Lisbrien , Nenagh , Co. Tipperary
CONDITIONALPlanning application 19600111
Tipperary - Tipperary County Council
Proposed Development
a solar PV panel array consisting of up to 22,500m2 of solar panels on ground mounted steel frames, 2 no. electricity control cabins, 4 no. inverter units, underground cable ducts, hard standing area, boundary security fence, site entrance, access track, landscaping, CCTV and all associated site works
Application Timeline
Application received
12 Feb 2019
Further information requested
2 Apr 2019
Further information received
25 Jul 2019
Decision: CONDITIONAL
15 Aug 2019
Decision due
21 Aug 2019
Appeal submitted
10 Sept 2019
Appeal decided: MODIFIED
22 Sept 2020
Application Details
- Location
- Lisbrien , Nenagh , Co. Tipperary
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Tipperary County Council
- Site Area
- 8.3 ha
Timeline
- Registration Date
- 12 February 2019
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 15 August 2019
- Permission Expires
- 21 September 2025
An Coimisiún Pleanála Appeal
- Appeal Reference
- ABP-305383-19
- Decision
- MODIFIED
- Submitted
- 10 September 2019
- Decided
- 22 September 2020
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
19600111 a solar PV panel array consisting of up to 22,500m2 of solar panels on ground mounted steel frames, 2 no. electricity control cabins, 4 no. inverter units, underground cable ducts, hard standing area, boundary security fence, site entrance, access track, landscaping, CCTV and all associated site works
Lisbrien , Nenagh , Co. Tipperary
RED III the development and operation of a solar photovoltaic (PV) farm with a total site area of 6.9 hectares comprising of the following – i) construction and operation of 22,500 sqm. of solar PV arrays on ground-mounted metal frames, with a maximum overall height of 4.7 metres, ii) Internal underground trenching, electrical cabling and ducting between the solar PV arrays and electrical invertor units, iii) 4 no. electrical invertor units, iv) use and upgrading of 1 no. existing field access point for construction and operational access to the site.1 no. temporary laydown area, v) 2 no. control cabins, vi) 33kV connector cable network, joint bays and associated works, vii) Internal access track, drainage works, security fencing, CCTV, and all associated ancillary site development works, viii) The decommissioning of the solar farm and reinstatement of the site at the end of its operational life - the application seeks a 10-year permission with an operational lifetime of 40 years
Lisbrien , Nenagh , Co. Tipperary
the construction of a dwelling house, garage, waste water treatment system & entrance along with all ancillary site works
Lisbrien , Capparoe , Nenagh Co. Tipperary
single storey extension and alterations to existing school including all associated site works
Lissenhall National School , Lisbrien/Lissenhall , Nenagh
a temporary prefabricated building and all associated site works
Lissenhall National School , Lisbrien/Lissenahall , Nenagh
a dwelling house, garage, waste water treatment system and entrance along with all ancillary site works
Lisbrien , Capparoe , Nenagh Co Tipperary
construction of dwelling house, garage, waste water treatment system and entrance along with all ancillary site works
Lisbrien , Capparoe , Nenagh Co Tipperary
proposed new car park, new site entrance, relocation/alterations to existing agricultural entrance, proposed new all-weather area and including all associated site works
Lisbrien/Lissenhall , Nenagh , Co. Tipperary
proposed car park, new site entrance, relocation / alterations to existing agricultural entrance, proposed new all weather area and including all associated site works
Lisbrien/Lissenhall , Nenagh , Co. Tipperary
a) Two new rooflights one in each gable roof hip; b) Single storey extension to the rear : Kitchen, dining, living area, WC, utility, en-suite & service store; c) Patio area to the rear and side; d) Removal of derelict outhouse & formation of a new side parking area; e) Wastewater Treatment system; f) Internal modifications to create 2 No. en-suite shower rooms at first floor and ground floor openings to the rear extension
Lisbrien , Lissenhall , Nenagh
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?