Solar farmsLodgedClare
109-hectare solar farm proposed at Ballycar Lislea Killulla, Co. Clare
23 December 2024 · Permission.ie Planning Wire · from the Clare County Council planning register · published 1 September 2026
An applicant lodged plans with Clare County Council on 23 December 2024 for a 109-hectare solar farm at Ballycar Lislea Killulla. The application seeks an operational life of 40 years.
Key facts
- Reference
- 24435
- Planning authority
- Clare County Council
- Location
- Ballycar Lislea Killulla, Mogullaan & Crossagh Rathlaheen South, Culleen Drumline & Ballycasey Beg Co Clare
- Received
- 23 December 2024
- Application type
- PERMISSION
- Site area
- 109 hectares
- Operational life
- 40 years
- Status
- WITHDRAWN
- Submissions until
- 4 February 2025 (closed)
- Council file
- View on the Clare County Council planning portal
In context
It is one of 8 solar farm applications Clare County Council has received in the past twelve months, against 333 nationally. Of the 572 such applications decided by councils in the past three years, 92% were granted.
What happens next
The five-week window for public submissions has closed. The council normally decides within eight weeks of the application being lodged, unless it requests further information, which stops the clock.
The development description, as lodged
Verbatim from the Clare County Council register. This is the source for every figure in the story above.
for the development at this site at the townlands of Ballycar, lislea, Kilulla, Mogullaan and Crossagh, Rathlaheen South, Culleen, Drumline and Ballycasey Beg, Co Clare The development will consist of an application for a 10-year development phase followed by a 40-year operational lifespan for a solar farm on a site encompassing approximately 109 hectares. The proposed development includes the installation of ground-mounted solar photovoltaic (PV) panels on steel frames accross the site. The project will incorporate 256 inverters arranged in a series string configuration, supported by 24 electrical skid hardstands that will house transformer units and a ring main unit facility. The development also entails the construction of a transformer compound to facilitate a connection to the existing 110kV Drumline Substation. An internal network cable will be installed to enable an under-the-fence connection from the on-site transformer compound to the adjacent substation. The transformer compound will include an Independent Power Producer (IPP) building, a 110kV transformer, and an 18 metre-high lightning monopole mast. Approximately 8.6 Kilometres of new and upgraded internal access tracks will be developed to provide connectivity within the site. Six new site entrances are proposed, including modification to existing junctions to accommodate construction access and the delivery of abnormal loads. These access points will connnect to Local Roads (L3166, Ballycar Road L3174 and L3136) and the Regional Road R458. All new entrances will link directly to the public road network. This application seeks approval for all associated site development and ancillary works necessary to support the successful delivery and operation of the proposed solar farm. A Natura Impact Statement will also be submitted to the Planning Authority with this application
Cite this story
Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.
Source: Permission.ie analysis of the national planning register, "109-hectare solar farm proposed at Ballycar Lislea Killulla, Co. Clare", 23 December 2024. https://www.permission.ie/news/clare-county-council/24435
<p>Source: <a href="https://www.permission.ie/news/clare-county-council/24435">109-hectare solar farm proposed at Ballycar Lislea Killulla, Co. Clare</a>, Permission.ie analysis of the national planning register, 23 December 2024.</p>
Map, site boundary, timeline and nearby applications for 24435.
All solar farms applicationsThe full register view, with a map and decision statistics.
Get stories like this the day they are lodged
A county watch emails you every new application in Clare the week it appears.
Set up alerts