Proposed Development

Erection of a compact 110KV outdoor type Transformer Station, to include 5 masts, a switchgear building, transformer, ancillary 110KV structures and equipment, access road, fencing and landscaping.

View the full application file on the council's planning portal →

Application Timeline

  1. Further information requested

    16 Sept 1998

  2. Application received

    28 Jan 1999

  3. Further information received

    28 Jan 1999

  4. Decision: Grant Permission

    22 Feb 1999

  5. Decision due

    25 Mar 1999

  6. Grant issued

    9 Apr 1999

Application Details

Location
Citywest Business Campus, Naas Road, Co. Dublin.
Applicant
N/A
Application Type
Permission
Planning Authority
South Dublin County Council
Site Area
5943 ha
Floor Area
145 sq m

Timeline

Registration Date
28 January 1999
Status
Decision
Decision
Grant Permission
Decision Date
22 February 1999
Grant Date
9 April 1999

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

35m
SD10A/0339Granted15 Nov 2010

Alterations to the existing electrical transformer station to include: the installation of 110kV cable terminations; a new 110kV busbar section and switchgear; an extension to the inner palisade to accommodate HV cable termination; associated site works.

ESB Citywest 110kV, Electrical Transformer Station, Citywest Avenue, Citywest Business Park, Co. Dublin.

68m
SD20A/0219Granted9 Apr 2021

Residential development consisting of 99 dwellings comprised of 84 two storey houses, 15 apartments and duplex units accommodated in 2 three storey blocks; the proposed houses are comprised of 9 two bed houses, 71 three bed houses, 4 four bed houses; the proposed apartments & duplex units are comprised of 6 one bed units, 3 two bed units and 6 three bed units, also providing for all associated site development and infrastructural works, car and bicycle parking, ESB sub-station, open spaces and landscaping, bin and bicycle storage; access to the development via a new vehicular entrance on the western boundary of the site, off the existing access road to the Luas park & ride facility on a site area of 3.14ha bounded to the north by Citywest Avenue, located east of a permitted residential development known as Citywest Village and existing ESB sub-station and is north of the Luas red line.

Citywest, Tallaght, Dublin 24

81m
SD21A/0164Request Additional Information23 Jun 2021

20 dwellings comprised of 14 two storey detached and terraced houses and 6 apartments & duplex units accommodated in 1 three storey building, comprised of 6 two bed houses, 7 three bed houses & 1 four bed house; apartments & duplex units are comprised of 3 one bed ground floor units, 3 three bed units overhead; all associated site development works, car & bicycle parking, open spaces & landscaping, bin & bicycle storage; access to the proposed development will be via the permitted new vehicular entrance (under Ref. SD20A/0219) on the western boundary of the site, off the existing access road (known as The Walk) to the Luas park & ride facility; development site is adjacent to a permitted residential development under Ref. SD20A/0219 which is bounded to the north by Citywest Avenue, is located east of a permitted residential development known as Citywest Village & existing ESB sub-station, and is north of the Luas red line; the effect of the proposed development will also be a modification to an extant permission under Reg. Ref. SD20A/0219.

Citywest, Tallaght, Dublin 24

90m
SD25A/0255Granted16 Oct 2025

Permission to install a standby industrial diesel generator and solar panels. The generator will include a bunded fuel tank and be located within a mesh enclosure. The proposed solar panels will be attached to a steel frame to be erected adjacent to the generator ( Covering an area of approximately 32 sq.m, to a maximum height of 4.8 meters above ground level ). Works to include all ancillary development works, all located within an existing fenced compound.

ESB Telecoms Ltd Telecommunications Compound, ESBs Citywest 110kV Substation, Citywest Avenue, Citywest, Dublin

91m
SD14A/0175Granted21 Aug 2014

Construction of a 2.4m high palisade compound.

ESB Citywest 110 kV substation, Citywest Avenue, Citywest, Co. Dublin.

96m
SD18A/0303Granted1 Nov 2018

Construction of two cable interface masts and associated works, the laying of underground cable through existing ducting through Citywest Avenue to the existing Citywest 110kV substation and the removal of two double circuit intermediate towers and two single circuit end masts.

