Solar farmsDecisionCarlow
Carlow County Council refuses permission for 63 MW solar farm at Rathrush Emlicon and Bendinstown, Ballon, Co. Carlow
31 July 2025 · Permission.ie Planning Wire · from the Carlow County Council planning register · published 1 September 2026
Carlow County Council refused permission on 31 July 2025 for a 63 MW solar farm at Rathrush Emlicon and Bendinstown, Ballon, an application first lodged on 17 September 2024.
Key facts
- Reference
- 2460295
- Planning authority
- Carlow County Council
- Location
- Rathrush Emlicon and Bendinstown, Ballon, Co. Carlow
- Received
- 17 September 2024
- Application type
- PERMISSION
- Site area
- 118.9 hectares
- Stated capacity
- 63 MW
- Operational life
- 35 years
- Status
- APPLICATION FINALISED
- Decision
- REFUSED
- Decision date
- 31 July 2025
- Appeal
- 323496-25 · CONDITIONAL
In context
It is one of 2 solar farm applications Carlow County Council has received in the past twelve months, against 335 nationally. Of the 573 such applications decided by councils in the past three years, 92% were granted.
What happens next
The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 31 July 2025. If no appeal is lodged, the council’s decision stands and a final grant issues.
The development description, as lodged
Verbatim from the Carlow County Council register. This is the source for every figure in the story above.
for a ten-year planning permission for a renewable energy development comprising the construction of a c. 63MW solar farm of 118.9ha and associated works in the Townlands of Rathrush, Emlicon and Bendinstown, Co Carlow. The proposed development will consist of: • A c. 63MW solar farm comprising ground mounted solar photovoltaic panels. • 15 No. Invertor Combiner Kiosk /Transformers and hardstands. • 1 No. Ring Main Unit. • 2 No. spare parts storage containers. • Provision of site access tracks and upgrading of existing tracks. • Underground cabling within the solar farm site, in private lands and under the L7111, L7114, L7115 local roads to connect the solar farm field parcels, and to connect the solar farm to the permitted Garreenleen Substation. • 3 No. temporary construction compounds. • Demolition of derelict agricultural building and disused silage storage structure. • Upgrading and widening works at Site entrances. • All ancillary development including such as an up to 2.4m high stock proof fence, CCTV and drainage infrastructure. This application is seeking a ten-year permission and a 35-year operational period from the date of overall commissioning of the solar farm. This application is accompanied by a Natura Impact Statement (NIS)
Cite this story
Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.
Source: Permission.ie analysis of the national planning register, "Carlow County Council refuses permission for 63 MW solar farm at Rathrush Emlicon and Bendinstown, Ballon, Co. Carlow", 31 July 2025. https://www.permission.ie/news/carlow-county-council/2460295
<p>Source: <a href="https://www.permission.ie/news/carlow-county-council/2460295">Carlow County Council refuses permission for 63 MW solar farm at Rathrush Emlicon and Bendinstown, Ballon, Co. Carlow</a>, Permission.ie analysis of the national planning register, 31 July 2025.</p>
Map, site boundary, timeline and nearby applications for 2460295.
All solar farms applicationsThe full register view, with a map and decision statistics.
Get stories like this the day they are lodged
A county watch emails you every new application in Carlow the week it appears.
Set up alerts