An extension to the existing access road and all associated infrastructure, including watermain, foul drainage network, pumping stations, stormwater drainage network and detention basin, electrical ducting, street lighting, footpaths, cycle tracks, landscaping and traffic signage. Phase 1 of these works was approved under planning application 18/360 in 2018, for which site works are now completed. The proposed scheme is a continuation of same and the development area is 4.59 Ha.
View the full application file on the council's planning portal →Application Details
- Location
- IDA Oakfield Business & Technology Park , Oakfield Sligo , Co. Sligo
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Sligo County Council
- Site Area
- 4.59 ha
Timeline
- Registration Date
- 20 December 2024
- Status
- INCOMPLETED APPLICATION
- Decision
- N/A
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
An extension to the existing access road and all associated infrastructure, including watermain, foul drainage network, pumping stations, stormwater drainage network and detention basin, electrical ducting, street lighting, footpaths, cycle tracks, landscaping and traffic signage. Phase 1 of these works was approved under planning application 18/360 in 2018, for which site works are now completed. The proposed scheme is a continuation of same and the development area is 4.59 Ha. The development has been subject of a Screening for Appropriate Assessment in accordance with Article 6(3) of the EU Habitats Directive (Directive 92/43/EEC) and the Planning and Development Act 2000 as amended. The Screening for Appropriate Assessment will be submitted with the Planning Application. The screening for Appropriate Assessment resulted in the requirement for a Natura Impact Statement (NIS) to be prepared in relation to the proposed development. The NIS will be submitted with the Planning Application.
IDA Oakfield Business & Technology Park , Oakfield Sligo , Co. Sligo
for development consisting of (a) retain and complete domestic garage on site currently constructed to ground floor level, (b) retain alterations to elevations of dwelling house as constructed on site, (c) retain location of dwelling house as built on site, together with all ancillary site works and services, (previous planning refs: PL13/366 and PL14/286)
Oakfield , Sligo
for site development works for future industrial/commercial development. The works will include site excavation, construction of a new site access road, new surface water and sanitary sewers , new watermain, new lighting and a new ESB substation at
Oakfield , Oakfield Road , Co. Sligo
Development consisting of a new Advance Technology Unit consisting of office and light industrial/production space. Permission is also sought for vehicular and pedestrian entrance to site, signage, new timber post and rail site boundaries, car parking, cycle shelters, landscaping, a gas skid, underground storage tank, ESB substation, switch room, access road and all associated site works, The development has been the subject of a Screening for Appropriate Assessment in accordance with Article 6(3) of the EU Habitats Directive (Directive 92/43/EEC) and the Planning and Development Act 2000 as amended. The Screening for Appropriate Assessment will be submitted to the Planning Authority with The Planning Application.
IDA Business & Technology Park , Oakfield , Sligo
development consisting of retention to alterations to front porch and velux roof window on front elevation to an existing dwelling.
Oakfield , Co Sligo , F91 K443
development consisting of the demolition of 2 existing external sheds, construction of new extensions and reconfigurations to the existing dwelling and all associated site works and services
1064 Oakfield Cottages , Oakfield , Co Sligo
for development consisting of (a) retain dwelling house as constructed in different location on a reduced site size as original planning permission PL 93/19125, (b) retain part of front boundary wall and property entrance as constructed which differs from original planning permission PL 93/19125, (c) decommission the existing septic tank and percolation area on site, (d) install a new waste water treatment system on site, (e) construct a new percolation area on land in the ownership of Sligo County Council
Twin Oaks , Oakfield , Co. Sligo
for development consisting of the refurbishment of an existing two storey house (approx. 66 sqm) including demolition of two flat roof extensions, construction of a single storey extension to the north and east of the existing house (approx. 120 sq.m) possibly to be built in two phases, including south facing rooflights, demolition of existing agricultural buildings on site, relocation of existing site entrance, provision of a new on site wastewater treatment system, landscaping and all associated site works
Oakfield House , Oakfield , Co. Sligo
construction of a new 2 storey dwelling house with a detached garage, together with a mechanical aeration system and associated percolation area, associated landscaping, boundary treatments, site works and services at Hill View
Carrowkeel , Ballisodare , Co Sligo
development consisting of the construction of a single storey domestic extension to the side of the existing domestic dwelling and all ancillary services
Carrowmore , Co. Sligo
Affected by this application?
Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.
Make a Submission or ObjectionPlanning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?