sub-division of existing site for the construction of one No Two storey 3 bedroom house and one No two storey 2 bedroom house constructed as a pair of semi-detached houses, demolition of existing shed on site to facilitate the development, connection to public foul sewer and all associated site works. Revised by Significant further Information which consists of: Revised house types for each house, revised site layout plan, revised car parking and front boundary treatment and all associated site works

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    8 Apr 2026

  2. Further information requested

    29 May 2026

  3. Further information received

    28 Jun 2026

  4. Decision: CONDITIONAL

    28 Jul 2026

  5. Decision due

    29 Jul 2026

Application Details

Location
Rose Cottage , Liffey View , Newbridge
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Kildare County Council
Site Area
0.048 ha
Floor Area
131 sq m
Residential Units
2

Timeline

Registration Date
8 April 2026
Status
DECISION MADE
Decision
CONDITIONAL
Decision Date
28 July 2026

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

37m
20359CONDITIONAL8 Apr 2020

(a) further extension and modifications to previously permitted extension to side (south-east facing) elevation of existing dwelling house. Original extension was previously granted permission under Pl. Ref. 72/249. Modifications include replacing flat roof with lean-to type roof, window and door arrangement, internal layout and an additional c. 6.3 Sq/M of floor space towards the rear, (b) connection to existing site services and all associated development works

9 Liffey View , Newbridge , Co. Kildare.

67m
2560773CONDITIONAL9 Jul 2025

for the modification to existing pitch lighting, (previously granted under permissions 18/478 and 23/1009), to provide additional luminaires to existing lighting poles to achieve average pitch lighting of 1000Lux for televised GAA matches for a maximum of 6 occasions throughout the year

St. Conleths Park , Main Street Newbridge , Co. Kildare

98m
18478CONDITIONAL27 Apr 2018

(1) Demolition of the existing covered standbuilding, the club house, the scoreboard and section of the front boundary wall and turnstiles; (2) The construction of a new 2-storey covered stand building, with facilities within the stand, comprising spectator seating, players’ and officials’ changing areas, spectators’ concourses, circulation, toilet areas, first-aid administrative offices, multi-purpose room, VIP/meeting areas, hospitality and bar serving facilities; confectionery/snack-bar facilities, stores, plant room and associated ancillary areas: (3) Modification to external hard and soft landscaping; (4) Alteration to existing boundary treatment/external signage; (5) Alterations to the existing main entrance and provision of a new entrance plaza (adjacent to the public car park off Main Street), incorporating a single storey stand-alone ticket office (30 sqm) and turnstiles with associated hoardings and signage; (6) Re-instatement of access through the existing stone archway on Athgarvan Road, currently block-up, to provide pedestrian access; (7) Works to the playing pitch including the replacement of some of the existing pitch enclosures/ball netting and an increase of the playing field dimensions from 139m x 81.4m to approximately 143.5 x 83m; (8) Provision of new scoreboard; (9) Provision of flood lighting (3 No. lighting columns at 33.5m high and 1 No. column 27.4m high above pitch level); (10) Provision of associated support services and infrastructural works at the County GAA grounds,

St. Conleth's Park , Newbridge , Co. Kildare.

101m
171480CONDITIONAL22 Dec 2017

development at County GAA grounds which is to consist of the removal of an existing container and site clearance, provision of a new single storey temporary accommodation building (91sqm) containing new changing rooms and associated plant room, shower and toilet areas, minor alterations to internal site enclosures and associated site and drainage works

St. Conleth's Park , Newbridge , Co. Kildare.

111m
231009CONDITIONAL5 Dec 2023

Extension of Duration of Planning Ref. 18/478 which consists of (1) Demolition of the existing covered standbuilding, the club house, the scoreboard and section of the front boundary wall and turnstiles; (2) The construction of a new 2-storey covered stand building, with facilities within the stand, comprising spectator seating, players’ and officials’ changing areas, spectators’ concourses, circulation, toilet areas, first-aid administrative offices, multi-purpose room, VIP/meeting areas, hospitality and bar serving facilities; confectionery/snack-bar facilities, stores, plant room and associated ancillary areas: (3) Modification to external hard and soft landscaping; (4) Alteration to existing boundary treatment/external signage; (5) Alterations to the existing main entrance and provision of a new entrance plaza (adjacent to the public car park off Main Street), incorporating a single storey stand-alone ticket office (30 sqm) and turnstiles with associated hoardings and signage; (6) Re-instatement of access through the existing stone archway on Athgarvan Road, currently block-up, to provide pedestrian access; (7) Works to the playing pitch including the replacement of some of the existing pitch enclosures/ball netting and an increase of the playing field dimensions from 139m x 81.4m to approximately 143.5 x 83m; (8) Provision of new scoreboard; (9) Provision of flood lighting (3 No. lighting columns at 33.5m high and 1 No. column 27.4m high above pitch level); (10) Provision of associated support services and infrastructural works at the County GAA grounds,

St. Conleth's Park , Newbridge , Co. Kildare.

111m
2460185REFUSED4 Mar 2024

for the sub-division of existing family site for the construction of a detached dormer bungalow, connection to public foul sewer, utilisation of existing site entrance and all associated site works

Chapel Lane , Newbridge , Co. Kildare

125m
2460862CONDITIONAL2 Sept 2024

for the sub-division of existing family site for the construction of a detached bungalow, connection to public foul sewer, utilisation of existing site entrance and all associated site works

Chapel Lane , Newbridge , Co. Kildare

130m
20482N/A13 May 2020

the construction of a dormer bungalow, connection to existing foul sewer and all associated site works

Chapel Lane , Newbridge , Co. Kildare.

137m
171427N/A15 Dec 2017

the installation of a new pumped foul sewer line along Chapel Lane to serve existing house and all associated site works

The Cottage , Chapel Lane , Newbridge

142m
211388CONDITIONAL28 Sept 2021

for (a) demolition of existing single storey dwelling and outbuilding, (b) construction of 4no. two bedroomed apartments, and 4no. one bedroomed apartments in 2no. two storey blocks, (c) site development works on and below ground, including new access roadway, footpaths, car parking, landscaping, water network, foul and surface water drainage including surface water attenuation system, refuse storage areas, bicycle shelters. Revised by Significant Further Information which consists of alterations to proposed Apartment Block B including a reduction of units from 4no. to 3 no.

Athgarvan Road , Newbridge , Co. Kildare.