← Back to search

Unit B17, Canal Turn, Clondalkin Industrial Estate, Clondalkin, Dublin 22

Granted

Planning application SD09A/0339

Dublin - South Dublin County Council

Proposed Development

Relocation of approved vehicular entrance to the western corner of the site boundary, an increase in the approved width of the entrance from 9m to 12m, and an extension of the existing roadside boundary wall and associated landscaping.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    27 Aug 2009

  2. Decision due

    21 Oct 2009

  3. Decision: Grant Permission

    21 Oct 2009

  4. Grant issued

    2 Dec 2009

Application Details

Location
Unit B17, Canal Turn, Clondalkin Industrial Estate, Clondalkin, Dublin 22.
Applicant
N/A
Application Type
Permission
Planning Authority
South Dublin County Council
Site Area
106.65 ha

Timeline

Registration Date
27 August 2009
Status
Decision
Decision
Grant Permission
Decision Date
21 October 2009
Grant Date
2 December 2009

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

1m
SD03A/0200Granted8 Apr 2003

Extension of 1845m.sq. to the existing meat processing facility in unit B17, linking to and incorporating Unit B16 into the facility, comprising marshalling, storage, plant rooms, waste area, canteen, toilets, dispatch office and ancillary works.

Tender Meats Ltd., 17B, Canal Turn, Clondalkin Industrial Estate, Clondalkin, Dublin 22

31m
S00A/0320Granted15 May 2000

2 number extensions to existing food processing facility for washing and storage at rear and side.

Unit B17, Canal Turn, Clondalkin Industrial Estate, Dublin 22.

86m
SD26A/0004WGrant Permission & Grant Retention8 Jan 2026

The proposed development includes retention permission for the reorientation of the gas AGI (above-ground installation) compound permitted under SDCC Reg. Ref.: SD23A/0158 and to retain an existing Gas AGI skid located to the north of the gas AGI compound. The development also includes the retention and completion of an extension to the existing Gas AGI compound to the south, to provide for a pressure regulating and metering station (PRMS) compound area. The PRMS compound extension comprises the following buildings and gas related infrastructure:•Skid House structure with a total area of c. 118 sq.m and overall height of c.3m. •E&I Kiosk with a total area of c. 11 sq.m and overall height of c. 2.7m •Boiler House comprising 2 no. individual units (Boiler House 1 & Boiler House 2) both with an area of c. 22 sq.m and overall height of c.3m. •Gas Quality Building with a total area of c. 3 sq.m and overall height of c. 2.4.m • All associated and ancillary works including valves and pipework, site lighting, boundary treatments, landscaping, drainage and infrastructure. The proposed development is located within a site which is subject to an EPA Industrial Emissions (IE) Directive license.

3-4, Crag Avenue, Clondalkin Industrial Estate, Clondalkin, Dublin 22

88m
ED20/0055Seek Clarification of Additional Information24 Feb 2021

Temporary compound to facilitate the diversion/undergrounding of existing ESB 38kV overhead lines and installation of new underground 110kV grid connections associated with development permitted under Reg Ref SD18A/0068 (as amended by Reg Ref. SD19A/0185).

3-4, Crag Avenue, Clondalkin Industrial Estate, Clondalkin, Dublin 12

89m
SD16A/0017Granted27 Jan 2016

Erection of 3 signs on buildings at their premises. This overall development was permitted under planning references SD13A/0096 & SD14A/0161.

Crag Terrace, Clondalkin Industrial Estate, Dublin 22

89m
SD13A/0096/EPGrant Extension of Duration of Permission26 Jul 2018

Demolition of all existing buildings on site (4,209sq.m.); part demolition of the existing concrete yard; construction of a new concrete yard and the change of use from a roof tile manufacturing plant to a metal recycling facility including the provision of a metal shearing machine (max. height 12.11m), control cabin tower (max. height 14.95m), materials handler machine mounted on a 5m high plinth and 2 no. stockpiles (max. height 7m); non-ferrous metal recovery building (962sq.m., max. height 14.15m) and covered yard (1685.5sq.m., max. height 14.15m) with weighbridge; depollutant reception yard and building (917.5sq.m., max. height 8.2m) for End of Life Vehicles (ELVs), including batteries/tyre store; workshop (390.5sq.m., max height 7.625m), 20,000 ltr gas oil tank and bund and washbay; two storey office building (378sq.m., max. height 8.658m); ESB substation (40sq.m.); store room (24sq.m.); MCC room (33sq.m.); 2 no. 18m weighbridges; 1.5m internal containment walls; 31 no. car parking spaces; 4 no. lorry parking spaces; 4m high inner security fencing; new drainage works including 2 no. attenuation tanks and 2 no. oil separators; new access off Crag Terrace including new gates and fencing and closure of existing access off Crag Avenue; all site development works and new landscaping works and boundary treatments all on a site of 2.36ha. An Environmental Impact Statement (EIS) has been prepared in respect of the Planning Application.

Crag Terrace & Crag Avenue, Clondalkin Industrial Estate, Clondalkin, Dublin 22.

89m
SD13A/0096Granted17 May 2013

Demolition of all existing buildings on site (4,209sq.m.); part demolition of the existing concrete yard; construction of a new concrete yard and the change of use from a roof tile manufacturing plant to a metal recycling facility including the provision of a metal shearing machine (max. height 12.11m), control cabin tower (max. height 14.95m), materials handler machine mounted on a 5m high plinth and 2 no. stockpiles (max. height 7m); non-ferrous metal recovery building (962sq.m., max. height 14.15m) and covered yard (1685.5sq.m., max. height 14.15m) with weighbridge; depollutant reception yard and building (917.5sq.m., max. height 8.2m) for End of Life Vehicles (ELVs), including batteries/tyre store; workshop (390.5sq.m., max height 7.625m), 20,000 ltr gas oil tank and bund and washbay; two storey office building (378sq.m., max. height 8.658m); ESB substation (40sq.m.); store room (24sq.m.); MCC room (33sq.m.); 2 no. 18m weighbridges; 1.5m internal containment walls; 31 no. car parking spaces; 4 no. lorry parking spaces; 4m high inner security fencing; new drainage works including 2 no. attenuation tanks and 2 no. oil separators; new access off Crag Terrace including new gates and fencing and closure of existing access off Crag Avenue; all site development works and new landscaping works and boundary treatments all on a site of 2.36ha. An Environmental Impact Statement (EIS) has been prepared in respect of the Planning Application.

Crag Terrace & Crag Avenue, Clondalkin Industrial Estate, Clondalkin, Dublin 22.

95m
SD10A/0174Granted16 Jun 2010

11.5m high water storage tank (capacity 520m3), and a new pump room (c. 17.5sq.m) to rear of existing warehouse and associated signage.

17, Crag Terrace, Clondalkin Industrial Estate, Dublin 22.

118m
SD18A/0342Refuse Permission for Retention24 Sept 2018

Retention sought for conversion of industrial unit to place of worship/church (456sq.m), new signage and associated works.

18/2, Canal Turn, Crag Terrace, Clondalkin, Dublin 22

123m
SD18A/0282Refuse Permission for Retention7 Aug 2018

Retention sought for conversion of 2 storey commercial unit to place of workship/church (430sq.m.), new signage and associated works.

18/2A Canal Turn, Crag Terrace, Clondalkin, Dublin 22

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?