← Back to search

Johnstown South , Arklow , Co. W icklow

CONDITIONAL

Planning application 211335

Wicklow - Wicklow County Council

Proposed Development

construction of a bungalow with garage and car port, new entrance and access driveway, new treatment system and percolation area to current EPA standards and all ancillary site works

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    5 Nov 2021

  2. Further information requested

    20 Dec 2021

  3. Further information received

    9 Feb 2022

  4. Decision: CONDITIONAL

    4 Mar 2022

  5. Decision due

    8 Mar 2022

  6. Grant issued

    7 Apr 2022

Application Details

Location
Johnstown South , Arklow , Co. W icklow
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Wicklow County Council
Site Area
0.303 ha
Floor Area
209 sq m
Residential Units
1

Timeline

Registration Date
5 November 2021
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
4 March 2022
Grant Date
7 April 2022
Permission Expires
6 April 2027

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

196m
2560271CONDITIONAL10 Apr 2025

construction of a bungalow with garage, a new entrance, a new treatment system and percolation area to current EPA standards and all ancillary site works

Johnstown South , Arklow , Co. Wicklow

208m
2360233N/A23 Aug 2023

the construction of a bungalow with garage, a new entrance, a new treatment system and percolation area to current EPA standards and all ancillary site works

Johnstown South , Arklow , Co Wicklow

523m
2560361REFUSED15 May 2025

period of 10 years for a proposed solar farm and BESS (battery energy storage system) development which will consist of the construction of PV panels mounted on metal frames, inverters, battery storage infrastructure (BESS units, and MV Stations), new access tracks, underground cabling, perimeter fencing with CCTV cameras and access gates, a temporary construction compound, a substation and all ancillary grid infrastructure and associated works. It is proposed to use the consented Ballymoney Solar Farm access point (Pl Ref: 19/627 and ABP Ref: 305289-19). The solar farm and BESS would be operational for 40 years. A Natura Impact Statement (NIS) will be submitted with this application

Townland of Ballymoney , Arklow , Co. Wicklow

686m
171497CONDITIONAL19 Dec 2017

solar farm within a site area of approximately 39 hectares consisting of solar photovoltaic panels covering an area of up to 27.2 ha on ground mounted steel frames, 1 no on site substation, 8 no inverter / transformer stations, underground cables and ducts, boundary security fence, new internal tracks, CCTV cameras and all associated site services. Permission is sought for a period of 10 years

Johnstown North , Co. Wicklow

694m
2360151CONDITIONAL14 Jul 2023

a 38KV grid connection cable and associated infrastructure to connect the approved Johnstown North solar farm (consented under planning ref. 171497) to the existing Arklow 220kV Substation comprising the laying of a 3,190m Underground Cabling (UGC) and associated infrastructure, located at Dublin Road, Arklow, Co. Wicklow

Townlands of Killinskyduff Templerainy Johnstown South and Johnstown North , Arklow , County Wicklow

773m
21968CONDITIONAL5 Aug 2021

single storey dwelling and domestic garage with a waste water treatment unit and percolation area to current EPA specifications, plus bored well, together with all associated site works

Seabank , Sea Road , Arklow

847m
2360185CONDITIONAL27 Jul 2023

to amend the design of the approved development (Planning Reference: 17/1497) which comprises a Solar PV Energy Development. Proposed amendments include (1) change in location and size of substation, (2) two additional temporary construction compounds will be located at the site entrances, (3) the number of modules will decrease, (4) the number of pile driven poles will decrease, (5) the size and number of transformer stations will increase, (6) the total fencing area will increase (7) the total amount of fencing posts will increase, (8) up to 21 CCTV cameras will be installed (9) access tracks will be optimised and increased in width and length, and (10) increase in operational lifetime from 25 years to 35years

Lands within the townland of Johnstown North , Co. Wicklow

924m
19627CONDITIONAL10 Jun 2019

solar farm within a site area of approx. 19 ha consisting of solar photovoltaic panels covering an area of up to 9.8 ha on ground mounted steel frames, 1 no on site substation, 3 no inverter / transformer stations, underground cables and ducts, boundary security fence, new internal tracks, CCTV cameras and all associated site services. Permission is sought for a period of 10 years

Ballymoney , Near Arklow , Co. Wicklow

1.1km
2560313CONDITIONAL24 Apr 2025

amend the design of the approved development (Planning Reference: 19/627 and ABP-305289-19) which comprises consent for a Solar Farm within a site area of 19 hectares consisting of solar photovoltaic panels covering an area of up to 9.8ha on ground mounted steel frames, 1 no. on-site substation; 3 no. inverter/transformer stations, underground cables and ducts, boundary security fence, new internal tracks, CCTV cameras and all associated site services within the townland of Ballymoney, near Arklow, Co. Wicklow. Planning permission was sought for a period of 10 years. Proposed amendments include (1) relocation of part of the internal access track, and (2) a gate will be added along the access track

Townland of Ballymoney , Arklow , Co. Wicklow

1.2km
221131N/A25 Oct 2022

erection of a front porch, replace existing flat roof on rear of existing dwelling with pitched roof married into existing pitched roof by raising the height of the existing pitched roof by 800mm, to remove existing chimneys, install a solar panel on the new south facing roof, and to replace existing flat roof on existing shed/domestic garage to rear of existing dwelling with a pitched roof, together with all associated site works

Seabank , Arklow , Co. Wicklow

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?