← Back to search

Avoca River Park , Arklow , Co. Wicklow

N/A

Planning application SI202102

Wicklow - Wicklow County Council

Proposed Development

development primarily comprises the demolition of existing structures on site and the provision of a substation compound along with associated and ancillary works and is described as follows: The existing structures on site to be demolished comprise 4 no. industrial commercial buildings, an associated hut/outbuilding, a gas enclosure, and a tank with bund wall. The remains of a previously demolished building, areas of hard standing, and existing surface treatments will also be removed as part of the site clearance works. The proposed substation compound is subdivided into two parts. The northern part of the compound will accommodate a two storey 110kV GIS substation building (with gross floor are of c. 1,377 sqm). The southern part of the compound will accommodate four transformers and a single storey client control building (with a gross floor area c. 416sqm) and associated underground services. Both parts of the substation compound will be enclosed within 2.6metre high security fencing. The overall compound will be enclosed with a property fence 1.4 metre height. The development includes access paths, landscaping, security fencing, provision of access roads, car parking within the GIS substation compound, provision of a rural supply electricity connection (connecting to existing electrical services to the east of the proposed substation compound ) for the GIS substation building, a unit substation, lightning masts, drainage and attenuation systems, services, and all associated construction works, and all ancillary works

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    22 Jan 2021

  2. Decision due

    18 Mar 2021

Application Details

Location
Avoca River Park , Arklow , Co. Wicklow
Applicant
N/A
Application Type
N/A
Planning Authority
Wicklow County Council

Timeline

Registration Date
22 January 2021
Status
PRE_VALIDATION
Decision
N/A
Decision Due
18 March 2021

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

154m
23320CONDITIONAL30 Mar 2023

for proposed change of use from industrial/warehouse to plastics recycling facility and associated works

Avoca River Park , Arklow , Co. Wicklow

205m
201247N/A8 Dec 2020

1. Demolition of existing ind building units totalling (C.2784.4m2) comprising of a c.7.1m high Overall Main Building (c.2460m2), a c.4.2m high Sub-station (c. 107.3m2), a c.3.6m high Guardhouse (c.106.2m2), a c.3.6m high East-Building (c.39.1m2), c.5m high Water Tank (c.56.8m2) &c.2.6m high Pump House Building (c.15.1m2), assoc works. 2. Dev of 3 no. Data Centre Buildings, ancillary offices & plant comprising of: Data Centre Building A, - a single storey Data Centre Building, with mezzanine 1st floor level offices (GFA c.10,564m2, building height c.13,658m & structures c.15,137m), made up of 2 no. Data Halls & loading areas with assoc 2 no. Dock Levellers & including 10 no. c.14m high flues, & adjacent 1 no. Standby Power Generation Compounds, consisting of 10 no. HV Diesel Generators &belly tanks (GFA c.530 m2), 1 no. storage fuel tank (GFA c.15m2). Data Centre Building B – a single storey data centre building with mezzanine 1st floor level offices (GFA c.18,508m2, building height c.13,658m &structures c.15,137m), made up of 4 no. Data Halls &loading areas with associated 2 no. Dock Levellers &including 20 no. c.14m high flues, &adjacent 2 no. Standby Power Generation Compounds, consisting of 20 no. HV diesel Generators &belly tanks (GFA c.1,060 m2), 2 no. storage fuel tanks (GFA c.30m2). Data Centre Building C – a single storey data centre building with mezzanine 1st floor level offices (GFA c.18,508m2, building height c.13,658m & structures c.15,137m), made up of 4 no. Data Halls & loading areas with associated 2 no. Dock Levellers &including 20 no. c.14m high flues, &adjacent 2 no. Standby Power Generation Compounds, consisting of 20 no. HV Diesel Generators & belly tanks (GFA c.1,060 m2), 2 no. storage fuel tanks (GFA c.30m2). 3. Upgrading of existing 110 kV Substation to comprise of Compound (c. 8539m2) consisting of 11 kV GIS Switch Room (GFA c.708m2), &4 no. External Transformers (GFA c.550m2), a grid connection, security fence & all assoc works & services. 4. Dev of 1 no. Fire Hydrant Pump Hse (GFA c.129m2) with Sprinkler Tank (c.49m2), 1 no. single storey Security Guard Hse (GFA c.48m2) &2 no. vehicular accesses, internal access rds & 224 no. surface car parking spaces. 5. An upgraded attenuation basin, a proposed ww treatment plant &polishing filter. 6. All assoc site services, with c.2.7m high palisade fence, landscaping, boundary & all assoc site development works above & below ground. An EIAR has been prepared in respect of the proposed dev

