Solar farmsDecisionCarlow
Carlow County Council refuses permission for 3.8-hectare solar farm at Gilbertstown and Bendinstown, Ireland, Co. Carlow
25 February 2026 · Permission.ie Planning Wire · from the Carlow County Council planning register · published 1 September 2026
Carlow County Council refused permission on 25 February 2026 for a 3.8-hectare solar farm at Gilbertstown and Bendinstown, Ireland, an application first lodged on 9 June 2025.
Key facts
- Reference
- 2560155
- Planning authority
- Carlow County Council
- Location
- Within the townlands of Gilbertstown and Bendinstown, Co. Carlow, Ireland
- Received
- 9 June 2025
- Application type
- PERMISSION
- Site area
- 3.8 hectares
- Permission sought
- 10 years
- Status
- APPEALED
- Decision
- REFUSED
- Decision date
- 25 February 2026
- Appeal
- PL-501034-CW-26
In context
It is one of 2 solar farm applications Carlow County Council has received in the past twelve months, against 337 nationally. Of the 573 such applications decided by councils in the past three years, 92% were granted.
What happens next
The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 25 February 2026. If no appeal is lodged, the council’s decision stands and a final grant issues. The applicant sought a 10-year permission, which sets how long they have to start the development.
The development description, as lodged
Verbatim from the Carlow County Council register. This is the source for every figure in the story above.
a 10 year permission for a Battery Energy Storage system. The proposed development will comprise of the following; A Battery Energy Storage System with associated infrastructure including a new internal access road, approximately 50 metres in length to the permitted Garreenleen Solar Farm (Planning Ref. 22163); An approximately 90 metre 33kV double circuit underground cable grid connection to the permitted Bendinstown 110kV Substation (Planning Ref. ABP–313139), to be installed in an excavated trench including underground ducting; Modular office and welfare buildings; Six steel storage containers and all associated site development and reinstatement works. A Natura Impact Statement (NIS) has been prepared and is included with this planning application.
Cite this story
Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.
Source: Permission.ie analysis of the national planning register, "Carlow County Council refuses permission for 3.8-hectare solar farm at Gilbertstown and Bendinstown, Ireland, Co. Carlow", 25 February 2026. https://www.permission.ie/news/carlow-county-council/2560155
<p>Source: <a href="https://www.permission.ie/news/carlow-county-council/2560155">Carlow County Council refuses permission for 3.8-hectare solar farm at Gilbertstown and Bendinstown, Ireland, Co. Carlow</a>, Permission.ie analysis of the national planning register, 25 February 2026.</p>
Map, site boundary, timeline and nearby applications for 2560155.
All solar farms applicationsThe full register view, with a map and decision statistics.
Get stories like this the day they are lodged
A county watch emails you every new application in Carlow the week it appears.
Set up alerts