Ballyglasheen , Kilfeakle , Co. Tipperary
UNCONDITIONALPlanning application 23305
Tipperary - Tipperary County Council
Proposed Development
the construction of an energy storage facility within a total site of up to 0.86 hA, to include one single storey electrical substation building and electrical compound, electrical transformer/inverter station modules, containerised battery storage modules and spare parts containers on concrete support structures, access tracks, associated electrical ducting, cable racking and cabling, security fencing and CCTV security monitoring system, lightning protection poles, communications equipment and ancillary infrastructure previous ref 18600406
View the full application file on the council's planning portal →Application Timeline
Application received
29 Nov 2023
Decision: UNCONDITIONAL
31 Jan 2024
Decision due
1 Feb 2024
Application Details
- Location
- Ballyglasheen , Kilfeakle , Co. Tipperary
- Applicant
- N/A
- Application Type
- EXTENSION OF DURATION
- Planning Authority
- Tipperary County Council
Timeline
- Registration Date
- 29 November 2023
- Status
- APPLICATION FINALISED
- Decision
- UNCONDITIONAL
- Decision Date
- 31 January 2024
- Permission Expires
- 30 January 2025
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
development will consist of a 10 year permission for the construction of an energy storage facility within a total site of up to 0.86 hA, to include one single storey electrical substation building and electrical compound, electrical transformer/inverter station modules, containerised battery storage modules and spare parts containers on concrete support structures, access tracks, associated electrical ducting, cable racking and cabling, security fencing and CCTV security monitoring system, lightning protection poles, communications equipment and ancillary infrastructure
Ballyglasheen , Kilfeakle , Co. Tipperary
development will consist of a 10 year permission for the construction of an energy storage facility within a total site of up to 0.86 hA, to include one single storey electrical substation building and electrical compound, electrical transformer/inverter station modules, containerised battery storage modules on concrete support structures, access tracks, associated electrical ducting, cable racking and cabling, security fencing and CCTV security monitoring system, lightning protection poles, communications equipment and ancillary infrastructure
Ballyglasheen , Kilfeakle , Co. Tipperary
the following development: (a) front porch, (b) rear extension, (c) revised front/roadside boundary including revisions to the existing site entrance, and (d) upgraded on-site wastewater treatment & disposal system serving the existing dwelling house and all associated ancillary works
Knockballynoe East , Kilfeakle , Co. Tipperary
construction of two extensions to dwelling consisting of lounge and master bedroom and Permission to construct domestic garage and associated site works
Knockballynoe East , Kilfeakle , Co. Tipperary
disconnecting from septic tank on adjoining property and permission to install secondary treatment system and soil polishing filter and associated site works
Dromline , Co. Tipperary
conversion of agricultural shed into residential accommodation as constructed and also permission to modify and convert this residential accommodation into one single dwelling house, permission to remove existing entrance and construct replacement entrance, permission to de-commission existing septic tank system on site and replace with new waste water treatment system and percolation area and permission to modify slatted unit on site and re-purpose same as Hay Barn and associated site works
Dromline , Tipperary , Co. Tipperary
a single story extension to the rear of the existing dwelling and all ancillary site works
Scart , Co. Tipperary , E34 K820
a single story extension to the rear of the existing dwelling
Scart , Tipperary Town , Co Tipperary
a single story extension to the rear of the existing dwelling, development to be 39m2 and makes up one additional room, associated roof works to tie into the existing dwelling roof and not exceed the ridge
Scart , Tipperary Town , Co. Tipperary
construction of a new vehicular entrance to facilitate forestry works access