Avoca River Park , Shelton Abbey & Kilbride , Arklow

210m
201285CONDITIONAL15 Dec 2020

1. Demolition of existing ind building units totalling (C.2784.4m2) comprising of a c.7.1m high Overall Main Building (c.2460m2), a c.4.2m high Sub-station (c. 107.3m2), a c.3.6m high Guardhouse (c.106.2m2), a c.3.6m high East-Building (c.39.1m2), c.5m high Water Tank (c.56.8m2) &c.2.6m high Pump House Building (c.15.1m2), assoc works. 2. Dev of 3 no. Data Centre Buildings, ancillary offices & plant comprising of: Data Centre Building A, - a single storey Data Centre Building, with mezzanine 1st floor level offices (GFA c.10,564m2, building height c.13,658m & structures c.15,137m), made up of 2 no. Data Halls & loading areas with assoc 2 no. Dock Levellers & including 10 no. c.14m high flues, & adjacent 1 no. Standby Power Generation Compounds, consisting of 10 no. HV Diesel Generators &belly tanks (GFA c.530 m2), 1 no. storage fuel tank (GFA c.15m2). Data Centre Building B – a single storey data centre building with mezzanine 1st floor level offices (GFA c.18,508m2, building height c.13,658m &structures c.15,137m), made up of 4 no. Data Halls &loading areas with associated 2 no. Dock Levellers &including 20 no. c.14m high flues, &adjacent 2 no. Standby Power Generation Compounds, consisting of 20 no. HV diesel Generators &belly tanks (GFA c.1,060 m2), 2 no. storage fuel tanks (GFA c.30m2). Data Centre Building C – a single storey data centre building with mezzanine 1st floor level offices (GFA c.18,508m2, building height c.13,658m & structures c.15,137m), made up of 4 no. Data Halls & loading areas with associated 2 no. Dock Levellers &including 20 no. c.14m high flues, &adjacent 2 no. Standby Power Generation Compounds, consisting of 20 no. HV Diesel Generators & belly tanks (GFA c.1,060 m2), 2 no. storage fuel tanks (GFA c.30m2). 3. Upgrading of existing 110 kV Substation to comprise of Compound (c. 8539m2) consisting of 11 kV GIS Switch Room (GFA c.708m2), &4 no. External Transformers (GFA c.550m2), a grid connection, security fence & all assoc works & services. 4. Dev of 1 no. Fire Hydrant Pump Hse (GFA c.129m2) with Sprinkler Tank (c.49m2), 1 no. single storey Security Guard Hse (GFA c.48m2) &2 no. vehicular accesses, internal access rds & 224 no. surface car parking spaces. 5. An upgraded attenuation basin, a proposed ww treatment plant &polishing filter. 6. All assoc site services, with c.2.7m high palisade fence, landscaping, boundary & all assoc site development works above & below ground. An EIAR has been prepared in respect of the proposed dev