Lands south of Citywest Avenue, Brownsbarn, Citywest Business Park, Saggart, Co. Dublin

116m
S00A/0316Granted12 May 2000

Advance facility including two storey offices for industrial and related uses, with provision for sub-division into three units, ESB sub-station, extension of campus roads and associated site development works with access from new interchange on Naas Road

Unit 5040 Citywest Campus, Brownsbarn, Naas Road, Dublin 24

133m
SD09A/0305Granted21 Oct 2009

Infrastructural works consisting of a car park accommodating 68 no. cars, associated site works and signage forming part of the future development needs of Citywest Business Campus on a site of approximately 0.32 Ha adjoining both sides of the Tallaght / Saggart Luas line extension (under construction) which traverses the lands south of Citywest Avenue with access from a road being constructed under Rail Order 06S.NA0002 between Citywest Avenue (roundabout at the junction of Citywest Avenue and Lake Drive) and the proposed Citywest Luas Station.

Citywest Business Campus, South Of Citywest Avenue, Naas Road, Dublin 24

180m
LRD22A/0001Invalid Application16 Dec 2022

The development will consist of: I. 384 residential units with a cumulative gross floor area of 33,190.15 sq.m comprising: a) 122. houses, consisting of 28 two-bed units, 83 three-bed units and 11 four-bed units, ranging in height from 2-3 storeys. b) 84 duplex units, consisting of 48 one-bedroom units and 36 three-bedroom units, ranging in height from 2-3 storeys. c) 178 apartments consisting of 43 one bedroom units and 135 two-bedroom units, ranging in height from 5-7 storeys. II. tenant amenity floorspace with a gross floor area of 139 sq.m. III. 1.49 ha of public open space including a public plaza and 0.15 ha of communal amenity space; IV. the provision of a childcare facility with a gross floor area of 239 sq.m and associated play area; V. the provision of 361 car parking spaces, including 10 disabled parking spaces and 16 reserved for visitor parking and 3 reserved for creche staff. VI. the provision of 734 bicycle parking spaces, including 472 residents bicycle parking spaces and 262 visitor cycle spaces. VII. vehicular access is proposed via 3 access points including the existing Kingswood roundabout on Citywest Avenue to the north, The Walk to the west and from the park and ride access road at the eastern end of the site. Dedicated pedestrian/cyclist links are proposed throughout the site. VIII. ESB substation, 3 x ESB kiosks, rooftop solar photovoltaics, landscaping and all ancillary site and development works.

Lands south of Citywest Avenue and west of Cheeverstown Luas Park and Ride, Brownsbarn, Dublin 24

181m
LRD23A/0001Granted6 Jan 2023

The development will consist of: I. 384 residential units with a cumulative gross floor area of 33,190.15 sq.m comprising: a) 122. houses, consisting of 28 two-bed units, 83 three-bed units and 11 four-bed units, ranging in height from 2-3 storeys. b) 84 duplex units, consisting of 48 one-bedroom units and 36 three-bedroom units, ranging in height from 2-3 storeys. c) 178 apartments consisting of 43 one bedroom units and 135 two-bedroom units, ranging in height from 5-7 storeys. II. tenant amenity floorspace with a gross floor area of 139 sq.m. III. 1.49 ha of public open space including a public plaza and 0.15 ha of communal amenity space; IV. the provision of a childcare facility with a gross floor area of 239 sq.m and associated play area; V. the provision of 361 car parking spaces, including 10 disabled parking spaces and 16 reserved for visitor parking and 3 reserved for creche staff. VI. the provision of 734 bicycle parking spaces, including 472 residents bicycle parking spaces and 262 visitor cycle spaces. VII. vehicular access is proposed via 3 access points including the existing Kingswood roundabout on Citywest Avenue to the north, The Walk to the west and from the park and ride access road at the eastern end of the site. Dedicated pedestrian/cyclist links are proposed throughout the site. VIII. ESB substation, 3 x ESB kiosks, rooftop solar photovoltaics, landscaping and all ancillary site and development works.

Lands south of Citywest Avenue and west of Cheeverstown Luas Park and Ride, Brownsbarn, Dublin 24

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?