Units 26, 27, 41, 42 And 43, Cherry Orchard Industrial Estate, Dublin 10
GrantedPlanning application SD06A/1133
Dublin - South Dublin County Council
Proposed Development
Demolition of existing 920mm high brick pier and 2 metal rail fence along Ballyfermot Road and for the erection of a new 2.0 metre high galvanised metal security fence, including 2 no. 10.0 metre wide gates and 2 no. 6.0 metre wide gates to provide necessary security along their site boundary enclosing Units 26, 43, 42 and part of Units 41 and 27.
View the full application file on the council's planning portal →Application Timeline
Application received
22 Dec 2006
Decision: Grant Permission
21 Feb 2007
Decision due
24 Feb 2007
Grant issued
3 Apr 2007
Application Details
- Location
- Units 26, 27, 41, 42 And 43, Cherry Orchard Industrial Estate, Dublin 10.
- Applicant
- N/A
- Application Type
- Permission
- Planning Authority
- South Dublin County Council
- Site Area
- 14400 ha
Timeline
- Registration Date
- 22 December 2006
- Status
- Decision
- Decision
- Grant Permission
- Decision Date
- 21 February 2007
- Grant Date
- 3 April 2007
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Demolition of existing 920mm high brick pier and 2 metal rail fence along Ballyfermot Road and the erection of a new 2m high galvanised metal security fence, including 2 no. 10m wide gates and 2no. 6m wide gates to provide necessary security along the site boundary enclosing units 26, 43, 42 and part of units 41 and 27 at Cherry Orchard Industrial Estate, Dublin 10.
Cardinal Health, Unit 26, 27, 41, 42 & 43, Cherry Orchard Industrial Estate, Dublin 10
Retention of existing covered areas which link their five adjoining industrial units: (a) 253.0sq.m. single storey building linking Units 26 and 42 and 43 including demolition of east gable wall of Unit 42 and west gable wall of Unit 26. (b) 231.0sq.m. single storey covered yard area linking Units 26. 27, 41 and 42 with new enclosing walls along east and north sides. (c) 90.0sq.m. single storey general store along north wall of Unit 42 connected to two storey section with 35.0sq.m. metre ground floor locker room and first floor over 35.sq.m. metre tea station including external steel escape stairs with general construction and external finishes matching and not exceeding heights of the existing construction and drainage connections to existing local drains.
Cardinal Health, Unit 26, 27, 41, 42 and 43, Cherry Orchard Industrial Estate, Dublin 10.
a) Construction of a new first floor offices over existing ground floor offices at No. 26; b) Internal alterations to existing ground floor offices; c) New front and side elevational treatment to ground floor offices to include new metal cladding, relocation of front entrance and all new windows.
26/43, Cherry Orchard Industrial Estate, Ballyfermot, Dublin 10
a) Construction of a new first floor offices over existing ground floor offices at No. 26, (b) Internal alterations to existing ground floor offices, (c) New front and side elevational treatment to ground floor offices to include new metal cladding, relocation of front entrance and all new windows.
26/43, Cherry Orchard Industrial Estate, Ballyfermot, Dublin 10.
Retention of existing covered areas which link their five adjoining industrial units: (a) 253.0sq. metre single storey building linking Units 26 and 42 and 43 including demolition of east gable wall of Unit 42 and west gable wall of Unit 26; (b) 231.0sq. metre single storey covered yard area linking Units 26, 27, 41 and 42 with new enclosing walls along east and north sides; (c) 90.0 sq. metre single storey general store along north wall of Unit 42 connected to two storey section with 35.0 sq. metre ground floor locker room and first floor over 35.0sq.m. metre tea station including external steel escape stairs with general construction and external finishes matching and not exceeding heights of the existing construction and drainage connections to existing local drains.
Cardinal Health, Unit 26, 27, 41, 42 and 43 Cherry Orchard Industrial Estate, Dublin 10.
Extend industrial unit no. 27. The proposed works consist of a portal frame factory extension finished to match the existing building.
Unit No. 27, Cherry Orchard Industrial Estate, Ballyfermot, Dublin 10.
Construction of a new warehouse to north of existing warehouse all to match existing structures on site.
Unit 27, Cherry Orchard Industrial Estate, Ballyfermot, Dublin 10
Construction of a new two storey, low profile, extension at north of existing structures to contain new toilets and changing rooms at ground floor level and new canteen at first floor level to replace the existing temporary structures on site together with all associated site works and services; All works proposed are ancillary to the use of the existing building and business.
Unit 27, Cherry Orchard Industrial Estate, Ballyfermot, Dublin 10
Proposed erection of a 233.57sq.m single storey single bay extension with 9 daylight panels integrated into pitched roof of existing unit.
Unit 28a, Cherry Orchard Industrial Estate, Ballyfermot, Dublin 10, D10XF44
Erection of 90sq.m single storey, single-bay extension with 6 daylight panels integrated into pitched roof for light industrial use, located to the rear of existing unit.
Unit 28a, Cherry Orchard Industrial Estate, Ballyfermot, Dublin 10, D10XF44