Farranrory Upper , BALLINGARRY , Co Tipperary
N/APlanning application 2260554
Tipperary - Tipperary County Council
Proposed Development
a temporary Meteorological Mast and associated site works that will operate for a further 3 years. The Meteorological Mast will retain its finished height not exceeding 80m above existing ground level consisting of a lattice tubular frame, guy wires and ancillary equipment
View the full application file on the council's planning portal →Application Details
- Location
- Farranrory Upper , BALLINGARRY , Co Tipperary
- Applicant
- N/A
- Application Type
- RETENTION
- Planning Authority
- Tipperary County Council
- Site Area
- 0.2 ha
Timeline
- Registration Date
- 13 October 2022
- Status
- INCOMPLETED APPLICATION
- Decision
- N/A
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
a temporary Meteorological Mast and associated site works that will operate for a further 3 years, it will retain its finished height not exceeding 80m above existing ground level consisting of a lattice tubular frame, guy wires and ancillary equipment
Farranrory Upper , Ballingarry , Co Tipperary
a ten year planning permission for a renewable energy development with a 40-year operational life (from the date of commissioning of the renewable energy development). The entirety of the development constitutes the provision of a 9-turbine wind farm and all associated works on lands in both Counties Tipperary and Kilkenny. This development comprises part of an overall development for which planning permission is also sought for a 38kV substation in the townland of Killeen, Co. Kilkenny. A separate planning application will be made for an underground grid connection to Tipperary County Council and to Kilkenny County Council. The proposed development will constitute the provision of the following: • Construction of up to 9 turbines each with a maximum overall ground to blade tip height of up to 150 metres and associated foundations and hardstand areas; • Construction of new site entrances and upgrade of existing site entrances; • Internal wind farm underground power and communications cabling; • Upgrade of existing access tracks and provision of new site access roads; • Removal of existing Meteorological Masts and construction of 1 new Meteorological Mast for monitoring wind speeds with a maximum height of up to 85 metres; • Site drainage network • Construction of a new temporary site compound for use during construction; • Two Borrow Pits • Construction of a new on-site 38kV substation The planning application will be accompanied by an Environmental Impact Assessment Report (EIAR) and Natura Impact Statement
Farranrory Upper Farranrory Lower Coolnashinnagh and Gortnasmuttaun , Co. Tipperary
a ten-year appropriate period planning permission for development of this site: the proposed development will constitute the provision of the following: the installation of 2.25 km of 38kV underground grid connection comprising cable ducting and associated electrical cabling and all other ancillary works including joint bays, culverts, maker posts and all associated developments. Advisory Note: The full extent of the grid connection is 33.8 km, and a separate planning application will be made for a underground grid connection to Kilkenny County Council. This development comprises part of an overall development for which planning permission was granted for a 9 turbine wind farm and all associated works on lands located in the townlands of Farranrory Upper, Farranrory Lower, Coolnashinnagh and Gortnasmuttaun, Co. Tipperary. The planning application will be accompanied by an Environmental Impact Assessment Report (EIAR) and Natura Impact Statement
Coolanshinnagh Ardragh Gortfree Bolakeale , Co. Tipperary
An amendment planning application for a planning application granted under reference PL/21/1620 in the townlands of Coolnashinnagh, Ardragh, Gortfee and Bolakeale, Co Tipperary. The previously consented planning application comprised the installation of 2.25 km of a 38kV underground grid connection comprising cable ducting and associated electrical cabling and all other ancillary works including joint bays, culverts, maker posts and all associated development. The proposed amendments to the previously consented grid connection comprise: • Increase in number of joint bays along the extent of the grid connection from a total of 35 to 45 joint bays • Grid connection to be operated at 38kV but installed to a 110kV underground cable design standards/infrastructure • Minor Adjustments to the route and red line boundary Advisory Note: The full extent of the grid connection is 33.65 km, and a separate amendment planning application will be made for an underground grid connection to Kilkenny County Council.
