Lissenhall National School , Lisbrien/Lissenhall , Nenagh
CONDITIONALPlanning application 20632
Tipperary - Tipperary County Council
Proposed Development
single storey extension and alterations to existing school including all associated site works
Application Timeline
Application received
19 Jun 2020
Decision: CONDITIONAL
6 Aug 2020
Decision due
13 Aug 2020
Grant issued
9 Sept 2020
Application Details
- Location
- Lissenhall National School , Lisbrien/Lissenhall , Nenagh
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Tipperary County Council
- Site Area
- 0.67 ha
Timeline
- Registration Date
- 19 June 2020
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 6 August 2020
- Grant Date
- 9 September 2020
- Permission Expires
- 8 September 2025
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
a temporary prefabricated building and all associated site works
Lissenhall National School , Lisbrien/Lissenahall , Nenagh
proposed new car park, new site entrance, relocation/alterations to existing agricultural entrance, proposed new all-weather area and including all associated site works
Lisbrien/Lissenhall , Nenagh , Co. Tipperary
proposed car park, new site entrance, relocation / alterations to existing agricultural entrance, proposed new all weather area and including all associated site works
Lisbrien/Lissenhall , Nenagh , Co. Tipperary
demolition of shed outbuildings and to construct a single storey extension to the side and rear of existing dwelling including all associated material alterations to the house and all ancillary site works
Lissenhall , Capparoe , Nenagh
to construct (I) Cubicle shed over existing topless cubicles and roofed extension to this area and all associated site works. Retention is required for(i) calving shed with underground effluent slatted tank (ii) topless cubicle area with feeding area.
Ballyphilip , Nenagh , Co. Tipperary
a solar PV panel array consisting of up to 22,500m2 of solar panels on ground mounted steel frames, 2 no. electricity control cabins, 4 no. inverter units, underground cable ducts, hard standing area, boundary security fence, site entrance, access track, landscaping, CCTV and all associated site works
Lisbrien , Nenagh , Co. Tipperary
19600111 a solar PV panel array consisting of up to 22,500m2 of solar panels on ground mounted steel frames, 2 no. electricity control cabins, 4 no. inverter units, underground cable ducts, hard standing area, boundary security fence, site entrance, access track, landscaping, CCTV and all associated site works
Lisbrien , Nenagh , Co. Tipperary
RED III the development and operation of a solar photovoltaic (PV) farm with a total site area of 6.9 hectares comprising of the following – i) construction and operation of 22,500 sqm. of solar PV arrays on ground-mounted metal frames, with a maximum overall height of 4.7 metres, ii) Internal underground trenching, electrical cabling and ducting between the solar PV arrays and electrical invertor units, iii) 4 no. electrical invertor units, iv) use and upgrading of 1 no. existing field access point for construction and operational access to the site.1 no. temporary laydown area, v) 2 no. control cabins, vi) 33kV connector cable network, joint bays and associated works, vii) Internal access track, drainage works, security fencing, CCTV, and all associated ancillary site development works, viii) The decommissioning of the solar farm and reinstatement of the site at the end of its operational life - the application seeks a 10-year permission with an operational lifetime of 40 years
Lisbrien , Nenagh , Co. Tipperary
a) Two new rooflights one in each gable roof hip; b) Single storey extension to the rear : Kitchen, dining, living area, WC, utility, en-suite & service store; c) Patio area to the rear and side; d) Removal of derelict outhouse & formation of a new side parking area; e) Wastewater Treatment system; f) Internal modifications to create 2 No. en-suite shower rooms at first floor and ground floor openings to the rear extension
Lisbrien , Lissenhall , Nenagh
change of house design to that granted under planning ref: 2260722 including: a) Internal modifications and upgrades to the existing dwelling house (Protected Structure S243) and creation of openings to the new extension b) Single storey and part two-storey rear extension to the existing dwelling house c) Removal of existing derelict out-house and formation of new domestic garage d) Wastewater treatment system and all associated site works