Kyle and Kyleagarry , Gortdrum , Co. Tipperary
CONDITIONALPlanning application 2460006
Tipperary - Tipperary County Council
Proposed Development
construction of an extension to the solar PV development permitted under planning application ref: PR 22/165 comprising the erection of photovoltaic panels laid out in arrays over a development area of ca. 17.44ha along with ancillary development including: 13 no. inverters (ca. 15.25m2 x 2.6m), 7 no. CCTV cameras mounted on 4m high poles, electrical and communications cabling, palisade security fencing and all ancillary works, this proposed extension development will be connected to an existing permitted solar development under planning application ref: PL 22/165 by underground cables - A Natura Impact Statement will accompany the planning application
View the full application file on the council's planning portal →Application Timeline
Application received
5 Jan 2024
Further information requested
28 Feb 2024
Further information received
29 May 2024
Decision due
23 Jul 2024
Decision: CONDITIONAL
23 Jul 2024
Grant issued
26 Aug 2024
Application Details
- Location
- Kyle and Kyleagarry , Gortdrum , Co. Tipperary
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Tipperary County Council
- Site Area
- 17.44 ha
Timeline
- Registration Date
- 5 January 2024
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 23 July 2024
- Grant Date
- 26 August 2024
- Permission Expires
- 25 August 2029
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
the construction of a 43MW Solar PV development comprising of ca. 155,000 no. photovoltaic panels laid out in arrays, the construction of a 38 kV substation, (ca. 114.9m2 X 4.75m tall) and transformer unit (ca. 15.25m2 X 2.4m tall) along with associated ancillary development including: 24 no. Power Hubs (ca. 15.25m” X 2.4m), which incorporate the inverters and the transformers within the same unit, 1 no. single storey communications building (11.1m” X 2.5m), 1 no. single storey client building (15.25m2 X 2.9m), 1 no. single storey equipment storage container (7.5m” X 2.7m), 15 no. CCTV cameras mounted on 4m high poles; and perimeter security fencing. The proposed development will also see the installation of ten (10 no.) ISO shipping container units for the purpose of battery storage (30.5 m” X 2.9m). The total development area will be ca. 70.5 ha
Kyleagarry Kyle Ballyryan East and Gortdrum , Donohill , Co. Tipperary
The construction of a 43MW Solar PV development comprising of ca. 155,000 no. photovoltaic panels laid out in arrays, the construction of a 38 kV substation, (ca. 114.9m2 X 4.75m tall) and transformer unit (ca. 15.25m2 X 2.4m tall) along with associated ancillary development including: 24 no. Power Hubs (ca. 15.25m” X 2.4m), which incorporate the inverters and the transformers within the same unit, 1 no. single storey communications building (11.1m” X 2.5m), 1 no. single storey client building (15.25m2 X 2.9m), 1 no. single storey equipment storage container (7.5m” X 2.7m), 15 no. CCTV cameras mounted on 4m high poles; and perimeter security fencing. The proposed development will also see the installation of ten (10 no.) ISO shipping container units for the purpose of battery storage (30.5 m” X 2.9m). The total development area will be ca. 70.5 ha
Kyleagarry Kyle Ballyryan East and Gortdrum , Co. Tipperary
the demolished cottage and Permisison to erect in its place a dormer type bungalow with effluent treatment tank and percolation system and all associated ancillary works
Kyle , Solohead , Co. Tipperary
demolished cottage and permission to erect in its place a dormer type bungalow with effluent treatment tank and percolation system and all associated ancillary works
Kyle , Solohead , Co Tipperary
demolish cottage and Planning Permission to erect in its place a dormer type bungalow
Kyle , Solohead , Co. Tipperary
The development will consist of the construction of Solar PV development comprising photovoltaic panels laid out in arrays over a total development site area of ca. 54.5 ha, the construction of a 38KV substation (ca. 114.4m2 x 4.75m tall), a transformer unit (ca. 18m2 x 4m tall) and associated bund (ca. 55m2) along with ancillary development including: 17 no. Power Hubs (ca. 15.25m2 x 2.4) which incorporate at inverter and a transformer, 1. No. single storey communications building (11.1m2 x 2.5m), 1 no. single storey client side sub-station building (15.25m2 x 2.9) 1. No. single storey equipment storage building (7.5m2 x 2.7m), 7 no. CCTV cameras mounted on 4m high poles, perimeter security fencing and all ancillary works. NIS will be submitted with the planning application
Kyleagarry Ballyryan East and Gortdrum , Donohill
the following: Effluent treatment system comprising treatment unit and polishing filter; and all associated site and ancillary works
Gortdrum , Donohill , Co. Tipperary E34 NV21
demolition of rear single storey extension to dwelling, Permission to construct new two storey extension and carry out renovations to existing dwelling, Permission to demolish domestic garage and domestic shed and Permission to install a new waste water treatment system and sand polishing filter
Milltown , Solohead , Co. Tipperary
The development will consist of the construction of Solar PV development comprising photovoltaic panels laid out in arrays over a total development site area of ca. 54.5 ha, the construction of a 38KV substation (ca. 114.4m2 x 4.75m tall), a transformer unit (ca. 18m2 x 4m tall) and associated bund (ca. 55m2) along with ancillary development including: 17 no. Power Hubs (ca. 15.25m2 x 2.4) which incorporate at inverter and a transformer, 1. No. single storey communications building (11.1m2 x 2.5m), 1 no. single storey client side sub-station building (15.25m2 x 2.9) 1. No. single storey equipment storage building (7.5m2 x 2.7m), 7 no. CCTV cameras mounted on 4m high poles, perimeter security fencing and all ancillary works. NIS will be submitted with the planning application
Kyleagarry Ballyryan East and Gortdrum , Donohill
a10 year permission for development consisting of the construction of a Solar PV development comprising photovoltaic panels laid out in arrays over a total development site area of ca. 54.5 ha, the construction of a 38kV substation (ca.114.4m2 x 4.75m tall), a transformer unit (ca. 18m2 x 4m tall) and associated bund (ca.55m2), along with ancillary development including: 17 no. Power Hubs (ca. 15.25m2 x 2.4m) which incorporate an inverter and a transformer, 1 no. single storey communications building (11.1m2 x2.5m),1 no. single storey client side sub-station building (15.25m2 x 2.9m), 1 no. single storey equipment storage building (7.5m2 x 2.7m), 7 no. CCTV cameras mounted on 4m high poles, perimeter security fencing and all ancillary works. An Natura Impact statement will accompany the planning application
Kyleagarry Ballyryan East and Gortdrum , Co. Tipperary
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?