Various townlands - Coolanshinnagh Ardragh Gortfree Bolakeale , , Co Tipperary.
a ten year appropriate period planning permission for the installation of 2.25km of 38kV underground grid connection comprising cable ducting and associated electrical cabling and all other ancillary works including joint bays, culverts, maker posts and all associated developments in the townlands of Coolnashinnagh, Ardragh, Bolakeale & Gortfree, Co. Tipperary. Advisory Note: The full extent of the grid connection is 33.8km, and a separate planning application will be made for an underground grid connection to Kilkenny County Council. This development comprises park of an overall development for which planning permission was granted for a 9-turbine wind farm and all associated works on lands located in the townlands of Farranrory Upper, Farranrory Lower, Coolnashinnagh & Gortnasmuttan, Co. Tipperary. The planning application will be accompanied by an Environmental Impact Assessment Report (EIAR) and Natura Impact Statement
Coolnashinnagh Ardagh Gortfree and Bolakeale , Co. Tipperary
a ten year planning permission for a renewable energy development with a 40-year operational life (from the date of commissioning of the renewable energy development). The entirety of the development constitutes the provision of a 9-turbine wind farm and all associated works on lands in both Counties Tipperary and Kilkenny. This development comprises part of an overall development for which planning permission is also sought for a 38kV substation in the townland of Killeen, Co. Kilkenny. A separate planning application will be made for an underground grid connection to Tipperary County Council and to Kilkenny County Council. The proposed development will constitute the provision of the following: • Construction of up to 9 turbines each with a maximum overall ground to blade tip height of up to 150 metres and associated foundations and hardstand areas; • Construction of new site entrances and upgrade of existing site entrances; • Internal wind farm underground power and communications cabling; • Upgrade of existing access tracks and provision of new site access roads; • Removal of existing Meteorological Masts and construction of 1 new Meteorological Mast for monitoring wind speeds with a maximum height of up to 85 metres; • Site drainage network • Construction of a new temporary site compound for use during construction; • Two Borrow Pits • Construction of a new on-site 38kV substation The planning application will be accompanied by an Environmental Impact Assessment Report (EIAR) and Natura Impact Statement
Farranrory Upper Farranrory Lower Coolnashinnagh and Gortnasmuttaun , Co. Tipperary
an amendment to the planning application previously granted permission under planning reference 20/972. The previously consented planning application included the construction of 9 turbines with maximum overall ground to blade tip height of up to 150 metres, associated foundations and hardstand areas; new site entrances, upgrade of existing site entrances; new on-site 38KV substation and all ancillary site works. The proposed amendments to the previously consented application comprise: (1) Increase the tip height of the turbines from 150 to 156.5 metres and increase the rotor diameter from 133 to 136 metres (3) Reconfiguration of a number of the consented hardstand layouts and associated changes to internal access roads (4) Minor Adjustments to the red line boundary (5) Provision of LiDAR (This application is accompanied by a NIS)
Farranrory Upper Farranrory Lower Coolnashinnagh & Gortnasmuttaun , Ballingarry , Co. Tipperary
a) an increase to the footprint of the substation compound of 381.6m2, b) an increase to the footprint of the substation building of 51.5m2, c) amendments to the layout of the offices and welfare facilities within the substation building, d) addition of 2 no. containers sized 6m by 2.43m by 2.59m in height for storage of parts and equipment during the operational phase, e) addition of 2 no. parking spaces and an extension of the access road, f) associated relocation of the permitted fence, g) amendments to the drainage design to accommodate changes to the layout, h) minor amendments to the red line of the permitted development to accommodate the above and i) addition of new joint bay
Coolnashinnagh , Ballingarry Thurles , Co. Tipperary
a dwelling, domestic garage, entrance, bore well, install waste water treatment system including associated site works
Garrynagree , The Commons , Thurles
(1) for construction of a 20 unit milking parlour complete with dairy, stores, meal bin, collection yard and holding pin (2) permission for conversion of existing open shed into cubicles and (3) permission for retention of as built effluent tank and all associated site works on our farm
Farronrory Lower , Ballingarry , Thurles
Affected by this application?
Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.