Avoca River Park , Shelton Abbey & Kilbride , Arklow

252m
201285CONDITIONAL15 Dec 2020

1. Demolition of existing ind building units totalling (C.2784.4m2) comprising of a c.7.1m high Overall Main Building (c.2460m2), a c.4.2m high Sub-station (c. 107.3m2), a c.3.6m high Guardhouse (c.106.2m2), a c.3.6m high East-Building (c.39.1m2), c.5m high Water Tank (c.56.8m2) &c.2.6m high Pump House Building (c.15.1m2), assoc works. 2. Dev of 3 no. Data Centre Buildings, ancillary offices & plant comprising of: Data Centre Building A, - a single storey Data Centre Building, with mezzanine 1st floor level offices (GFA c.10,564m2, building height c.13,658m & structures c.15,137m), made up of 2 no. Data Halls & loading areas with assoc 2 no. Dock Levellers & including 10 no. c.14m high flues, & adjacent 1 no. Standby Power Generation Compounds, consisting of 10 no. HV Diesel Generators &belly tanks (GFA c.530 m2), 1 no. storage fuel tank (GFA c.15m2). Data Centre Building B – a single storey data centre building with mezzanine 1st floor level offices (GFA c.18,508m2, building height c.13,658m &structures c.15,137m), made up of 4 no. Data Halls &loading areas with associated 2 no. Dock Levellers &including 20 no. c.14m high flues, &adjacent 2 no. Standby Power Generation Compounds, consisting of 20 no. HV diesel Generators &belly tanks (GFA c.1,060 m2), 2 no. storage fuel tanks (GFA c.30m2). Data Centre Building C – a single storey data centre building with mezzanine 1st floor level offices (GFA c.18,508m2, building height c.13,658m & structures c.15,137m), made up of 4 no. Data Halls & loading areas with associated 2 no. Dock Levellers &including 20 no. c.14m high flues, &adjacent 2 no. Standby Power Generation Compounds, consisting of 20 no. HV Diesel Generators & belly tanks (GFA c.1,060 m2), 2 no. storage fuel tanks (GFA c.30m2). 3. Upgrading of existing 110 kV Substation to comprise of Compound (c. 8539m2) consisting of 11 kV GIS Switch Room (GFA c.708m2), &4 no. External Transformers (GFA c.550m2), a grid connection, security fence & all assoc works & services. 4. Dev of 1 no. Fire Hydrant Pump Hse (GFA c.129m2) with Sprinkler Tank (c.49m2), 1 no. single storey Security Guard Hse (GFA c.48m2) &2 no. vehicular accesses, internal access rds & 224 no. surface car parking spaces. 5. An upgraded attenuation basin, a proposed ww treatment plant &polishing filter. 6. All assoc site services, with c.2.7m high palisade fence, landscaping, boundary & all assoc site development works above & below ground. An EIAR has been prepared in respect of the proposed dev

Avoca River Park , Shelton Abbey & Kilbride , Arklow

264m
18940CONDITIONAL20 Aug 2018

demolition of buildings & structures on site & construction of Data Storage Facility comprising 3 data storage buildings & all assoc site infrastructure: data storage facility 1 (6 Pod Data Centre) located to north of site served by 1 gas generator compound to south of Data Storage building including 5 flues & 2 bunded fuel tanks located to south east & south west of Data Storage building & powered by (-part grid / - part gas) with emergency diesel fuel backup. Data storage facility 2 (8 pod data centre) located to south of Data Storage Facility 1 served by 1 gas generator compound to the south of building incl 6 flues & 2 bunded fuel tanks located to south east & south west of Data Storage building & powered by (-part grid / -part gas) with emergency diesel fuel backup. Data storage 3 (8 pod data centre) located to south of site served by 1 diesel generator compound to north of building incl 8 flues & 2 bunded fuel tanks, located to north east & north west of Data Storage building & powered by grid. The dev will consist of upgrade of existing 100 kV substation to provide a Substation Compound comprising Gas Insulated Switchgear (GIS) equipment with 4 50 mega Volt Amp bays within a single storey MV building 10 lighting protection masts, 4 oil filled transformers, with c2.4m high palisade fence, provision of 1 single storey security guard house at primary access to data storage facilities, provision of 4 vehicular access points off Shelton Abbey (access rd) on western side (2 to serve Data Storage Facilities, 1 to serve GIS substation & 1 to serve MV building), internal access roads, surface level car parking, site services (foul & surface water drainage & water supply) incl 1 pump house with 3 water tanks to sough west, 1 attenuation pond to south east, waste water treatment plant to the west of Shelton Abbey (access road), landscaping, boundary & site dev works above & below ground. Accompany by EIAR

Avoca River Park , Shelton Abbey & Kilbride , Arklow

273m
2360416N/A16 Nov 2023

the installation of circa. 3,492sq.m array of solar photovoltaic (PV) panels on ground mounted frames on an agricultural plot within the existing complex, together with ducting, underground electrical cabling, and all associated site works The proposed development is within the curtilage of a protected structure (RPS No. 40-05) listed under the current Wicklow County Development Plan 2022-2028.

