St Mary's Care Centre , Longford Road , Robinstown
CONDITIONALPlanning application 206061
Westmeath - Westmeath County Council
Proposed Development
Construction of a security porch to the existing front entrance of C.A.D.S. Unit Building. The proposed development consists of works to a protected structure.
View the full application file on the council's planning portal →Application Timeline
Application received
18 Mar 2020
Decision: CONDITIONAL
3 Jul 2020
Decision due
7 Jul 2020
Grant issued
12 Aug 2020
Application Details
- Location
- St Mary's Care Centre , Longford Road , Robinstown
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Westmeath County Council
Timeline
- Registration Date
- 18 March 2020
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 3 July 2020
- Grant Date
- 12 August 2020
- Permission Expires
- 11 August 2025
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
construction of a temporary accommodation ambulance base prefabricated building and all associated site development works. The proposed works consists of works within the curtilage of a protected structure.
St Mary's Care Centre , Castlepollard Road , Robinstown
widening of five existing door openings. The development consists of the alteration of the five external door openings and the replacement of their non original doorsets. The building is a protected structure RPS No. 019-018, former Mullingar Union Workhouse Complex (St. Marys Hospital)
St Mary's Hospital , Castlepollard Road , Robinstown
The development consists of 30 new car parking spaces at the perimeter of the existing carpark within the hospital campus, The development is within the curtilage of a protected structure
Midland Regional Hospital , Longford Road , Mullingar
for development as previously granted under planning reference 16/6289 for ground floor window in-lieu of external door on northeast elevation, additional first floor window to ensuite on northeast elevation, increase in height of lean-to roof over utility and addition of roof window to roof slope on northeast elevation to accommodate walk in wardrobe to rear first floor bedroom
Brookfield , Mullingar , Co.Westmeath
a) a 2-storey energy centre building; b) window, curtain wall, door and cladding replacement works; c) roof mounted solar photovoltaic panels, and all associated site development works. The development also consists of replacement of existing windows and external ductwork to protected structure RPS No 019-004.
Midlands Regional Hospital Mullingar , Longford Road , Mullingar Co. Westmeath
to retain and complete new vehicular entrance to the site and associated site works
Irishtown , Mullingar , Co. Westmeath
construction of a 616sqm ground floor extension with plant room 214sqm above, to include Magnetic Resonance Imaging (MRI) Unit and extensions to the Emergency and Radiology Departments and all ancillary works as necessary at south-west side of The Midlands Regional Hospital Mullingar and the demolition and removal of the 86sqm ambulance base building. The development is within the curtilage of a Protected Structure (Ref 019-004).
Midland Regional Hospital Mullingar , Longford Road , Mullingar
development which will consists of a new single storey extension to rear of existing two storey dormer dwelling, with external alterations inclusive of 2 new windows to eastern and western sides of house and all associated site works
25 Brookfield , Mullingar , Co. Westmeath
development which will consist of the construction of a 3 storey apartment building containing 38 units, comprising of 26 No. 2-bedroom apartments and 12 No. 1-bedroom apartments, the provision of a site entrance off the R394 Road, the works will also include, roads, paths, paving, parking, amenity space, boundary treatments, landscaping, foul sewer drainage, surface water drainage, attenuation tanks with an attenuated outflow to an existing open drain and ancillary structures including bin stores and ESB substation and all associated site development works to complete the development
Robinstown , Mullingar , Co. Westmeath
The development will consist for a 1741 m2 two storey out-patients department (OPD) together with an adjacent free-standing 28m2 plant room. The OPD will consist of medical consulting rooms, admin offices, storerooms, toilets, staff facilities and ancillary accommodation. The development to include installation of PV panels to the roof of the OPD, landscaping, all necessary site works and services connections together with the provision of 2No. Totem signpost at the entrance to the hospital. The development is within the curtilage of a Protected Structure RPS No 019-004
Midlands Regional Hospital , Mullingar , Co Westmeath