← Back to search

Rathduff , Townland of Thomastown Demesne South , Co. Tipperary

CONDITIONAL

Planning application 2660469

Tipperary - Tipperary County Council

Proposed Development

RED III development which will consist of an amendment to a previously consented development (planning reference PL92.313424) comprising the reconfiguration and enlargement of the permitted substation layout from c. 24.0m x 19.0m compound with an enlarged compound (c. 54.1m x 25.9m), to include a Solar Farm (IP) section and an ESB section, containing control rooms, power quality equipment, transformers and a 12m x 12m hardstanding area. The development includes ancillary infrastructure such as 2.44m high palisade fencing, lighting, CCTV and internal access tracks, as well as a minor reconfiguration of the permitted solar array, involving the removal of 11 tables of solar panels to accommodate the revised substation footprint. All other infrastructure of the development permitted under PL92.313424 remain unchanged. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    19 May 2026

  2. Decision: CONDITIONAL

    14 Aug 2026

  3. Decision due

    24 Aug 2026

Application Details

Location
Rathduff , Townland of Thomastown Demesne South , Co. Tipperary
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Tipperary County Council
Site Area
42.68 ha

Timeline

Registration Date
19 May 2026
Status
DECISION MADE
Decision
CONDITIONAL
Decision Date
14 August 2026

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

2m
211014CONDITIONAL13 Jul 2021

a period of 5 years to construct and complete a Solar PV Energy Development with a total site area of 42.68 hectares, to include a single storey electrical substation building, electrical transformer and inverter substation modules, solar PV panels ground mounted on support structures, internal access tracks, security fencing, electrical cabling and ducting, CCTV and other ancillary infrastructure, drainage, additional landscaping and habitat enhancement as required and associated site development works including works relating to the access to the site. The development would be operational for 35 years

Rathduff , Thomastown Demesne South , Co. Tipperary

2m
20506N/A25 May 2020

a period of 5 years to construct and complete a Solar PV Energy Development with a total site of 43.68 hectares, to include a single storey electrical substation building, electrical transformer and inverter substation modules, solar PV panels, ground mounted on support structures, internal access tracks, security fencing, electrical cabling and ducting, CCTV and other ancillary infrastructure, drainage, additional landscaping and habitat enhancement as required and associated site development works including works relating to the access to the site. The solar farm would be operational for 35 years

Rathduff , Thomastown , Co. Tipperary

130m
20103N/A6 Feb 2020

a period of 5 years to construct and complete a Solar PV Energy Development with a total site of 43.68 hectares, to include a single storey electrical substation building, electrical transformer and inverter substation modules, solar PV panels, ground mounted on support structures, internal access tracks, security fencing, electrical cabling and ducting, CCTV and other ancillary infrastructure, drainage, additional landscaping and habitat enhancement as required and associated site development works including works relating to the access to the site. The solar farm would be operational for 35 years

Rathduff , Thomastown , Co. Tipperary

139m
20271N/A16 Mar 2020

a period of 5 years to construct and complete a Solar PV Energy Development with a total site of 43.68 hectares, to include a single storey electrical substation building, electrical transformer and inverter substation modules, solar PV panels, ground mounted on support structures, internal access tracks, security fencing, electrical cabling and ducting, CCTV and other ancillary infrastructure, drainage, additional landscaping and habitat enhancement as required and associated site development works including works relating to the access to the site. The solar farm would be operational for 35 years

Rathduff , Thomastown , Co. Tipperary

1.0km
17600559N/A18 May 2017

the construction of a two storey dwelling, garage, septic tank, peroclation area, site entrance, site boundaries and all associated site works

Ballymacady , Golden , Co. Tipperary

1.0km
2460802CONDITIONAL20 Sept 2024

an existing in -line stable shed and Planning Permission for a livestock shed with underground slatted concrete tank, feeding passage, concrete apron and livestock shed over existing uncovered cubicle area and all associated works

Thomastown Demesne South , Golden , Co Tipperary

1.1km
17601440N/A22 Dec 2017

Dwelling, Garage, Effluent Treatment System, Entrance and all associated site works.

Ballymacady , Golden , Co. Tipperary

1.1km
18600170CONDITIONAL13 Feb 2018

Dwelling, Garage, Effluent Treatment System, Entrance and all associated site works.

Ballymacady , Golden , Co. Tipperary

1.1km
2660024CONDITIONAL15 Jan 2026

extension and renovation of existing dwelling, permission to retain extension to rear of dwelling, permission to construct new domestic garage, permission to decommission existing septic tank and install new waste water treatment system and percolation area and associated site works

Thomastown North , Golden , Co. Tipperary

1.1km
2560023CONDITIONAL16 Jan 2025

extension and renovation of existing dwelling, demolition of rear porch, installation of waste water treatment system and percolation area and de-commission of existing septic tank, to demolish two sheds and remove concrete slab on site and associated site works