Shelton Abbey Open Prison , Arklow , Co. Wicklow

278m
2360383N/A27 Oct 2023

the installation of circa. 3,492sq.m array of solar photovoltaic (PV) panels on ground mounted frames on an agricultural plot within the existing Shelton Abbey Open Prison complex, together with ducting, underground electrical cabling, and all associated site works

Shelton Abbey Open Prison , Arklow , Co. Wicklow

286m
2360437CONDITIONAL22 Nov 2023

the installation of circa. 3,492sq.m array of solar photovoltaic (PV) panels on ground mounted frames on an agricultural plot within the existing Shelton Abbey Open Prison, together with ducting, underground electrical cabling, and all associated site works The proposed development is considered to be within the curtilage of a protected structure (RPS No. 40-05) listed under the current Wicklow County Development Plan 2022-2028. The proposed solar array installation will have no impact on the protected structure, located over 330.00 meters away from the proposed site.

Shelton Abbey Open Prison , Arklow , Co. Wicklow

293m
18914N/A10 Aug 2018

demolition of buildings & structures on site & construction of Data Storage Facility comprising 3 data storage buildings & all assoc site infrastructure: data storage facility 1 (6 Pod Data Centre) located to north of site served by 1 gas generator compound to south of Data Storage building including 5 flues & 2 bunded fuel tanks located to south east & south west of Data Storage building & powered by (-part grid / - part gas) with emergency diesel fuel backup. Data storage facility 2 (8 pod data centre) located to south of Data Storage Facility 1 served by 1 gas generator compound to the south of building incl 6 flues & 2 bunded fuel tanks located to south east & south west of Data Storage building & powered by (-part grid / -part gas) with emergency diesel fuel backup. Data storage 3 (8 pod data centre) located to south of site served by 1 diesel generator compound to north of building incl 8 flues & 2 bunded fuel tanks, located to north east & north west of Data Storage building & powered by grid. The dev will consist of upgrade of existing 100 kV substation to provide a Substation Compound comprising Gas Insulated Switchgear (GIS) equipment with 4 50 mega Volt Amp bays within a single storey MV building 10 lighting protection masts, 4 oil filled transformers, with c2.4m high palisade fence, provision of 1 single storey security guard house at primary access to data storage facilities, provision of 4 vehicular access points off Shelton Abbey (access rd) on western side (2 to serve Data Storage Facilities, 1 to serve GIS substation & 1 to serve MV building), internal access roads, surface level car parking, site services (foul & surface water drainage & water supply) incl 1 pump house with 3 water tanks to sough west, 1 attenuation pond to south east, waste water treatment plant to the west of Shelton Abbey (access road), landscaping, boundary & site dev works above & below ground. Accompany by EIAR

Avoca River Park , Shelton Abbey & Kilbride , Arklow

296m
2372CONDITIONAL27 Jan 2023

the proposed development occupies part of the site of (and will supersede) a previously permitted data centre development under Reg. Ref. 20/1285. The proposed development, for which a ten-year permission is sought, consists of the following: Demolition of the existing structures on site (industrial structures and outbuildings) and site clearance works; construction of 3 no. three storey information and communication technology (ICT) facility buildings, each with a gross floor area (GFA) of c. 16,206 sq.m (c. 48,618sq.m GFA in total), and with a parapet height of c. 19.5 metres; each of the 3 no. ICT buildings will accommodate ICT equipment rooms, mechanical equipment rooms, staff welfare facilities, ancillary office space, security rooms, storage, and loading bays; a customer compound, a power trunk building, a transformer compound and a water tank compound area are provided to the north of the ICT facility buildings; the development includes the extension of the existing road and serving the existing industrial park to access the subject site, with gated access points to the proposed ICT facility development to be provided off this roadway; construction of internal road network and circulation areas, footpaths, provision of 124 no. car parking spaces and motorcycle and cycle parking spaces; landscaping and planting, boundary treatments, lighting, security fencing, and all associated site works including underground foul and storm water drainage network, attenuation and percolation areas, and utility cable (including connections to the substation permitted under ABP Ref. 310090-21, resulting in the partial culverting of an existing drainage ditch), on an application site area measuring c. 9.69 hectares. An Environmental Impact Assessment Report (EIAR) has been prepared and will be submitted to the Planning Authority with the planning application

Site located at Avoca River Park , Arklow , Co. Wicklow

The submission window has closed

Observations on this application closed on Thursday 25 February 2021, five weeks after it was received. The authority cannot accept a late submission.

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?