Carlow County Council granted permission on 31 October 2025 for a 57-hectare solar farm at in, an application first lodged on 22 May 2025.
Key facts
- Reference
- 2560137
- Planning authority
- Carlow County Council
- Location
- In the townlands of Ballybannon Ballybar Lower Ballybar Upper Ballycarney, Ballyloo Cloghna Linkardstown and Park, in County Carlow.
- Received
- 22 May 2025
- Application type
- PERMISSION
- Site area
- 57 hectares
- Permission sought
- 10 years
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision date
- 31 October 2025
In context
It is one of 2 solar farm applications Carlow County Council has received in the past twelve months, against 335 nationally. Of the 573 such applications decided by councils in the past three years, 92% were granted.
What happens next
The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 31 October 2025. If no appeal is lodged, the council’s decision stands and a final grant issues. The applicant sought a 10-year permission, which sets how long they have to start the development.
The development description, as lodged
Verbatim from the Carlow County Council register. This is the source for every figure in the story above.
A 10 Year Planning Permission for a solar farm with a total area of circa 57 hectares. The solar farm will consist of solar panels on ground mounted frames, 8 no. single storey electrical inverter/transformer stations, 2 no. single storey spare parts containers, 1 no. Ring Main Unit, 3 no. weather stations, underground electrical ducting and cabling within the development site, private lands and within the L4038, L8185, R448, L3051, L3052 and L3050 public roads to connect solar farm field parcels, security fencing, CCTV, access tracks, 5 no. watercourse/drain deck crossings and 2 no. horizontal directional drill crossings (under M9 motorway and the Dublin - Waterford railway), temporary construction compounds, landscaping and all associated ancillary development and drainage works. Construction and operational access will be via 2 no. existing entrances from the R448 and L1010. Sections of the proposed underground electrical cabling will traverse the solar farms proposed under Carlow County Council References 24/60043 and 24/60205, but will not alter infrastructure proposed under these applications. The operational lifespan of the solar farm will be 40 years and planning permission is requested for this duration. A Natura Impact Statement (NIS) has been prepared and will be submitted to the Planning Authority with the application.
Cite this story
Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.
Source: Permission.ie analysis of the national planning register, "Carlow County Council grants permission for 57-hectare solar farm at in, Co. Carlow", 31 October 2025. https://www.permission.ie/news/carlow-county-council/2560137
<p>Source: <a href="https://www.permission.ie/news/carlow-county-council/2560137">Carlow County Council grants permission for 57-hectare solar farm at in, Co. Carlow</a>, Permission.ie analysis of the national planning register, 31 October 2025.</p>
Map, site boundary, timeline and nearby applications for 2560137.
All solar farms applicationsThe full register view, with a map and decision statistics.
Get stories like this the day they are lodged
A county watch emails you every new application in Carlow the week it appears.
Set up alerts