the demolition of an existing bungalow to provide for a new one and a half storey five bedroom dwelling house, new effluent treatment system, new garage and all associated site development works

Grove House , Osberstown , Naas