← Back to search

Unit 1 IDA Ardmore Business and Technology Park , Marlinstown , Mullingar

CONDITIONAL

Planning application 22495

Westmeath - Westmeath County Council

Proposed Development

Consisting of an extended hardstanding area(50m x 37m) for improved circulation, facilitating current operations, and a complementary enhanced landscaping amenity area adjacent to the existing premises and all associated ancillary works.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    12 Oct 2022

  2. Decision: CONDITIONAL

    2 Dec 2022

  3. Decision due

    6 Dec 2022

  4. Grant issued

    5 Jan 2023

Application Details

Location
Unit 1 IDA Ardmore Business and Technology Park , Marlinstown , Mullingar
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Westmeath County Council

Timeline

Registration Date
12 October 2022
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
2 December 2022
Grant Date
5 January 2023
Permission Expires
4 January 2028

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

111m
22257CONDITIONAL17 May 2022

development consisting of the installation of a roof mounted solar photovoltaic panels to include all ancillary works and services

Unit 1 IDA Ardmore Business & Technology Park , Marlinstown , Mullingar

111m
22178N/A7 Apr 2022

The development will consist of the installation of a roof mounted solar photovoltaic panels to include all ancillary works and services.

Unit 1 IDA Ardmore Business & Technology Park , Marlinstown , Mullingar Co. Westmeath

112m
2560115CONDITIONAL19 Mar 2025

development which will consist of the following works: 1. Full Permission is sought for the construction of a new shipping area and tank storage extension building to the rear of the existing building. 2. Retention Permission is also sought for the as constructed engine storage facility building to the rear of the existing building together with the security fencing erected along the northeastern boundary all as shown on the submitted drawings with all ancillary site works and services

Unit 1 IDA Ardmore Business & Technology Park , Marlinstown , Mullingar County Westmeath

112m
2460117N/A15 Apr 2024

A temporary free standing shipping area extension to move completed products for final dressing and shippping.

Unit 1 IDA Ardmore Business & Technology Park I Marlinstown I Mullingar I Co. Westmeath I Ireland I N91 R762 , Marlinstown , Mullingar

125m
2360209CONDITIONAL6 Jul 2023

development which will consist of the replacement of a permitted single storey terminal electrical station and separate permitted switchgear enclosure (both previously permitted as part of a solar farm permission by An Bord Pleanála Reference ABP-300135-17 (Westmeath County Council Planning Ref. 16/6264) with 1 no. proposed single storey 20kV substation building on the site of the previously permitted terminal station. The development also incorporates proposed track revisions adjacent to the substation to accommodate an emergency fire tender turning area

Marlinstown , Mullingar , Co. Westmeath

166m
2360224CONDITIONAL14 Jul 2023

development which will consist of an extension of the internal road network from the existing 1-arm roundabout located to the West of the site. The development will include a road extension (approximately 75m long), associated footpaths, public lighting and all associated services and site works to facilitate the development

IDA Ardmore Business & Technology Park , Marlinstown Ardmore , Mullingar Co. Westmeath

270m
2660324N/A20 Jun 2026

development at the site at Ardmore Business & Technology Park. The site is c. 1.307 hectares in size. It is made up of greenfield lands together with sections of existing road, footpath and cycleway. It is bound to the north, east and west by estate roads within Mullingar Business Park (with access from the N52), and to the south by an existing hedgerow. The development will consist of: [1] The construction of an Advanced Building Solution (ABS) building ranging from one to three storeys (6.2 meters (m) to 14.2 m in height), with a gross floor area of 2,500 square meters (sq. m) to accommodate light industrial / manufacturing and office uses. The building will comprise: (a) A three-storey reception and support office block (12.7 m to 14.2 m in height, 700 sq. m in area) providing covered entrance, reception, administration, staff welfare facilities, ancillary office space and plant rooms; (b) A light industrial / manufacturing production space (10 m clear internal height, 12.7 m to 14 m externally, 1,725 sq. m in area); (c) A single-storey services block (6.2 m in height, 75 sq. m in area) accommodating a substation, switchroom and waste storage area, together with an associated external services yard; and (d) The provision of c. 300 sq. m of photovoltaic panels at roof level. [2] The modification of two existing vehicular access points to provide one point of vehicular and pedestrian access and one point of articulated lorry access; the creation of a new shared pedestrian / cycle entrance point and path. [3] The construction of 41 no. car parking spaces (including 3 no. accessible spaces and 7 no. EV charging spaces) and 42 no. bicycle parking spaces (6 no. Sheffield bicycle stands and 15 no. bicycle stands under shelters, each stand accommodating 2 no. bicycles). [4] The provision of a new uncontrolled pedestrian and cycle crossing in the Mullingar Business Park Estate Road and the northern part of the site, together with associated vehicular and pedestrian signage and ancillary works. [5] All associated and ancillary site development works, site and landscape clearance, the installation of hard and soft landscape planting; drainage infrastructure; fencing and boundary treatments; building, vehicular and pedestrian signage; utilities and site services; and all associated site works

Mullingar (Ardmore) Business & Technology Park , Marlinstown Ardmore , Mullingar Co. Westmeath

277m
176222CONDITIONAL10 Aug 2017

Upgrade works to the existing entrance with the installation of a new security gate and fencing, installation of security cameras including cabinets and installation of a new rigid wire mesh boundary fence around the entire site (approx. 2.4km)

Ardmore IDA Business & Technology Park , Marlinstown , Mullingar

344m
2360210CONDITIONAL6 Jul 2023

development which will consist of the extension of the operational lifespan of a solar farm permitted by An Bord Pleanála under Ref. ABP-300135-17 (Westmeath County Council Planning Ref. 16/6264) from 25 No. years as permitted (by reason of Condition No.3 of permission Ref. ABP 300135-17) to 40 No. years

Marlinstown , Mullingar , Co. Westmeath

411m
22347CONDITIONAL1 Jul 2022

a new Advanced Building Solution consisting of office and light industrial/production spaces. Permission is also sought for vehicular/pedestrian entrance, signage, new timber post-and-rail boundaries, car parking, cycle shelters, landscaping, gas skid, underground storage tank, independent ESB substation & switch room building, access road and all associated site works. The development has been subject of a Screening for Appropriate Assessment in accordance with Article 6(3) of the EU Habitats Directive (Directive 92/43/EEC) and the Planning and Development Act 2000 as amended. The Screening for Appropriate Assessment will be submitted to the Planning Authority with the Planning Application

IDA Ardmore Business & Technology Park , Mullingar , Co.Westmeath

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?