Courttown East and West , Athy , Co. Kildare
CONDITIONALPlanning application 2561366
Kildare - Kildare County Council
Proposed Development
permission to construct a Soiled water / Slurry lagoon, Planning permission to erect a meal storage bin and associated site work
View the full application file on the council's planning portal →Application Timeline
Application received
3 Dec 2025
Further information requested
27 Jan 2026
Further information received
13 Jul 2026
Decision: CONDITIONAL
7 Aug 2026
Decision due
9 Aug 2026
Application Details
- Location
- Courttown East and West , Athy , Co. Kildare.
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Kildare County Council
- Site Area
- 3.89 ha
Timeline
- Registration Date
- 3 December 2025
- Status
- DECISION MADE
- Decision
- CONDITIONAL
- Decision Date
- 7 August 2026
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
to construct an A-roof, cow cubicle shed (agricultural building), concrete feed passage and associated site work
Courtown East and West , Athy , Co. Kildare.
Extension of Duration of Planning Ref. 08/48 - construction of a storey and a half type dwelling, garage and to install a mechanical aeration unit and soil polishing filter and all ancillary site works
Churchtown North , Athy , Co. Kildare.
Extension of Duration of 08/48 comprising construction of a storey and a half type dwelling, garage and to install a mechanical aeration unit and soil polishing filter and all ancillary site works
Churchtown North , Athy , Co Kildare
A. Constructing a part single storey, part 2 storey dwelling, B. Constructing a single storey garage C. Installation of a new wastewater treatment system & polishing filter D. Construction of a new vehicular entrance and all ancillary site works
Churchtown , Athy , Co. Kildare.
to construct an A-Roof shed (agricultural building), concrete feed passage, concrete apron/dung storage and associated site work. Revised by significant further information consisting of; an upgrade/relocation of existing entrance and site boundary increased
Castlemitchell , Athy , Co. Kildare.
of an existing domestic storage shed and retention of existing shared recessed entrance
Churchtown , Athy , Co. Kildare.
an existing domestic storage shed & retention of existing shared recessed entrance
Churchtown , Athy , Co. Kildare.
of single storey extension to the rear of existing cottage and alterations to front elevation
Butterfly Cottage , Churchtown , Co. Kildare R14 YN12.
to amend the design of the approved development (Planning Reference 16/1007). Permission is also sought to amend the lifespan of the consented development from 27 years to 35 years. The development will consist of ground mounted solar panel photovoltaic (PV) farm to generate renewable electricity on a 12.02ha site, comprising solar arrays, associated electrical infrastructure, fencing, access improvements and ecologically beneficial landscape works at Moatstown Development Site, Milltown, Athy, Co. Kildare, ITM Grid Reference 665656, 696962, subject to 17 conditions. Amendments proposed are: No changes to red line boundary and no changes to perimeter fence or CCTV points; The height of the solar panels has been increased slightly from 2.3m to 2.5m, their angle span amended from 20-30 degrees to 10-40 degrees. Panels layout has been slightly reconfigured to account for the changes in the height. A slight increase in the overall land take from solar panels; Changes in land take for new access tracks from 3,500sqm to 1,890sqm; Temporary compound area to be moved 60m southwest, but will retain its overall size of 2,800sqm with slight alteration to its overall shape. Compound will be reinstated at the end of the construction phase; Energy Storage Area will be enlarged from 750sqm to 1,265sqm, an increase of 515sqm; Changes from four substations/energy storage containers and one grid connection point to two substations with larger areas of hardstanding and a grid connection point. The land take from the proposed changes is expected to change from 774sqm to 940sqm, an increase of 166sqm; overall decrease in ground disturbance/land take is expected to be approximately 929sqm.
Moatstown , Milltown , Athy
Extension of Duration of Planning Ref. 16/1007 - a temporary (27 years) ground-mounted solar photovoltaic (PV) farm to generate renewable electricity on a 12.02ha site, comprising solar arrays, associated electrical infrastructure, fencing, access improvements and ecologically beneficial landscape works
Moatstown Development Site , Milltown , Athy Co. Kildare.