Proposed Development

RED III develoment to construct a photovoltaic solar farm development. The proposed development seeks a 10-year planning permission for the proposed photovoltaic solar farm development and all associated site works. The development will consist of linear arrays of solar photovoltaic panels on ground mounted frames of ca. 9.40 hectares overall area, including: associated cabling & ducting and hybrid inverters; a 20kV electrical customer control building; ESB modular hub and transformers; site entrance and access track; perimeter fencing up to 2.5 metres high; pole mounted CCTV cameras up to 3 metres high; temporary access track, temporary contractor’s compound & temporary storage area; and all associated site development and ancillary works. A Natura Impact Statement (NIS) will be submitted to the Planning Authority in connection with the application. The proposed development will have a 40-year operational life from the date of commissioning. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to Section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with Section 34D(b), the provisions of Article 26A of the Planning and Development Regulations 2001 to 2025 shall apply

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    23 Oct 2026

  2. Decision due (upcoming)

    17 Dec 2026

Application Details

Location
Magherareagh Townland , Ardfinnan , Co. Tipperary
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Tipperary County Council
Site Area
9.4 ha

Timeline

Registration Date
23 October 2026Other applications received that week
Status
NEW APPLICATION
Decision
N/A
Decision Due
17 December 2026

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

2m
17600582REFUSED22 May 2017

the development will consist of a solar farm comprising of approximately 9.4 hectares of solar panels on ground mounted steel frames, 1 no. single storey delivery substation, 2 no. single storey inverter/transformer units, drainage swales, underground cable ducts on site, temporary construction compound (including site offices, portable toilets and parking area), boundary security fence, site entrance, access tracks, CCTV and all associated site works

Magherareagh , Ardfinnan , Co. Tipperary

20m
2660960N/A30 Sept 2026

RED III construction of a photovoltaic solar farm development - the proposed development seeks a 10-year planning permission for the proposed photovoltaic solar farm development and all associated site works. The development will consist of linear arrays of solar photovoltaic panels on ground mounted frames of ca. 9.40 hectares overall area, including: associated cabling & ducting and hybrid inverters; a 20kV electrical customer control building; ESB modular hub and transformers; site entrance and access track; perimeter fencing up to 2.5 metres high; pole mounted CCTV cameras up to 3 metres high; temporary access track, temporary contractor’s compound & temporary storage area; and all associated site development and ancillary works. A Natura Impact Statement (NIS) will be submitted to the Planning Authority in connection with the application. The proposed development will have a 40-year operational life from the date of commissioning

Magherareagh Townland , Ardfinnan , Co. Tipperary

469m
21263CONDITIONAL3 Mar 2021

existing detached domestic garage/art studio and to retain fuel storage shed, all with associated site works

Magherareagh , Ardfinnan , Clonmel

659m
19601326CONDITIONAL28 Nov 2019

minor changes to the elevations of existing dwelling and to retain as constructed extension to existing domestic garage, to retain two number additional sheds, to retain dog kennels and dog runs all with associated site works

Kilballygorman , Ardfinnan , Clonmel

738m
17601014CONDITIONAL14 Sept 2017

change of house type and repositioned driveway at house no. 48 from that approved under Permission No. 05/1228, the house has been changed from 5 bedroom type 5a to 4 bedroom type 4a and the driveway has been altered and repositioned so that it is accessed from the estate road opposite house no. 8

48 Ros na Greine , Clogheen Road Magheragh , Ardfinnan Clonmel

768m
17601210CONDITIONAL3 Nov 2017

67 houses complete with external works. The proposed development will comprise: 4 no. semi-detached single storey 2 bedroom houses; 11 no. semi-detached single storey 3 bedroom houses (3 no. with garages); 1 no. detached single-storey house; 39 no. semi-detached two-storey 3 bedroom houses (2 no. with garages); 8 no. detached two-storey 3 bedroom houses, 1 no. detached two storey 4 bedroom house with garage; 3 no. detached two-storey 5 bedroom house with garage under clause A 42 (1A)(a)(V)

Clogheen Road , Maghereagh , Ardfinnan

858m
2460399CONDITIONAL24 May 2024

the construction of an electricity control compound to connect the permitted Monroe East Solar Array (Pl. Ref: 16/600642 & 21/473) to Ardfinnan 38kV Substation including palisade fencing, site entrance, 2 No. electricity control units, and all ancillary site works

Kilballygorman , Ardfinnan Clonmel , Co. Tipperary

873m
2561231CONDITIONAL29 Nov 2025

the construction of a dwelling, garage, effluent treatment system, entrance and all associated site works

Ballydrinan , Ardfinnan , Clonmel

881m
17600500CONDITIONAL5 May 2017

construction of a bedroom with special bathroom at ground floor level to rear of my dwelling, along with all ancillary site works

37 Castleview , Ardfinnan , Co. Tipperary

898m
2460837CONDITIONAL2 Oct 2024

the construction of a dwelling, entrance, waste water treatment system and all associated site development works

Ballydrinan , Cahir , Co. Tipperary

Affected by this application?

Closing soon
4days left to make a submission

Observations close on Thursday 26 November 2026, five weeks from the date the application was received. The fee is €20, and only planning grounds count.

Check if you have grounds — free

Two questions, no payment: we'll tell you whether what concerns you is something the council can actually take into account.

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?