Townlands of Killinskyduff Templerainy Johnstown South and Johnstown North , Arklow , County Wicklow
CONDITIONALPlanning application 2360151
Wicklow - Wicklow County Council
Proposed Development
a 38KV grid connection cable and associated infrastructure to connect the approved Johnstown North solar farm (consented under planning ref. 171497) to the existing Arklow 220kV Substation comprising the laying of a 3,190m Underground Cabling (UGC) and associated infrastructure, located at Dublin Road, Arklow, Co. Wicklow
View the full application file on the council's planning portal →Application Timeline
Application received
14 Jul 2023
Further information requested
31 Aug 2023
Further information received
22 Feb 2024
Decision due
20 Mar 2024
Decision: CONDITIONAL
20 Mar 2024
Grant issued
23 Apr 2024
Application Details
- Location
- Townlands of Killinskyduff Templerainy Johnstown South and Johnstown North , Arklow , County Wicklow
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Wicklow County Council
- Site Area
- 2.6 ha
Timeline
- Registration Date
- 14 July 2023
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 20 March 2024
- Grant Date
- 23 April 2024
- Permission Expires
- 22 April 2029
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
solar farm within a site area of approximately 39 hectares consisting of solar photovoltaic panels covering an area of up to 27.2 ha on ground mounted steel frames, 1 no on site substation, 8 no inverter / transformer stations, underground cables and ducts, boundary security fence, new internal tracks, CCTV cameras and all associated site services. Permission is sought for a period of 10 years
Johnstown North , Co. Wicklow
to amend the design of the approved development (Planning Reference: 17/1497) which comprises a Solar PV Energy Development. Proposed amendments include (1) change in location and size of substation, (2) two additional temporary construction compounds will be located at the site entrances, (3) the number of modules will decrease, (4) the number of pile driven poles will decrease, (5) the size and number of transformer stations will increase, (6) the total fencing area will increase (7) the total amount of fencing posts will increase, (8) up to 21 CCTV cameras will be installed (9) access tracks will be optimised and increased in width and length, and (10) increase in operational lifetime from 25 years to 35years
Lands within the townland of Johnstown North , Co. Wicklow
demolition of existing storage shed, a new shed to serve as house ancillary storage and hobby shed to store vintage cars and associated site development works
Johnstown North , Arklow , Co. Wicklow
demolition of existing storage shed, a new storage shed and associated site development works
Johnstown North , Arklow , Co. Wicklow Y14FH01
demolition of existing storage shed, a new storage shed and associated site development works
Johnstown North , Arklow , Co. Wicklow
demolition of existing single storey shed and garage to rear, construction of new part single storey part storey and a half extension containing 2 dormer windows to rear, removal of existing septic tank and new replacement proprietary effluent treatment system and all associated site works
Sparrows Den , Johnstown North , Arklow
construction of a bungalow with garage and car port, new entrance and access driveway, new treatment system and percolation area to current EPA standards and all ancillary site works
Johnstown South , Arklow , Co. W icklow
period of 10 years for a proposed solar farm and BESS (battery energy storage system) development which will consist of the construction of PV panels mounted on metal frames, inverters, battery storage infrastructure (BESS units, and MV Stations), new access tracks, underground cabling, perimeter fencing with CCTV cameras and access gates, a temporary construction compound, a substation and all ancillary grid infrastructure and associated works. It is proposed to use the consented Ballymoney Solar Farm access point (Pl Ref: 19/627 and ABP Ref: 305289-19). The solar farm and BESS would be operational for 40 years. A Natura Impact Statement (NIS) will be submitted with this application
Townland of Ballymoney , Arklow , Co. Wicklow
construction of a bungalow with garage, a new entrance, a new treatment system and percolation area to current EPA standards and all ancillary site works
Johnstown South , Arklow , Co. Wicklow
the construction of a bungalow with garage, a new entrance, a new treatment system and percolation area to current EPA standards and all ancillary site works
Johnstown South , Arklow , Co Wicklow
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?