Solar farmsDecisionCarlow
Carlow County Council grants permission for 91.2-hectare solar farm at Grangeford Old and Friarstown, Co. Carlow
22 August 2024 · Permission.ie Planning Wire · from the Carlow County Council planning register · published 1 September 2026
Carlow County Council granted permission on 22 August 2024 for a 91.2-hectare solar farm at Grangeford Old and Friarstown, an application first lodged on 14 December 2023.
Key facts
- Reference
- 2360297
- Planning authority
- Carlow County Council
- Location
- Grangeford Old and Friarstown, Co. Carlow, R93 PX51
- Received
- 14 December 2023
- Application type
- PERMISSION
- Site area
- 91.2 hectares
- Permission sought
- 10 years
- Operational life
- 40 years
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision date
- 22 August 2024
In context
It is one of 2 solar farm applications Carlow County Council has received in the past twelve months, against 333 nationally. Of the 572 such applications decided by councils in the past three years, 92% were granted.
What happens next
The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 22 August 2024. If no appeal is lodged, the council’s decision stands and a final grant issues. The applicant sought a 10-year permission, which sets how long they have to start the development.
The development description, as lodged
Verbatim from the Carlow County Council register. This is the source for every figure in the story above.
10-year permission. The development will consist of the construction of (i) a Solar PV development comprising photovoltaic panels laid out in arrays over a total development site area of ca. 91.2ha, (ii) the construction of a 38kV substation building ((6.1m (h) x 20.9 (l) and 7.3 (w)) and associated compound area, a transformer unit (ca. 6m x ca. 3.6m) and associated bund, (iii) 352 number Battery Energy Storage System units comprising 22 modules (ca. 21.9m x ca.5.2m) each with 16 number cabinet units within each module and (iv) all ancillary development including 15 number transformer integrated units (ca. 10.5m x ca.2.7m), 12 number inverter units (ca. 6.0m x ca.2.4m), 7 number CCTV cameras mounted on 4m high poles, a 3m high acoustic barrier, with berm and fencing, perimeter security fencing, site access, site egress and all ancillary works and services. The development will have a 40-year operational lifetime. Permission currently exists for a PV development on ca/65.6ha of the site (Planning Permission Ref No. 21/23) that will be superseded by this application if approved
Cite this story
Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.
Source: Permission.ie analysis of the national planning register, "Carlow County Council grants permission for 91.2-hectare solar farm at Grangeford Old and Friarstown, Co. Carlow", 22 August 2024. https://www.permission.ie/news/carlow-county-council/2360297
<p>Source: <a href="https://www.permission.ie/news/carlow-county-council/2360297">Carlow County Council grants permission for 91.2-hectare solar farm at Grangeford Old and Friarstown, Co. Carlow</a>, Permission.ie analysis of the national planning register, 22 August 2024.</p>
Map, site boundary, timeline and nearby applications for 2360297.
All solar farms applicationsThe full register view, with a map and decision statistics.
Get stories like this the day they are lodged
A county watch emails you every new application in Carlow the week it appears.
Set up alerts